Iowa Great Lakes Sanitary Dist. v. Travelers Cas. & Sur. Co. of Am.

913 F.3d 760
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 11, 2019
Docket17-2732
StatusPublished
Cited by5 cases

This text of 913 F.3d 760 (Iowa Great Lakes Sanitary Dist. v. Travelers Cas. & Sur. Co. of Am.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Great Lakes Sanitary Dist. v. Travelers Cas. & Sur. Co. of Am., 913 F.3d 760 (8th Cir. 2019).

Opinion

LOKEN, Circuit Judge.

This is a diversity action removed from state court in December 2015. Iowa Great Lakes Sanitary District (IGLSD) alleges that an Ultraviolet Wastewater Disinfectant System (UV System) installed at IGLSD's Dickinson County Wastewater Treatment Facility "has consistently failed to function in any working capacity." IGLSD asserts a claim against Travelers Casualty and Surety Company of America (Travelers) under the Performance and Maintenance Bond issued to guarantee performance by the project's contractor, and breach of warranty claims against the UV System vendor, Evoqua Water Technologies, f/k/a Siemens Water Technologies (Evoqua). IGLSD appeals the District Court's 1 grant of summary judgment dismissing these claims. Reviewing the grant of summary judgment de novo , we affirm. Bruce Martin Const., Inc. v. CTB, Inc. , 735 F.3d 750 , 753 (8th Cir. 2013) (standard of review).

I. Background.

In 2007, IGLSD contracted with McHan Construction, Inc., to complete a *762 $14,593,000 addition to the Wastewater Treatment Facility, including installation of a UV System. McHan procured a Performance and Maintenance Bond from Travelers fully guaranteeing McHan's "faithful performance of the contract" with IGLSD. After the contract was in effect, McHan purchased a vertical open channel UV System from Evoqua for $132,000. The purchase agreement included an express two-year limited warranty "that the equipment or material ... is free from defects in workmanship and materials." The two-year warranty period would commence on the date the equipment successfully completed a required sixty-day performance test.

After McHan defaulted in late 2009, Travelers and IGLSD entered into a "Take Over Agreement" whereby Travelers agreed "to complete the Project pursuant to the terms of the Contract," with its Performance and Maintenance Bond "in full force and effect." Start-up problems plagued installation of the UV System, causing further delays in completing the contract. When the installed UV equipment eventually completed the sixty-day performance testing, IGLSD's project engineer, James Rasmussen, advised the parties on November 8, 2011: "With the latest Performance Test on Module No. 2 the UV disinfection equipment is now Substantially Completed and the project can be finally accepted. The Warranty Period for the equipment will be considered to be started on November 1, 2011."

Substantial Completion did not end the parties' problems with the UV System, which IGLSD alleges was often nonoperational. In June 2012, an electrical fire damaged one of the modules; it was returned to Evoqua's factory for repairs. In May 2013, IGLSD complained there was soot in the system, it was malfunctioning, and warranty issues had not been addressed. In a July 2013 letter to Travelers, Engineer Rasmussen noted the equipment warranty would expire November 1, 2013, expressed concern that Siemens and Evoqua were not supporting the equipment, summarized numerous items needing repair, and asked Travelers to "develop a plan to repair/replace the equipment by the end of the Warranty date."

Alerted to these complaints, Evoqua sent a technician to assess the equipment in September 2013. Based on his report, in April 2014 Evoqua proposed that the two UV modules undergo a substantial rehab, with IGLSD and Evoqua splitting the $75,000.00 cost. In a May 12, 2014 letter, Engineer Rasmussen responded that IGLSD "does not wish to go any further to repair the failed equipment" and requested that the UV System "be removed from the project and the cost of the initial purchase of the equipment be refunded." This lawsuit followed.

In its summary judgment Order, the district court noted that Chief Magistrate Judge C.J. Williams had entered an order that "prohibited IGLSD from proffering expert testimony as a sanction for IGLSD's failure to comply with the court's deadlines." The district court also ruled that IGLSD had violated Local Rule 56(b) by failing to respond to the Statements of Undisputed Material Facts submitted by Evoqua and Travelers in support of their summary judgment motions, and therefore those facts "are deemed to have been admitted by IGLSD." IGLSD does not challenge these significant procedural rulings on appeal.

II. The Breach of Warranty Claim Against Evoqua.

IGLSD claims that Evoqua breached its limited two-year express warranty that the UV System equipment "is free from defects in workmanship and materials."

*763 A breach of express warranty claim under Iowa law "requires proof of a product defect as defined in Products Restatement section 2." Cummings v. Deere & Co. , 589 F.Supp.2d 1108 , 1118 n.22 (S.D. Iowa 2008), quoting Wright v. Brooke Group, Ltd. , 652 N.W.2d 159 , 182 (Iowa 2002). Summary judgment is mandated "against a party who fails to make a showing sufficient to establish the existence of an element essential to that party's case, and on which that party will bear the burden of proof at trial." Celotex Corp. v. Catrett , 477 U.S. 317 , 322, 106 S.Ct. 2548 , 91 L.Ed.2d 265 (1986). "Evidence of a defect is an indispensable element of any express or implied warranty claim." Coop. Power Ass'n v. Westinghouse Elec. Corp. , 60 F.3d 1336 , 1344-45 (8th Cir. 1995).

In cases involving "complicated technical and scientific issues ... expert testimony is required to submit the issue of a product defect under Iowa law." Cummings , 589 F.Supp.2d at 1118 . "Whether expert testimony is required ultimately depends on whether it is a fact issue upon which the jury needs assistance to reach an intelligent or correct decision." Reed v. Chrysler Corp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
913 F.3d 760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-great-lakes-sanitary-dist-v-travelers-cas-sur-co-of-am-ca8-2019.