Lesikar Construction Company v. Acoustex, Inc.

509 S.W.2d 877, 1974 Tex. App. LEXIS 2202
CourtCourt of Appeals of Texas
DecidedApril 26, 1974
Docket17509
StatusPublished
Cited by29 cases

This text of 509 S.W.2d 877 (Lesikar Construction Company v. Acoustex, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lesikar Construction Company v. Acoustex, Inc., 509 S.W.2d 877, 1974 Tex. App. LEXIS 2202 (Tex. Ct. App. 1974).

Opinion

OPINION

BREWSTER, Justice.

, This suit was brought by a subcontractor, Acoustex, Inc., against a general contractor, Lesikar Construction Company, seeking to recover the balance claimed to be owed the subcontractor for work it did in constructing the W. E. Boswell High School at Saginaw, Texas. The general contractor’s bonding company, General Insurance Company of America, was also named as a defendant and it was sued on the general contractor’s bond that was posted under Art. 5160, Vernon’s Ann.Civ. St. The plaintiff was awarded a judgment for $4,378.73 against the two defendants and this appeal is from that decree. This sum represented the balance due on the contract price plus accrued interest.

The defendants in their first three points of error contend that the trial court erred in rendering the judgment for plaintiff because (1) the jury found that the plaintiff had failed to comply with a condition precedent in the contract that required him to furnish the general contractor an affidavit showing that all bills for labor and materials had been paid in full before he was entitled to payment; (2) the jury found that Lesikar Construction Company did not waive its right to require plaintiff to furnish the bills paid affidavit required by the contract; and (3) the court disregarded the jury findings that Lesikar did not waive its right to require plaintiff to furnish such bills paid affidavit as required by the contract.

We overrule defendants’ first three points of error.

By the contract in question executed on July 5, 1968, Acoustex, Inc., a subcontractor, agreed to complete the furnishing and installation of all gypsum drywall partitions and ceilings and acoustical treatment to be used in the school building involved. Section 4 of the contract between the sub *879 contractor and general contractor contained the following provisions:

“SECTION FOUR: Contractor agrees to pay Subcontractor for the performance of work hereunder the sum of Eleven Thousand One Hundred Twenty and no/100 ($11,120.00) . . . and to make payments on account thereof in accordance with the provisions that follow:
“c. Upon the completion of said work or furnishing said materials, in accordance with said plans and specifications, to furnish to Contractor evidence in the form of an affidavit that all bills both for labor and materials have been paid in full, and upon the presentation of such affidavit the Contractor shall pay to the Subcontractor the balance due under this Contract.”

The jury found in answer to Issue No. 1 that Acoustex, Inc., had not furnished to Lesikar an affidavit that all bills for labor and materials had been paid in full. The verdict (Issue No. 2) also established that Lesikar did not waive its right to have Acoustex, Inc. furnish it an affidavit that all bills for labor and materials had been paid in full.

The architect on. the job certified that the school building project was fully completed on January 11, 1969. The architect at that time accepted all work done on the job, including that done by the plaintiff, Acoustex, Inc. The general contractor, Lesikar, was paid his contract price in full by the owner for doing the school job on February 20, 1969. After completing his contract the subcontractor did not furnish Lesikar an affidavit stating that all his bills for labor and materials had been paid. The price for which plaintiff had contracted to do the work and furnish the materials was $11,120.00. The first mention defendant ever made to plaintiff of plaintiff’s failure to furnish defendant a bills paid affidavit was while this lawsuit was being prepared for trial. The case was not tried until almost four years after the contract was completed. There was no evidence in the record that anyone has ever tried to fix a lien or make a claim against the general contractor, his bondsman, or against the owner for unpaid labor or material bills incurred by plaintiff in performing the contract. All of the facts recited in this paragraph are undisputed.

Marion Yancey, the plaintiff’s general manager, testified at the trial that the amount that had been paid to plaintiff by the general contractor was $7,647.23 leaving an unpaid balance owed to plaintiff on the contract price of $3,472.77. Yancey also testified that plaintiff had paid all of its bills for labor and materials that were furnished in connection with this job, and that no one had ever asked defendant to pay any of such bills.

The witness, Bob Land, was general manager of plaintiff at the time this job was done. He was employed elsewhere at the time of the trial. He also testified that the plaintiff had paid all the bills for labor and materials that it furnished in connection with this job. The testimony of both Land and Yancey was given under oath to the effect that these bills for plaintiff’s labor and materials were paid.

We deem the evidence in the case to establish as a matter of law that the plaintiff has in fact prior to trial fully paid all such bills. The testimony of the witnesses, Marion Yancey and Bob Land, to that effect is undisputed. They were both, at different times, general managers of the plaintiff, but their uncontradicted testimony is clear and positive and there are no circumstances in evidence tending to discredit or impeach such testimony. In addition there is no testimony that any claims or liens were sought to be fixed by anyone against the contractor, his bondsmen or the owner arising out of labor done or materials furnished by plaintiff under this contract. Under these circumstances we hold that the evidence conclusively establishes the fact that all such bills for labor and material have been paid in full. See 62 Tex. *880 Jur.2d 451-452, Witnesses, Sec. 373, and McGuire v. City of Dallas, 141 Tex. 170, 170 S.W.2d 722 (Tex.Com.App., 1943). In addition, Mr. Lesikar, president of defendant corporation, had the means and opportunity to dispute this testimony while he was testifying, but failed to do so.

The same questions presented to us here under defendants’ first three points of error were presented to the Supreme Court in the case of Citizens Nat. Bank v. Texas & P. Ry. Co., 136 Tex. 333, 150 S.W.2d 1003 (1941). There Locke entered into a construction contract with the railroad and performed it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanders Oil & Gas, Ltd. v. Big Lake Kay Constr., Inc.
554 S.W.3d 79 (Court of Appeals of Texas, 2018)
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104 (Texas Supreme Court, 2010)
Redland Insurance Co. v. Southwest Stainless, L.P.
181 S.W.3d 509 (Court of Appeals of Texas, 2005)
Bencon Management & General Contracting, Inc. v. Boyer, Inc.
178 S.W.3d 198 (Court of Appeals of Texas, 2005)
Jenkins v. Eckerd Corp.
913 So. 2d 43 (District Court of Appeal of Florida, 2005)
City of Houston v. Allco, Inc.
Court of Appeals of Texas, 2004
Beard Family Partnership v. Commercial Indemnity Insurance Co.
116 S.W.3d 839 (Court of Appeals of Texas, 2003)
Ramex Construction Co. v. Tamcon Services Inc.
29 S.W.3d 135 (Court of Appeals of Texas, 2000)
ACME BRICK, DIV. OF JUSTIN INDUSTRIES, INC. v. Temple Associates, Inc.
816 S.W.2d 440 (Court of Appeals of Texas, 1991)
Mar-Len of Louisiana, Inc. v. Gorman-Rupp Co.
795 S.W.2d 880 (Court of Appeals of Texas, 1990)
American National Insurance Co. v. Gifford-Hill & Co.
673 S.W.2d 915 (Court of Appeals of Texas, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
509 S.W.2d 877, 1974 Tex. App. LEXIS 2202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lesikar-construction-company-v-acoustex-inc-texapp-1974.