South Texas Electric Cooperative v. Dresser-Rand Co.

575 F.3d 504, 2009 U.S. App. LEXIS 15261, 2009 WL 1961732
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 9, 2009
Docket08-40715
StatusPublished
Cited by15 cases

This text of 575 F.3d 504 (South Texas Electric Cooperative v. Dresser-Rand Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Texas Electric Cooperative v. Dresser-Rand Co., 575 F.3d 504, 2009 U.S. App. LEXIS 15261, 2009 WL 1961732 (5th Cir. 2009).

Opinion

HAYNES, Circuit Judge:

In this appeal, Dresser-Rand asks us to overturn a jury verdict holding it liable for repair costs incurred by South Texas Elec *506 trie Cooperative (STEC) as a result of Dresser’s failure to fulfill warranty obligations. Finding the evidence fully supportive of the jury’s verdict, we affirm.

I.

This appeal arises from a contract dispute between STEC, a utility serving southeastern Texas, and Dresser, a manufacturer of industrial products, including steam turbines. In 2001, STEC contracted with Dresser to purchase a steam-powered turbine for use at one of STEC’s power plants. Under the contract, Dresser promised to manufacture and install the steam turbine free of defects in materials and workmanship; it also promised to repair defects under an express warranty.

Dresser’s repair obligations included two specific notice provisions. Under paragraph 13.03(A), Dresser was required to correct any defects with the turbine after receiving written notice from STEC. Under paragraph 13.03(B), if Dresser failed to take action to correct the defects, STEC could remedy the defects itself after providing Dresser with ten days written notice.

The contract also contained a two-part procedure for resolving disputes. Under paragraph 9.04, if STEC believed it had a claim against Dresser, STEC was required to submit its claim to a contract engineer. Under paragraph 15.01, the parties agreed that after referring the dispute to the contract engineer, they would give the engineer sufficient time to issue a decision— and then, if necessary, refer the matter to the senior management of their respective organizations. The contract explicitly made a decision by the engineer a “condition precedent” to filing suit. However, the parties were not bound to accept the decision of the contract engineer.

STEC experienced problems with the turbine immediately following its installation. At its initial start-up in August 2003, the turbine vibrated at such high levels that it required immediate shut-down. The evidence at trial showed that STEC informed Dresser of these problems early on and that, indeed, Dresser was aware of the root cause of the vibration issues as early as the design/build phase of the project. Despite this knowledge, Dresser did little over the next two years to remedy the problem. While it sent STEC an action plan and proposed that STEC install new bearing pads, the vibration issue remained.

In 2003, STEC hired Bentley-Nevada to collect vibration data from the turbine in order to determine the cause of the vibration. Dresser was aware that Bentley-Nevada was conducting these tests and agreed to cover the costs. The vibration nevertheless continued. Nearly two years later, in early 2005, STEC wrote to Dresser that it “had conducted several additional vibration studies with multiple consultants.” Finally, in November 2005, STEC definitively diagnosed the cause of the turbine’s vibration and, without providing Dresser further written notice, employed outside consultants to do the repair work.

STEC sued Dresser in March 2006, seeking damages in the amounts that STEC paid its outside contractors. A jury found for STEC on all of its claims. The jury found that Dresser was liable for breach of contract and breach of express warranty. On Dresser’s defenses, the jury found that STEC substantially complied with the contract’s notice provisions and was excused from complying with its dispute resolution provisions. The jury found damages of $706,406.46.

The district court entered judgment on the verdict and denied Dresser’s motion for judgment as a matter of law. This appeal followed.

*507 II.

Much is left unchallenged in this appeal. Dresser does not contest that STEC informed it of the steam turbine’s vibration problems, that those problems arose from a cause within the scope of Dresser’s warranty obligations, or that it failed to fulfill those obligations. Rather, Dresser’s contentions relate only to the adequacy of STEC’s notice under paragraph 13.03(B) of the parties’ contract and the propriety of the jury’s determination that STEC was excused from invoking the contract’s dispute resolution procedures prior to filing suit. With respect to paragraph 13.03(B), Dresser raises a host of related contentions:

• that the district court erred by submitting the issue of substantial compliance to the jury;
• that STEC failed to obtain a jury finding on substantial compliance with notice under paragraph 13.03(B); and
• that the evidence was legally insufficient to support a finding of substantial compliance.

We address Dresser’s challenges in turn, adhering to our well-established standard for reviewing a district court’s denial of a motion for judgment as a matter of law. 1

Dresser contends that the district court erred by submitting to the jury the issue of STEC’s substantial compliance with the notice required by paragraph 13.03(B); it asserts that contractual notice provisions like these demand strict compliance.

Dresser’s arguments are contrary to well-established Texas law, recognizing the applicability of the doctrine of substantial compliance to contractual notice provisions. See Barbier v. Barry, 345 S.W.2d 557, 562 (Tex.Civ.App.-Dallas 1961, no writ) (holding notice that failed to adhere to technical requirements of the contract effective and in substantial compliance with the contract); see also Tex. JJtils. Elec. Co. v. Aetna Cas. & Sur. Co., 786 S.W.2d 792, 794 (Tex.App.-Dallas 1990, writ, denied) (rejecting argument that notice provision in bond must be strictly complied with). Dresser conceded as much at oral argument.

In support of its strict compliance argument, Dresser relies on this circuit’s decision in PYCA Industries, Inc. v. Harrison County Waste Water Management District, 177 F.3d 351 (5th Cir.1999). In that case, this court held that an owner’s receipt of actual notice of a claim did not relieve the contractor from strictly complying with the contract’s formal protest procedures, which required that it articulate with reasonable certainty and on a timely basis the nature of its claims. Id. at 370-71: But PYCA did not establish a per se rule, id. at 371 & 371 n. 30, and the facts here are distinguishable from that case on two significant grounds. First, the contract in PYCA explicitly made a failure to strictly comply with the written notice provision a basis for waiver. Id. at 369-70.

*508 The contract here does not. Second, in PYCA,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
575 F.3d 504, 2009 U.S. App. LEXIS 15261, 2009 WL 1961732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-texas-electric-cooperative-v-dresser-rand-co-ca5-2009.