James Construction Group, LLC, Primoris Services Corporation v. Westlake Chemical Corporation

CourtCourt of Appeals of Texas
DecidedDecember 17, 2019
Docket14-18-00083-CV
StatusPublished

This text of James Construction Group, LLC, Primoris Services Corporation v. Westlake Chemical Corporation (James Construction Group, LLC, Primoris Services Corporation v. Westlake Chemical Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Construction Group, LLC, Primoris Services Corporation v. Westlake Chemical Corporation, (Tex. Ct. App. 2019).

Opinion

Affirmed as Modified, and Majority and Concurring and Dissenting Opinions filed December 17, 2019.

In The

Fourteenth Court of Appeals

NO. 14-18-00083-CV

JAMES CONSTRUCTION GROUP, LLC AND PRIMORIS SERVICES CORPORATION, Appellants/Cross-Appellees V.

WESTLAKE CHEMICAL CORPORATION, Appellee/Cross-Appellant

On Appeal from the 334th District Court Harris County, Texas Trial Court Cause No. 2014-72717

MAJORITY OPINION

James Construction Group, LLC (“James”), Primoris Services Corporation (“Primoris”), and Westlake Chemical Corporation (“Chemical”) appeal a judgment adjudicating their respective contract claims, which arose out of a construction agreement between Chemical and James. Following a jury trial, the trial court signed a judgment awarding Chemical $1,157,019.50 in breach-of-contract damages against James and Primoris, jointly and severally, and $2,923,600.50 in attorney’s fees against Primoris only. The judgment also awards James $1,270,962.89 in breach-of-contract damages against Chemical on James’s counterclaim. Each party raises multiple issues on appeal. For the reasons explained below, we modify the judgment and affirm the judgment as modified.

General Background

Chemical and James signed a construction contract providing for James to perform over $500 million in civil and mechanical construction work at a chlor- alkali chemical plant owned by Westlake Vinyls Company, L.P. (“Vinyls”). Although Chemical signed the contract in its own name, Vinyls authorized Chemical to sign it on Vinyls’s behalf, and the jury found that Chemical was acting as Vinyls’s agent in entering the contractual relationship. In a separate agreement (the “Guaranty”), James’s parent company, Primoris, unconditionally guaranteed James’s performance under the construction contract.

Following various disputes during the project Chemical filed this lawsuit, and the parties asserted breach-of-contract claims against each other. We first summarize the general nature of the claims at issue and then detail additional pertinent facts in connection with their related issues.

A. Summary of Chemical’s claims

Chemical’s claims against James mainly involve allegations that James breached contract provisions requiring it to perform work safely and to compensate Chemical for remedial or termination costs resulting from unsafe work. Chemical contends that due to James’s safety violations Chemical intervened and terminated some or all of James’s scope of work in accordance with Chemical’s contract rights. Chemical sought to recover damages allegedly incurred in exercising those rights and hiring others to complete the job.

2 Chemical’s claims are grounded on two key contract provisions. First, paragraph 17.2, entitled “Inspection and Intervention,” provides that Chemical may “intervene in any appropriate way” if, in its reasonable opinion, James performs its contractual duties in an unsafe manner. In that instance, Chemical has the right to require James to take immediate remedial action to Chemical’s satisfaction. James is solely accountable for all costs associated with such intervention and remedial action, whether those costs are incurred by Chemical, James, or any third party.

Another section, paragraph 21, applies to “Termination and Substitute Performance.” Specifically, paragraph 21.3 enumerates Chemical’s right to terminate the contract for James’s default, including for serious safety violations. Paragraph 21.3 sets forth the relevant contractual sequence of events as follows: if Chemical determines in its reasonable opinion that James has “serious safety violations,” then Chemical may so notify James. Upon notification, James must begin to remedy the defect cited within a certain period. If Chemical is not reasonably satisfied with the pace or quality of the remediation effort, Chemical must notify James of that fact and may elect to terminate the contract or a portion of the work by providing notice to that effect. After providing notice, Chemical has the right to take unrestricted possession of the work or portion terminated and pay for its completion. Any extra cost in excess of the contract price incurred by Chemical in completing the terminated work is at James’s expense.

Chemical also asserts a claim under the contract’s indemnity provision, paragraph 19.1. Chemical avers that James’s employee died while performing work under the contract, that Chemical incurred expenses in defending a wrongful-death claim asserted by the employee’s family, and that James breached paragraph 19.1 by failing to indemnify Chemical for its costs resulting from the claim.

3 At trial, Chemical contended its damages resulting from James’s breaches exceeded $8.5 million.

Finally, Chemical sued Primoris for breach of the Guaranty, contending that Primoris was liable for all contract damages owed by James.

B. Summary of James’s claims

James’s counterclaims also rest in part on paragraph 21.3. James alleges that Chemical breached paragraph 21.3 by (1) improperly terminating James’s work because Chemical’s grounds for termination were unreasonable, and (2) failing to provide the notice paragraph 21.3 requires.

James also contends that Chemical violated paragraph 26 of the contract, which is entitled “Waiver of Consequential Damages” and states among other things that neither party shall be liable to the other for any “consequential, incidental, indirect or punitive damages of any kind or character,” and “no claim shall be made” by either party against the other for such damages regardless of the legal theory supporting the claim. According to James, all of Chemical’s asserted contract damages are consequential in nature and barred by paragraph 26.

C. Summary of the jury findings and judgment

Following a multi-week trial, a jury made the following relevant findings:

1. Chemical entered into the construction contract in its own name but with authority to act on behalf and for the benefit of Vinyls. The jury also found that James was estopped from denying that Chemical entered into the construction contract with Vinyls’s authority and on Vinyls’s behalf.

2. James failed to comply with paragraph 17.2, the “intervention” provision. The jury awarded Chemical $1,054,251.81 as a result of this breach.

4 3. James failed to comply with paragraph 21.3, the “termination” provision; and Chemical substantially complied with that paragraph’s notice provisions. The jury awarded Chemical $1,054,251.81 as a result of this breach.1 Due to the jury’s findings in Chemical’s favor, it did not answer a series of questions on James’s counterclaims under paragraph 21.3. 4. James failed to comply with paragraph 19.1, the “indemnity” provision. The jury awarded Chemical $102,767.69 as a result of this breach.

5. Chemical incurred $2,923,600.50 in reasonable and necessary attorney’s fees through trial and would incur up to an additional $450,000 in attorney’s fees in the event of appeal. 6. Chemical failed to comply with paragraph 26, the waiver of consequential damages provision. The damages awarded for this breach were divided into two categories. The jury awarded James $238,778.26 for attorney’s fees incurred in defending against “chlorine costs” asserted by Chemical.2 Additionally, the jury awarded James a total of $1,032,184.63 for attorney’s fees incurred through trial (plus $62,500 in appellate fees) in defending against “consequential damages other than chlorine costs” asserted by Chemical.

After several post-verdict motions, the trial court signed an amended judgment incorporating the above findings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alyeska Pipeline Service Co. v. Wilderness Society
421 U.S. 240 (Supreme Court, 1975)
Brooks v. Hollaar
297 P.3d 125 (Alaska Supreme Court, 2013)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Nissan Motor Co. Ltd. v. Armstrong
145 S.W.3d 131 (Texas Supreme Court, 2004)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
Cooper Tire & Rubber Co. v. Mendez
204 S.W.3d 797 (Texas Supreme Court, 2006)
Varner v. Cardenas
218 S.W.3d 68 (Texas Supreme Court, 2007)
Fortis Benefits v. Cantu
234 S.W.3d 642 (Texas Supreme Court, 2007)
PAJ, Inc. v. Hanover Insurance Co.
243 S.W.3d 630 (Texas Supreme Court, 2008)
Ulico Casualty Co. v. Allied Pilots Ass'n
262 S.W.3d 773 (Texas Supreme Court, 2008)
Columbia Medical Center of Las Colinas, Inc. v. Hogue
271 S.W.3d 238 (Texas Supreme Court, 2008)
Regal Finance Co. v. Tex Star Motors, Inc.
355 S.W.3d 595 (Texas Supreme Court, 2010)
Material Partnerships, Inc. v. Ventura
102 S.W.3d 252 (Court of Appeals of Texas, 2003)
McMahan v. Greenwood
108 S.W.3d 467 (Court of Appeals of Texas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
James Construction Group, LLC, Primoris Services Corporation v. Westlake Chemical Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-construction-group-llc-primoris-services-corporation-v-westlake-texapp-2019.