Mar-Len of Louisiana, Inc. v. Gorman-Rupp Co.

795 S.W.2d 880, 1990 Tex. App. LEXIS 2437, 1990 WL 146668
CourtCourt of Appeals of Texas
DecidedAugust 30, 1990
Docket09-89-063 CV
StatusPublished
Cited by9 cases

This text of 795 S.W.2d 880 (Mar-Len of Louisiana, Inc. v. Gorman-Rupp Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mar-Len of Louisiana, Inc. v. Gorman-Rupp Co., 795 S.W.2d 880, 1990 Tex. App. LEXIS 2437, 1990 WL 146668 (Tex. Ct. App. 1990).

Opinion

OPINION

WALKER, Chief Justice.

This is a suit by appellee, The Gorman-Rupp Company (hereinafter referred to as “Gorman-Rupp” or appellee) against appellant, Mar-Len of Louisiana, Inc. (hereinafter referred to as “Mar-Len” or appellant) for breach of contract. The breach of contract claim is in connection with a purchase order submitted by Mar-Len to Gor-man-Rupp. The purchase order is in re *882 gard to the manufacture and supply of certain goods, including pumps and control devices, which were to be utilized in the construction of five (5) transfer stations for a waste treatment facility for the City of DeRidder, Louisiana. Mar-Len was the general contractor on a portion of the waste treatment project.

As reflected by plaintiffs first amended original petition, Gorman-Rupp also sued Safeco Insurance Company of America (hereinafter referred to as “Safeco”) in connection with the payment and/or performance bonds which were required to be procured by Mar-Len in connection with the project. Mar-Len and Safeco responded to Gorman-Rupp’s allegations by asserting a general denial together with certain affirmative defenses. In particular, Mar-Len and Safeco affirmatively asserted that all conditions precedent to plaintiffs recovery had not occurred or had not been satisfied.

On October 10, 1988, this action proceeded to trial before a jury in the 136th Judicial District Court, Honorable Jack King presiding. At the close of plaintiff’s evidence, Mar-Len and Safeco asserted their motions for directed verdict. The trial court took such motions for directed verdict under consideration for a later ruling. Upon the close of all the evidence, Mar-Len and Safeco re-urged their motions for directed verdict. The trial court again took same under consideration. On October 13, 1988, the jury returned a ten (10)-two (2) verdict in favor of appellee.

Thereafter, Mar-Len and Safeco filed with the trial court their motion for judgment non obstante veredicto, and motion for judgment. The judgment was signed by the trial court on November 29, 1988. As reflected by said judgment, the trial court permitted Gorman-Rupp to recover the sum of $62,500.00 plus pre-judgment interest in the amount of $18,270.55 against Mar-Len. The trial court further found that Gorman-Rupp should take nothing against Safeco. Thereafter, on December 20, 1988, Mar-Len timely filed with the trial court its motion for new trial. After a hearing was held upon said motion, the trial court denied same.

The appellant has duly perfected this appeal to this Court, and, for reasons set out in appellant’s brief, appellant seeks a reversal of the judgment of the trial court or in the alternative, a remand for a new trial.

A detailed statement of the facts will add clarity to our opinion in this ease. Mar-Len is a general construction contractor. In March of 1983, Mar-Len entered into a contract with the City of DeRidder, Louisiana under the terms of which Mar-Len was to construct a municipal waste water treatment system. The project was EPA regulated. The project consisted of five (5) separate lift stations, which were designed to transfer waste products.

In conjunction with the execution of the original construction contract, Mar-Len contracted with Safeco to provide a payment bond and a performance bond. The City of DeRidder, Louisiana retained the engineering firm of Meyer & Associates, Inc., to monitor the construction of the project.

Gorman-Rupp is a Mansfield, Ohio, corporation which engages in the manufacture and sale of commercial pumps and related equipment, for the utilization of same in municipal sanitary systems. When an authorized representative of Gorman-Rupp discovers the existence of a potential municipal project, the representative obtains all of the necessary plans and specifications for that project and forwards same to Gor-man-Rupp. Gorman-Rupp would review the plans and specifications, and thereafter make a determination as to the appropriateness of its equipment. More specifically, the plans would first be reviewed by Gor-man-Rupp’s sales department. The sales department of Gorman-Rupp would then transfer the plans and specifications to its mechanical and electrical engineering section.

The engineering section of Gorman-Rupp would design the proper piping, valves and other mechanical design features of the system. Thereafter, the electrical engineering section would review the electrical requirements of the project. Gor-man-Rupp would then prepare a list of materials, determine all applicable costs, *883 and prepare a bid price for the project. If Gorman-Rupp was unsuccessful in obtaining the contract, all costs associated with the submission with the bid would not be compensable.

In regard to the pump package made the basis of this action, Gorman-Rupp followed the above submission process. In connection with the DeRidder project, Pump & Power of Houston, Texas, was Gorman-Rupp’s authorized representative. In regard to the DeRidder project, Gorman-Rupp through Pump & Power of Houston quoted an original bid price of $349,590.00.

Mar-Len, however, had received a lower bid from a company known as Crown Pump. Accordingly, Mar-Len originally entered into a purchase order with Crown Pump, for an amount approximately $160,-000.00 less than the Gorman-Rupp bid. The purchase between Mar-Len and Crown Pump was conditional in the sense that certain “submittals” of the system had to be approved by Meyer & Associates, Inc., the project engineer.

Prior to the actual inclusion of the pump package into the project, the project engineer must approve the various performance specifications (known as “submittals”) of the pumps. This is accomplished by the pump manufacturer and general contractor submitting to the project engineer submit-tals of the mechanical, electrical and other related specifications of the pumps. There would be no liability on the part of Mar-Len in regard to the proposed orders, if the city’s engineer refused to accept the sub-mittals of the pump. This express condition was written on the Crown Pump purchase order.

In May of 1983, Meyer & Associates, Inc. began receiving submittals in regard to Crown Pump. Meyer & Associates, Inc. did not, however, approve the various sub-mittals of Crown Pump. In August of 1983, the project engineer issued a final rejection of the Crown Pump submittals, formally disapproving of same. As a result of the project engineer disapproving the use of Crown Pumps, Mar-Len was placed in a position of having to seek a new supplier.

Thereafter Mar-Len contacted Gorman-Rupp for the purpose of receiving a revised bid for the pump package. By letter dated July 22, 1983, Gorman-Rupp, through Pump & Power of Houston informed Mar-Len that Gorman-Rupp had reduced its price to $315,871.00. The new bid of Gor-man-Rupp was reduced from its former bid in that Gorman-Rupp had devised a new, special control system.

Based upon Gorman-Rupp’s revised bid, Mar-Len issued its company’s purchase order to Pump & Power of Houston for the purchase of the pump package. Upon the face of the purchase order are the words, “pending submittal approval”.

Robert Ehalt, the representative of Gor-man-Rupp who was in charge of the project, testified in person at the time of trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
795 S.W.2d 880, 1990 Tex. App. LEXIS 2437, 1990 WL 146668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mar-len-of-louisiana-inc-v-gorman-rupp-co-texapp-1990.