Schwarz-Jordan, Inc. of Houston v. Delisle Construction Co.

569 S.W.2d 878, 21 Tex. Sup. Ct. J. 509, 1978 Tex. LEXIS 375
CourtTexas Supreme Court
DecidedJuly 19, 1978
DocketB-7486
StatusPublished
Cited by53 cases

This text of 569 S.W.2d 878 (Schwarz-Jordan, Inc. of Houston v. Delisle Construction Co.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schwarz-Jordan, Inc. of Houston v. Delisle Construction Co., 569 S.W.2d 878, 21 Tex. Sup. Ct. J. 509, 1978 Tex. LEXIS 375 (Tex. 1978).

Opinion

POPE, Justice.

This is a breach of contract action. Schwarz-Jordan, Incorporated, sued Delisle Construction Company for failure to pay monies due under a written subcontracting agreement. In a non-jury trial, the trial court rendered judgment for plaintiff Schwarz-Jordan. The court of civil appeals reversed and rendered judgment that Schwarz-Jordan take nothing. 561 S.W.2d 619. We reverse the judgment of the court of civil appeals and remand the cause to that court.

Delisle Construction Company had contracted with the City of Houston to remodel the concourse and flight station interiors at Houston Intercontinental Airport. Delisle subcontracted the installation of a new type of metal ceiling to Schwarz-Jordan under a standard subcontracting agreement. The subcontract incorporated the provisions of the prime contract by reference. Since the metal ceiling concept was new, both the prime contract and the subcontract required the construction of a model (mock-up) and its approval by the city engineer before further work on the metal ceiling could proceed.

Schwarz-Jordan constructed the mock-up at the airport. The city engineer then disapproved the mock-up and eliminated the metal ceiling from the construction plans. The basis for the engineer’s disapproval was the concept itself and not that Schwarz-Jor-dan’s work was unsatisfactory. The City of Houston paid the prime contractor, Delisle, an amount undisclosed by the record for the preparation, installation and removal of the mock-up at the airport. Delisle paid Schwarz-Jordan nothing for its work on the project, and Schwarz-Jordan brought this suit for breach of contract.

The court of civil appeals interpreted the portion of the mock-up provision emphasized below, as it was incorporated into the subcontracting agreement, as a condition precedent to any liability on the subcontracting agreement:

Mock-up : Contractor shall install suspension members for curved section and 10 feet of straight section in one concourse *880 and install the pans. Upon approval of the installation work may proceed per schedule.

The prime contract provided (emphasis added):

Mock-up: Contractor shall install suspension members for curved section and 10 feet of straight section in one concourse and install the pans. Upon approval of the installation work may proceed per schedule.
* * * * * *
Whenever the words “approved,” “satisfactory,” ... or similar words or phrases are used, it shall be assumed that the word “Engineer” follows the verb as the object of the clause, such as “approved by the Engineer.”
******
The Engineer may direct that alterations, deviations, additions or omissions be made to or from the work as indicated or required.
******
15. Changes and Extra Work — Within the general scope and sort of work or construction covered by the contract, the Engineer may, without notice to the surety on the Contractor’s bond, make such changes in .the design, materials or machinery or the plans for installation or construction or other quality of character of the work or materials required as he may find necessary to the accomplishment of the general purpose of the work or construction contracted for. .
If any change so ordered results in an increase or decrease of cost to the Contractor an addition to or deduction from the contract price on account thereof shall be computed by the Engineer as provided in Section 16 of this specification. .
16. Compensation for Extra Work; Allowance or Deduction on Account of Changes —Extra work ordered in writing by the Engineer as provided in Section 15 of this specification shall be paid for on the basis of the Engineer’s computation of the aggregate of labor, material, truck hire and equipment rental entering into the performance thereof as follows: .
Deduction from or addition to the contract price for any lump sum bid item on account of a change order, ordered as provided in Section 15 of this specification, shall be computed by the Engineer as follows:
******
An allowance shall be made in favor of the Contractor for the work done under such change order, computed in the same manner hereinabove provided for the computation of compensation for extra work. The Engineer shall then determine, based on the Contractor’s breakdown between labor and material, equipment rent and other direct cost items, the cost to the Contractor if he were to have done the work omitted under the change order. To the sum so determined, the Engineer shall add 15 percent to cover the estimated overhead and profit to have been made by the Contractor on the omitted work. The Engineer will then determine the difference between the allowance so computed for the additional work done under the change order and deduction so computed on account of the work omitted under the change order, and the difference so determined shall be either added to or deducted from the lump sum bid, as the case may be. ******

The subcontracting agreement’s Article X provided, in part:

ARTICLE X
In addition to the foregoing provisions the parties also agree: That the Subcontractor shall: .
(1) Be bound to the Contractor on the terms of the Contractor Documents and this Agreement, and assume toward the Contractor all the obligations and responsibilities that the Contractor, by those documents, assumes toward the Owner, as applicable to this Subcontract. .
*881 (13) Make any and all changes or deviations from the original plans and specifications without nullifying the original contract when specifically ordered to do so in writing by the Contractor. The Subcontractor prior to the commencement of this revised work, shall submit promptly to the Contractor written copies of the cost or credit proposal for such revised work in a manner consistent with the Contract Documents.
⅜ sfc * ⅜ ⅜ *
That the Contractor shall—
(19) Be bound to the Subcontractor by all the obligations that the Owner assumes to the Contractor under the Contract Documents and by all the provisions thereof affording remedies and redress to the Contractor from the Owner insofar as applicable to this Subcontract.
* * * * * *

We do not agree with the holding that the mock-up provision of the contract was a condition precedent to defendant’s obligation. The clear language of the contract directs the contractor and subcontractor to build a mock-up. The engineer’s approval was not, however, a condition precedent to the obligation to build a mock-up.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BCC Merchant Solutions, Inc. v. Jet Pay, LLC
129 F. Supp. 3d 440 (N.D. Texas, 2015)
Arbor Windsor Court, LTD v. Weekley Homes, LP
Court of Appeals of Texas, 2015
Janos Farkas v. Second Congress, Ltd.
Court of Appeals of Texas, 2014
FAULKNERUSA, LP v. Alaron Supply Co., Inc.
322 S.W.3d 357 (Court of Appeals of Texas, 2010)
City of Houston v. Allco, Inc.
Court of Appeals of Texas, 2004
Robbins v. Payne
55 S.W.3d 740 (Court of Appeals of Texas, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
569 S.W.2d 878, 21 Tex. Sup. Ct. J. 509, 1978 Tex. LEXIS 375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schwarz-jordan-inc-of-houston-v-delisle-construction-co-tex-1978.