FAULKNERUSA, LP v. Alaron Supply Co., Inc.

322 S.W.3d 357, 2010 Tex. App. LEXIS 5965, 2010 WL 2929460
CourtCourt of Appeals of Texas
DecidedJuly 28, 2010
Docket08-09-00119-CV
StatusPublished
Cited by5 cases

This text of 322 S.W.3d 357 (FAULKNERUSA, LP v. Alaron Supply Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FAULKNERUSA, LP v. Alaron Supply Co., Inc., 322 S.W.3d 357, 2010 Tex. App. LEXIS 5965, 2010 WL 2929460 (Tex. Ct. App. 2010).

Opinion

OPINION

GUADALUPE RIVERA, Justice.

FaulknerUSA, L.P., FaulknerUSA GP, Inc. (Faulkner), and Safeco Insurance Company of America (Safeco), appeal the trial court’s summary judgment in favor of Alaron Supply Company, Inc. (Alaron). We reverse.

BACKGROUND

Faulkner, as general contractor, entered into three contracts with Alaron, as subcontractor, to provide food service equipment, laundry service and equipment, and parking control system service and equipment at the San Antonio Convention Center Hotel. The food contract was for $2,306,000, the laundry contract was for $1,837,420, and the parking contract was for $349,037. Each contract required a 100 percent surety bond, which Safeco provided, and that 10 percent would be withheld as retainage. Further, each contract contained the following provision:

Condition Precedent to Payment by Owner to FaulknerUSA for the Subcontract Work is a condition precedent to Subcontractor’s payment by FaulknerU-SA. Subcontractor is entitled to payment only for that portion of the Subcontract Work for which FaulknerUSA has been paid by Owner. Subcontractor expressly assumes the risk of nonpayment by Owner. The Subcontract Amount includes compensation to Subcontractor for the assumption of this risk. This provision establishes a condition precedent, and it shall not be construed merely as a Time of Payment Clause.

Later, Alaron sued Faulkner and Safeco for suit on sworn account, breach of contract, and suit on payment bond. According to Alaron’s first amended petition, it fully or substantially performed under the three contracts and Faulkner and Safeco owed $790,577.74 for the services rendered. After verified denials were filed, Alaron moved for summary judgment. Although Faulkner and Safeco responded that Alaron’s summary judgment motion should be denied, they did not also move for summary judgment. The trial court granted summary judgment in favor of Alaron.

DISCUSSION

Faulkner raises nine issues on appeal. The first contends that the trial court erred by failing to sustain its objections to an affidavit attached to Alaron’s motion for summary judgment, the second alleges that the trial court failed to rule that an affidavit attached to Faulkner’s response to Alaron’s motion for summary judgment was sufficient to raise a fact issue, the third asserts that payment by the owner was a condition precedent to any payment to Alaron, the fourth contests whether there was a question of fact as to whether payment of retainage was due, the fifth challenges Alaron’s sworn account pleadings, the sixth contends that Faulkner filed a proper sworn denial to Alaron’s suit on sworn account, the seventh alleges that timely notice of bond was not given, the eighth asserts that Safeco was not subject to summary judgment, and the ninth contests whether judgment was proper against Faulkner “GP.” Finding merit in Faulkner’s third issue, we need not address the remaining claims. See Tex. R.App. P. 47.1 (“The court of appeals must hand down a written opinion that is as brief as practicable but that addresses ev *359 ery issue raised and necessary to final disposition of the appeal.”).

Standard of Review

Alaron moved for summary judgment on “traditional” grounds. Therefore, Alaron bore the burden to show that there was no genuine issue of material fact and that it was entitled to judgment as a matter of law. Tex. R. Crv. P. 166a(c). On appeal, we review Alaron’s motion and the evidence de novo, taking as true all evidence favorable to the nonmovant — Faulkner— and indulging every reasonable inference and resolving any doubts in Faulkner’s favor. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex.2005); Nixon v. Mr. Prop. Mgmt. Co., Inc., 690 S.W.2d 546, 548-49 (Tex.1985).

We further review de novo the construction of an unambiguous contract. MCI Tel. Corp. v. Tex. Utils. Elec. Co., 995 S.W.2d 647, 650-51 (Tex.1999). In so doing, our primary concern is the true intentions of the parties as expressed in the instrument. Coker v. Coker, 650 S.W.2d 391, 393 (Tex.1983). In determining the parties’ intent, we examine the entire agreement and give effect to all provisions such that none are rendered meaningless. Id. We further apply the pertinent rules of construction, look to the plain meaning of the contract language, and enforce the contract as written. Vincent v. Bank of Am., N.A., 109 S.W.3d 856, 867 (Tex.App.-Dallas 2003, pet. denied).

Condition Precedent

Condition precedents are events that must be performed before a right accrues to enforce a contract. Hohenberg Bros. Co. v. George E. Gibbons & Co., 537 S.W.2d 1, 3 (Tex.1976). No particular words are necessary for the existence of a condition, but such terms as “if,” “provided that,” “on condition that,” or some other phrase that conditions performance, usually connote an intent for a condition rather than a promise. Id.; Gulf Const. Co., Inc. v. Self, 676 S.W.2d 624, 627 (Tex.App.-Corpus Christi 1984, writ ref'd n.r.e.). As forfeitures are not favored, finding a condition precedent should be avoided if another reasonable reading of the contract is possible. Criswell v. European Crossroads Shopping Ctr., Ltd., 792 S.W.2d 945, 948 (Tex.1990); Schwarz-Jordan, Inc. of Houston v. Delisle Const. Co., 569 S.W.2d 878, 881 (Tex.1978).

The parties cite Gulf as controlling authority. In that case, the contract provided that:

When the owner or his representative advances or pays the general contractor, the general contractor shall be hable for and obligated to pay the sub-contractor up to the amount or percentage recognized and approved for payment by the owner’s representative less the retain-age required under the terms of the prime contract. Under no circumstances shall the general contractor be obligated or required to advance or make payments to the sub-contractor until the funds have been advanced or paid by the owner or his representative to the general contractor.

Gulf, 676 S.W.2d at 627. The provision was not labeled “condition precedent,” nor did it contain terms such as “if,” “provide that,” “on condition that,” or some other phrase that would condition performance. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
322 S.W.3d 357, 2010 Tex. App. LEXIS 5965, 2010 WL 2929460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/faulknerusa-lp-v-alaron-supply-co-inc-texapp-2010.