City of Houston v. Allco, Inc.

CourtCourt of Appeals of Texas
DecidedJuly 1, 2004
Docket01-02-00812-CV
StatusPublished

This text of City of Houston v. Allco, Inc. (City of Houston v. Allco, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Houston v. Allco, Inc., (Tex. Ct. App. 2004).

Opinion

Opinion issued July 1, 2004






In The

Court of Appeals

For The

First District of Texas





NO. 01-02-00812-CV





CITY OF HOUSTON, Appellant


V.


ALLCO, INC., Appellee





On Appeal from the 80th District Court

Harris County, Texas

Trial Court Cause No. 99-56191





MEMORANDUM OPINION

          Allco, Inc. sued the City of Houston (“the City”) for breach of contract, alleging that the City failed to pay for “extra work” that Allco performed in conjunction with a contract between Allco and the City. The City appeals the trial court’s judgment awarding Allco damages. In deciding the City’s five issues raised on appeal, we determine (1) whether the City’s immunity from suit has been waived; (2) whether the trial court correctly interpreted the contract at issue; (3) whether the trial court’s findings of fact support its judgment; and (4) whether factually sufficient evidence exists to support the amount of damages awarded to Allco.

          We affirm.

Factual and Procedural Background

          In 1994, Allco entered into a contract (“the contract”) with the City to provide “sewer rehabilitation services.” In several of its provisions, the contract specified that Allco would not be entitled to compensation for “extra work,” i.e., work that was not already approved under the contract, unless Allco notified the City that extra work was required and received prior, written approval for the extra work from the City’s engineer.

          Unrelated to the contract, residents of the Kennedy Heights region of Houston filed a toxic tort suit in 1995 against Chevron U.S.A., Inc. in Texas state court. The residents alleged that Chevron contaminated the soil in their neighborhoods with petroleum by-products. On July 10, 1995, the state court ordered the City to notify counsel for the tort plaintiffs of any sewer work being performed in the Kennedy Heights subdivision. That order was dissolved by further order on August 11, 1995.

          In June 1996, Allco was conducting sewer rehabilitation work for the City under work order number 38 in the Crestmont subdivision—an area included within the scope of the Kennedy Heights tort litigation. At that time, the City had never informed Allco of the Kennedy Heights litigation filed in state court. Also unknown to Allco, another lawsuit had been filed by Kennedy Heights residents in Houston federal court. On June 18, 1996, at 5:10 p.m., a federal marshal served Allco with a temporary restraining order signed by the federal judge in the second Kennedy Heights suit. The order required Allco to cease further excavation work on the Crestmont project. At that time, Allco had 70 to 80 open trenches in the Crestmont subdivision. Allco faxed a copy of the temporary restraining order to the City’s public works department.

          The following day, Allco entered into an agreed order, which required Allco to establish a plan to “rope off” the construction site and areas where the excavated dirt was stored and to provide the tort plaintiffs access to monitor the site. Allco hauled the dirt, which had been excavated prior to Allco’s receiving the restraining order, to an esplanade where the dirt was covered and a fence was erected.

          Although the contract permitted Allco to use the excavated dirt to refill the trenches it had dug, Allco believed that the language of the agreed order, requiring it to secure the dirt, prevented Allco from using that dirt to refill the trenches. As a result, Allco purchased and trucked in new dirt—an expense it would not have normally incurred under the contract. During these activities, city inspectors were present at the work site.

          On June 21, 1996, an assistant city attorney sent Allco a letter, demanding that Allco dispose of the “excess excavated material and debris.” If Allco did not do as requested, the assistant city attorney warned Allco that it would be in breach of contract. After receiving the letter, Allco paid for the transport and disposal of the excavated dirt. As part of the disposal process, Allco hired a company to test the excavated dirt to determine whether it was contaminated. By the end of July 1996, the excavated dirt had been trucked to a landfill for disposal at Allco’s expense.

          On February 10, 1998, Allco submitted a claim to the City for the extra work associated with the Kennedy Heights litigation. The city attorney denied the claim six months later. In April 1999, Allco sought approval for the extra work from the City’s engineer. The City did not respond. Allco then filed suit against the City, alleging breach of contract and seeking $89,306.43 in damages for the extra work it had completed in the Crestmont subdivision. Following a bench trial, the trial court signed a judgment in favor of Allco. The court found that Allco was entitled only to part of the damages it requested. The trial court awarded the company $27,468.88, plus interest, representing the costs associated with testing, moving, and ultimately disposing of the excavated dirt.

          The trial court also signed findings of fact and conclusions of law in support of its judgment. In its findings, the trial court acknowledged that the contract “provides for extra work and sets out the procedure to be followed in carrying out extra work.” The court also found that the contract “requires notice, relative to extra costs, and Allco used this format in complying with the claim filing process.” Relatedly, in finding of fact 23, the trial court found,

Allco concedes that no prior[,] written approval was sought and obtained for changes[.] Allco’s testifying representative stated he would not have gone on to the job in the first instance without a plan and approval from the City had the City informed Allco about the Kennedy Heights litigation[.] Had the City of Houston informed Allco of this litigation, Allco would have sought written authorization[.]

          Relating to the costs that Allco incurred in testing and disposing of the excavated dirt, finding of fact 18(D) reads, in part, as follows:

While the [agreed order] did not specifically require Allco to truck the soil, Allco responded reasonably to that order in thinking that it was necessary to remove the soil[.] Additionally, Allco reasonably responded to the Assistant City Attorney’s directive not to breach the contract and to “remove excess excavated material and debris immediately.”

          

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Centex Corp. v. Dalton
840 S.W.2d 952 (Texas Supreme Court, 1992)
Westech Engineering, Inc. v. Clearwater Constructors, Inc.
835 S.W.2d 190 (Court of Appeals of Texas, 1992)
Ames v. Great Southern Bank
672 S.W.2d 447 (Texas Supreme Court, 1984)
Ortiz v. Jones
917 S.W.2d 770 (Texas Supreme Court, 1996)
Hohenberg Bros. Co. v. George E. Gibbons & Co.
537 S.W.2d 1 (Texas Supreme Court, 1976)
Dewhurst v. Gulf Marine Institute of Technology
55 S.W.3d 91 (Court of Appeals of Texas, 2001)
Sun Exploration and Production Co. v. Benton
728 S.W.2d 35 (Texas Supreme Court, 1987)
Lesikar Construction Company v. Acoustex, Inc.
509 S.W.2d 877 (Court of Appeals of Texas, 1974)
Bekins Moving & Storage Co. v. Williams
947 S.W.2d 568 (Court of Appeals of Texas, 1997)
Massachusetts Bond. & Ins. Co. v. Orkin Exterm. Co.
416 S.W.2d 396 (Texas Supreme Court, 1967)
Schwarz-Jordan, Inc. of Houston v. Delisle Construction Co.
569 S.W.2d 878 (Texas Supreme Court, 1978)
Vaughn v. DAP Financial Services, Inc.
982 S.W.2d 1 (Court of Appeals of Texas, 1997)
Cal-Tex Lumber Co., Inc. v. Owens Handle Co., Inc.
989 S.W.2d 802 (Court of Appeals of Texas, 1999)
Missouri State Life Ins. Co. v. Le Fevre
10 S.W.2d 267 (Court of Appeals of Texas, 1928)
Jones v. Gibbs
130 S.W.2d 265 (Texas Supreme Court, 1939)
Gardner v. Platt
68 S.W.2d 297 (Court of Appeals of Texas, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
City of Houston v. Allco, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-houston-v-allco-inc-texapp-2004.