FaulknerUSA, L.P., FaulknerUSA GP, Inc. and Safeco Insurance Company of America v. Alaron Supply Company, Inc.

Court of Appeals of Texas·Decided July 28, 2010·No. 08-09-00119-CV·Published

Opinion

COURT OF APPEALS

EIGHTH DISTRICT OF TEXAS

EL PASO, TEXAS

FAULKNERUSA, LP, FAULKNERUSA § GP, INC., AND SAFECO INSURANCE No. 08-09-00119-CV COMPANY OF AMERICA, § Appeal from the

Appellants, § 166th District Court

v. § of Bexar County, Texas

ALARON SUPPLY COMPANY, INC., § (TC#2008-CI-12096)

Appellee. §

OPINION

FaulknerUSA, L.P., FaulknerUSA GP, Inc. (Faulkner), and Safeco Insurance Company of America (Safeco), appeal the trial court’s summary judgment in favor of Alaron Supply Company, Inc. (Alaron). We reverse.

BACKGROUND

Faulkner, as general contractor, entered into three contracts with Alaron, as subcontractor, to provide food service equipment, laundry service and equipment, and parking control system service and equipment at the San Antonio Convention Center Hotel. The food contract was for $2,306,000, the laundry contract was for $1,837,420, and the parking contract was for $349,037. Each contract required a 100 percent surety bond, which Safeco provided, and that 10 percent would be withheld as retainage. Further, each contract contained the following provision:

Condition Precedent to Payment by Owner to FaulknerUSA for the Subcontract Work is a condition precedent to Subcontractor’s payment by FaulknerUSA.

Subcontractor is entitled to payment only for that portion of the Subcontract Work for which FaulknerUSA has been paid by Owner. Subcontractor expressly assumes the risk of nonpayment by Owner. The Subcontract Amount includes compensation to Subcontractor for the assumption of this risk. This provision establishes a condition precedent, and it shall not be construed merely as a Time of Payment Clause.

Later, Alaron sued Faulkner and Safeco for suit on sworn account, breach of contract, and suit on payment bond. According to Alaron’s first amended petition, it fully or substantially performed under the three contracts and Faulkner and Safeco owed $790,577.74 for the services rendered. After verified denials were filed, Alaron moved for summary judgment. Although Faulkner and Safeco responded that Alaron’s summary judgment motion should be denied, they did not also move for summary judgment. The trial court granted summary judgment in favor of Alaron.

DISCUSSION

Faulkner raises nine issues on appeal. The first contends that the trial court erred by failing to sustain its objections to an affidavit attached to Alaron’s motion for summary judgment, the second alleges that the trial court failed to rule that an affidavit attached to Faulkner’s response to Alaron’s motion for summary judgment was sufficient to raise a fact issue, the third asserts that payment by the owner was a condition precedent to any payment to Alaron, the fourth contests whether there was a question of fact as to whether payment of retainage was due, the fifth challenges Alaron’s sworn account pleadings, the sixth contends that Faulkner filed a proper sworn denial to Alaron’s suit on sworn account, the seventh alleges that timely notice of bond was not given, the eighth asserts that Safeco was not subject to summary judgment, and the ninth contests whether judgment was proper against Faulkner “GP.” Finding merit in Faulkner’s third issue, we need not address the remaining claims. See TEX . R. APP . P. 47.1 (“The court of appeals must hand down a written opinion that is as brief as practicable but that addresses every issue raised and necessary to final disposition of the appeal.”).

Standard of Review

Alaron moved for summary judgment on “traditional” grounds. Therefore, Alaron bore the burden to show that there was no genuine issue of material fact and that it was entitled to judgment as a matter of law. TEX . R. CIV . P. 166a(c). On appeal, we review Alaron’s motion and the evidence de novo, taking as true all evidence favorable to the nonmovant – Faulkner – and indulging every reasonable inference and resolving any doubts in Faulkner’s favor. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005); Nixon v. Mr. Prop. Mgmt. Co., Inc., 690 S.W.2d 546, 548-49 (Tex. 1985).

We further review de novo the construction of an unambiguous contract. MCI Tel. Corp. v.

Tex. Utils. Elec. Co., 995 S.W.2d 647, 650-51 (Tex. 1999). In so doing, our primary concern is the true intentions of the parties as expressed in the instrument. Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983). In determining the parties’ intent, we examine the entire agreement and give effect to all provisions such that none are rendered meaningless. Id. We further apply the pertinent rules of construction, look to the plain meaning of the contract language, and enforce the contract as written. Vincent v. Bank of Am., N.A., 109 S.W.3d 856, 867 (Tex. App. – Dallas 2003, pet. denied).

Condition Precedent

Condition precedents are events that must be performed before a right accrues to enforce a contract. Hohenberg Bros. Co. v. George E. Gibbons & Co., 537 S.W.2d 1, 3 (Tex. 1976). No particular words are necessary for the existence of a condition, but such terms as “if,” “provided that,” “on condition that,” or some other phrase that conditions performance, usually connote an intent for a condition rather than a promise. Id.; Gulf Const. Co., Inc. v. Self, 676 S.W.2d 624, 627 (Tex. App. – Corpus Christi 1984, writ ref’d n.r.e.). As forfeitures are not favored, finding a condition precedent should be avoided if another reasonable reading of the contract is possible. Criswell v. European Crossroads Shopping Ctr., Ltd., 792 S.W.2d 945, 948 (Tex. 1990); Schwarz-

Jordan, Inc. of Houston v. Delisle Const. Co., 569 S.W.2d 878, 881 (Tex. 1978).

The parties cite Gulf as controlling authority. In that case, the contract provided that:

When the owner or his representative advances or pays the general contractor, the general contractor shall be liable for and obligated to pay the sub-contractor up to the amount or percentage recognized and approved for payment by the owner’s representative less the retainage required under the terms of the prime contract.

Under no circumstances shall the general contractor be obligated or required to advance or make payments to the sub-contractor until the funds have been advanced or paid by the owner or his representative to the general contractor.

Gulf, 676 S.W.2d at 627. The provision was not labeled “condition precedent,” nor did it contain terms such as “if,” “provide that,” “on condition that,” or some other phrase that would condition performance. Id. After discussing the credit risk borne by the general contractor, that is, that the owner may become insolvent, the court noted that “in order to transfer this normal credit risk . . . from the general contractor to the subcontractor, the contract between the general contractor and the subcontractor should contain an express condition clearly showing that to be the intention of the parties.” Id. at 628-29. Finding the provision did not, the court held that the provision was not a condition precedent but rather a covenant that modified the time and manner of payment. Id. at 630 (“We hold that the [clause] merely provides a covenant dealing with ‘terms of payment’ or ‘manner of payment’ rather than a condition precedent.”); see also Sheldon L. Pollack Corp. v. Falcon Industries, Inc., 794 S.W.2d 380, 384 (Tex. App. – Corpus Christi 1990, writ denied) (construing the following provision as a covenant that modified time and manner of payment: “Payment Schedule: Contractor will pay subcontractor the sum of $2,352,000.00 in installments as follows: lump sum of TWO MILLION THREE HUNDRED FIFTY-TWO THOUSAND AND NO/100 DOLLARS ($2,352,000.00) ninety percent on or about the 30th day of each month for work incorporated or materials suitably stored as acceptable to owner and contractor and for which payment has been made by owner or lender to contractor; ten percent to be paid following completion of the subcontractor’s work and acceptance by owner and release to contractor of retainage.”).

Free access — add to your briefcase to read the full text and ask questions with AI

FaulknerUSA, L.P., FaulknerUSA GP, Inc. and Safeco Insurance Company of America v. Alaron Supply Company, Inc., (Tex. Ct. App. 2010).

FaulknerUSA, L.P., FaulknerUSA GP, Inc. and Safeco Insurance Company of America v. Alaron Supply Company, Inc. (FaulknerUSA, L.P., FaulknerUSA GP, Inc. and Safeco Insurance Company of America v. Alaron Supply Company, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Gulf Const. Co., Inc. v. Self
676 S.W.2d 624 (Court of Appeals of Texas, 1984)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Criswell v. European Crossroads Shopping Center, Ltd.
792 S.W.2d 945 (Texas Supreme Court, 1990)
Vincent v. Bank of America, N.A.
109 S.W.3d 856 (Court of Appeals of Texas, 2003)
Hohenberg Bros. Co. v. George E. Gibbons & Co.
537 S.W.2d 1 (Texas Supreme Court, 1976)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
Sheldon L. Pollack Corp. v. Falcon Industries, Inc.
794 S.W.2d 380 (Court of Appeals of Texas, 1990)
Schwarz-Jordan, Inc. of Houston v. Delisle Construction Co.
569 S.W.2d 878 (Texas Supreme Court, 1978)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)