Solar Applications Engineering, Inc. v. T.A. Operating Corp.

327 S.W.3d 104, 54 Tex. Sup. Ct. J. 238, 2010 Tex. LEXIS 889, 2010 WL 4910135
CourtTexas Supreme Court
DecidedDecember 3, 2010
Docket06-0243
StatusPublished
Cited by111 cases

This text of 327 S.W.3d 104 (Solar Applications Engineering, Inc. v. T.A. Operating Corp.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Solar Applications Engineering, Inc. v. T.A. Operating Corp., 327 S.W.3d 104, 54 Tex. Sup. Ct. J. 238, 2010 Tex. LEXIS 889, 2010 WL 4910135 (Tex. 2010).

Opinion

Justice WAINWRIGHT

delivered the opinion of the Court.

In this case, a general contractor and an owner dispute performance and final payment under a construction contract. 1 Solar Applications Engineering, Inc. d/b/á Wade Construction (Solar), the general contractor, and T.A. Operating Corporation d/b/a TravelCenters of America (TA), the owner, entered a contract to build a truck stop in San Antonio, Texas. After Solar substantially completed the project, disputes arose regarding the completion of certain remaining work and the attachment of liens on the property by subcontractors and Solar. TA eventually terminated the contract and refused to make final payment to Solar. Solar sued TA for breach of contract to recover the contract balance, and TA counterclaimed for delay and defective work. At trial, the court’s jury charge focused primarily on damages. The verdict substantially favored Solar, with the jury awarding actual damages of $400,000 offset by $8,000 in defects and omissions.

On appeal, TA argued that because Solar did not provide a hen-release affidavit, which TA argues was a condition precedent to final payment under the contract, Solar cannot recover for breach of contract. On rehearing, the court of appeals reversed the trial court’s judgment, holding that the lien release provision was a condition precedent and that Solar failed to prove it complied with the lien-release provision. It rendered a take-nothing judgment in favor of TA. 2

*106 The issue before this Court is whether the lien-release provision is a condition precedent to Solar’s recovery for breach of contract and whether failure to provide it is a bar to recovery. TA reasonably argues that an owner who has paid the contract amount to the general contractor is entitled to a building free of subcontractor’s liens. Solar contends, also reasonably, that it is entitled to the balance remaining under the contract for completing the project offset by the cost to remedy defects and omissions. Under normal circumstances, Solar might have provided a conditional lien-release affidavit to allow Solar to fulfill its obligation under the contract, to allow TA to be assured that it will not be double-billed for work on the project, and to allow the parties to resolve their dispute regarding the scope of the work. But the standard operating procedure broke down here, and the court of appeals ultimately ruled that TA was entitled to a windfall, even though the issue of breach or satisfaction of conditions precedent was not tried to the jury.

We hold that the lien-release provision is a covenant, not a condition precedent to Solar’s recovery on the contract. We reverse the judgment of the court of appeals, reinstate the trial court’s judgment, and remand to the trial court for further proceedings consistent with this opinion.

I. BACKGROUND

TA entered into a contract with Solar to construct, for approximately $4 million, a retail building for use as a truck stop, restaurant, and convenience store. The contract between Solar and TA contemplates a specific sequence of events leading up to completion and final payment that is common in construction contracts. This procedure is consistent with a statutory scheme that provides contractors and builders with lien rights to secure payment for labor, but also gives owners the right to retain a percentage of the contract balance to satisfy any outstanding liens on the project if necessary.

The contractual sequence for the truck stop project is as follows: The parties agree on a construction schedule and then Solar begins work according to the schedule. On application for payment by Solar, TA is required to provide monthly progress payments. When Solar believes the construction project ready for its intended use, that it is “substantially complete,” it so notifies TA. After an inspection, if TA agrees that the project is substantially complete, TA issues a “certificate of Substantial Completion” and attaches a list of items, referred to as the “punch list,” to be completed or corrected before final payment. 3 Next, upon written notice from Solar that the punch list is done and the project is complete, TA conducts a final *107 inspection with Solar to identify any deficiencies, and Solar remedies those deficiencies. 4 After Solar corrects the identified deficiencies, it may submit a “final Application for Payment” that is accompanied by complete and legally effective releases or waivers of all lien rights (“lien-release affidavit”). 5

In this case, the parties agree that the project was substantially complete in August 2000. A few weeks later, TA presented Solar with a punch list, but disputes arose over the remaining items that needed to be completed before final payment. Solar then filed a lien against the project for $472,393, and subcontractors also filed liens against the property. TA terminated Solar pursuant to the contract’s “for cause” termination provision contending that, among other things, Solar had failed to keep the project lien-free and failed to complete the punch list. 6 The termination letter also notified Solar that TA was asserting claims for $736,800.15 against Solar for its failure to complete the construction project on time. The day after TA terminated the contract, Solar provided TA with an “Application and Certificate for Payment” for $472,149, the amount Solar believed to be the remaining contract balance. TA refused to make payment, contending Solar had not complied with the lien-release provision by failing to submit a lien-release affidavit. TA contended it had no obligation to make final payment on a building with outstanding construction liens. Solar then sued TA for breach of contract under the theory of substantial performance for the unpaid balance of the contract, and TA counterclaimed for alleged delays and defective work.

By the time of trial, subcontractors filed $246,627 in liens against the project. The trial court severed the subcontractors’ claims and ordered that any sums recovered by Solar, other than attorney’s fees, would be held in trust for the benefit of the subcontractors’ claims. The jury found in favor of Solar, and the trial court entered a judgment on the verdict in favor of Solar, awarding $392,000 in damages, which represented the balance due under the contract less an $8,000 offset to remedy all remaining “punch list” defects and omissions found by the jury.

TA appealed, and the court of appeals initially affirmed the trial court’s judgment. On rehearing, however, the court of appeals reversed and rendered judgment that Solar take nothing. The court of appeals assumed that the lien-release *108 provision was a condition precedent and held that the doctrine of substantial performance did not excuse Solar’s failure to provide a lien-release affidavit, and thus Solar forfeited final payment under the contract. 191 S.W.3d 173, 180-81 (Tex.App.-San Antonio 2005, pet. granted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SM Energy Co. v. Colgate Prod., LLC
New Mexico Court of Appeals, 2025
Michael A. Bentley v. Chandra L. Bentley
Court of Appeals of Texas, 2024

Cite This Page — Counsel Stack

Bluebook (online)
327 S.W.3d 104, 54 Tex. Sup. Ct. J. 238, 2010 Tex. LEXIS 889, 2010 WL 4910135, Counsel Stack Legal Research, https://law.counselstack.com/opinion/solar-applications-engineering-inc-v-ta-operating-corp-tex-2010.