Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant)

Court of Appeals of Texas·Decided March 4, 2026·No. 04-22-00756-CV·Published

Opinion

Fourth Court of Appeals

San Antonio, Texas

MEMORANDUM OPINION

OPINION ON MOTION FOR REHEARING No. 04-22-00756-CV

GRAPEVINE GROUP CONCRETE CONTRACTORS, INC., Appellant/Cross-Appellee

v.

YC PARTNERS, LTD. d/b/a Yantis Company and Yantis Corporation, Appellees/Cross-Appellants

From the 131st Judicial District Court, Bexar County, Texas Trial Court No. 2018-CI-05255 Honorable Aaron Haas, Judge Presiding

Opinion by: Lori Massey Brissette, Justice

Sitting: Irene Rios, Justice Lori Massey Brissette, Justice H. Todd McCray, Justice

Delivered and Filed: March 4, 2026 REVERSED AND REMANDED On November 19, 2025, we issued an opinion and judgment reversing the trial court’s judgment and remanding the matter for a new trial on all issues. On January 2, 2026, counsel for appellee, YC Partners, Ltd. d/b/a Yantis Company and Yantis Corporation (collectively, “YC”), timely filed a “Request for Conditional Voluntary Remittitur and Motion for Panel Rehearing.” Appellant, Grapevine Group Contractors, Inc. (“Grapevine”) filed a response to YC’s filing as

well as its own “Motion for Rehearing.” YC then filed a reply. After considering the request for remittitur, the motions, the response, and the reply, we grant in part YC’s motion for rehearing, withdraw our prior opinion and judgment, and substitute this opinion and judgment in its stead. The request and the motions are otherwise denied. See TEX. R. APP. P. 46.5, 49.3.

This case involves a complex web of conduct that resulted in a subcontractor walking off two jobs and a contractor having to incur additional expenses to complete both projects. The trial court, as factfinder, was tasked with determining, among other things, which party was first to materially breach the contracts and whether the contractor was liable for failure to pay the subcontractor under the Texas Construction Trust Fund Act and Texas Prompt Pay Act. We reverse the case and remand for a new trial on all issues.

BACKGROUND

YC, a construction contractor, hired Grapevine as subcontractor to complete concrete work relating to two projects known as the Bandera Road Subdivision Unit 2 (“Bandera”) and Toepperwein Bluffs (“Toepperwein”). 1 The parties entered into two subcontracts, one for each project, with nearly identical terms. The Bandera subcontract had an estimated value of $207,435.00, which eventually increased to $217,332.00, and the Toepperwein subcontract had an estimated value of $175,447.00.

After working together and securing payment for the first invoices in September, the parties’ relationship began deteriorating when YC disputed the progress estimates provided by Grapevine on each project as well as the amount due. Despite these disputes, the parties continued to work together, with Grapevine continuing its concrete work and YC continuing to discuss the necessary revisions and inspecting the work as it progressed. Then, Matt Yantis—YC’s owner—

1 The Bandera subdivision where the Bandera project took place was owned by M/I Homes of San Antonio, LLC. The Toepperwein subdivision where the Toepperwein project took place was owned by LECA Construction, LLC.

took the position that YC’s payment to Grapevine on the projects would be contingent on Grapevine’s satisfaction of an invoice due to Curv Compliance, a separate company owned by Yantis which had provided OSHA safety classes to Grapevine employees. Grapevine initially agreed to this approach, but then later reconsidered, giving notice that it was stopping the work on both projects and would be filing liens. YC bonded around the liens and hired C4 Construction Services, LLC (“C4”) to complete the projects.

Grapevine sued YC for, among other things, breach of contract (as to both projects), quantum meruit, failure to comply with the Texas Prompt Payment Act and the Texas Construction Trust Fund Act, and attorney’s fees. YC countersued for breach of contract (as to both projects), removal of fraudulent liens, and attorney’s fees. After a bench trial, the trial court entered a final judgment granting YC, after all offsets and credits due, 2 damages from Grapevine in the amount of $31,806.37, prejudgment and post-judgment interest, and attorney’s fees and court costs of $55,421.01 (along with conditional attorney’s fees). 3 The trial court also issued extensive findings of fact and conclusions of law.

Both companies appeal the trial court’s ruling raising multiple points of error including:

(1) the sufficiency of the evidence to support the trial court’s determination of which party first materially breached the subcontracts, (2) the sufficiency of evidence supporting YC’s damages, (3) the trial court’s calculation of Grapevine’s damages, (4) the trial court’s ruling as to Grapevine’s claim for quantum meruit, (5) the trial court’s conclusions as to several claims based on the Texas Property Code, and (6) the award of attorney’s fees.

2 The trial court did not delineate in its final judgment the amount of damages awarded to YC or the amount of damages awarded to Grapevine, instead simply setting forth an amount due to YC after offsets and credits. 3 The court also denied Grapevine’s claims against the other defendants, M/I Homes of San Antonio, LLC, Roberto C. Leal, LECA Construction, LLC, and Fidelity and Deposit Company of Maryland and declared Grapevine’s liens void.

FIRST MATERIAL BREACH 4

Grapevine argues the evidence is legally and factually insufficient to support the trial court’s findings that it was the first to materially breach the subcontracts. Further, Grapevine challenges the trial court’s finding that YC’s non-payment of invoices was not a prior material breach which excused Grapevine’s continued performance. Further, Grapevine asserts that, even if it did materially breach the subcontracts, YC’s continued performance forfeited its right to discharge its obligations.

Standard of Review Both parties sued, contending the other committed the first material breach. The trial court found in favor of YC. Thus, we must review the evidence, first, to determine whether there is any evidence to support the trial court’s finding that Grapevine was the first to materially breach the subcontracts and, second, whether Grapevine conclusively proved that YC was, instead, the first to materially breach the contracts. See Graham Cent. Station, Inc. v. Pena, 442 S.W.3d 261, 263 (Tex. 2014) (when attacking adverse finding on issue on which appellant did not have burden of proof, it must demonstrate on appeal that no evidence supports adverse finding); Dow Chem. Co. v. Francis, 46 S.W.3d 237, 241 (Tex. 2001) (per curiam) (when challenging adverse finding on which appellant has burden of proof, it must demonstrate on appeal evidence establishes, as matter of law, all vital facts in support of issue).

4 “In many disputes over failure of performance, both parties fail to finish performance, and the question is whether one of them is justified in so doing by the other party’s failure.” RESTATEMENT (SECOND) OF CONTRACTS § 237(b) (1981). “This task can be as enigmatic as the childhood question: ‘Which came first—the chicken or the egg?’” Principle of Cure and Its Implications upon Materiality—Principle of “First Uncured Material Breach” as Justification for Future Contract Nonperformance, 5 BRUNER & O’CONNOR CONSTRUCTION LAW § 18:16; see Mustang Pipeline Co., Inc. v. Driver Pipeline Co., Inc., 134 S.W.3d 195, 200 (Tex. 2004) (“In the standard contract dispute, one party cancels the contract or refuses to pay due to alleged breaches by the other; in such circumstances, jurors will often find both parties failed to comply with the contract (as the jury did here) unless instructed that they must decide who committed the first material breach.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant), (Tex. Ct. App. 2026).

Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant) (Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
Long Trusts v. Griffin
222 S.W.3d 412 (Texas Supreme Court, 2006)
Dealers Electrical Supply Co. v. Scoggins Construction Co.
292 S.W.3d 650 (Texas Supreme Court, 2009)
Hernandez v. Lautensack
201 S.W.3d 771 (Court of Appeals of Texas, 2006)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
McKee v. McNeir
151 S.W.3d 268 (Court of Appeals of Texas, 2004)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104 (Texas Supreme Court, 2010)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Hanks v. GAB Business Services, Inc.
644 S.W.2d 707 (Texas Supreme Court, 1982)
Graham Central Station, Inc. v. Jesus Peña
442 S.W.3d 261 (Texas Supreme Court, 2014)
Enzo Investments, LP v. Charles White
468 S.W.3d 635 (Court of Appeals of Texas, 2015)
Douglas W. STREBEL, Appellant, v. John C. WIMBERLY II, Appellee
371 S.W.3d 267 (Court of Appeals of Texas, 2012)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)