Hernandez v. Lautensack

201 S.W.3d 771, 2006 WL 949989
CourtCourt of Appeals of Texas
DecidedAugust 17, 2006
Docket2-05-085-CV
StatusPublished
Cited by66 cases

This text of 201 S.W.3d 771 (Hernandez v. Lautensack) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hernandez v. Lautensack, 201 S.W.3d 771, 2006 WL 949989 (Tex. Ct. App. 2006).

Opinion

OPINION

ANNE GARDNER, Justice.

I. Introduction

Roy Hernandez, individually and d/b/a/ Hernandez Roofing and Philip Lautensack filed cross appeals from a judgment in favor of Lautensack concerning the roof Hernandez put on Lautensack’s house. In three issues, Hernandez argues that Lau-tensack’s presuit notice under the Residential Construction Liability Act was untimely, that there was no evidence that Lautensack’s alleged damages were reasonable, and that the trial court erred in awarding attorney’s fees to Lautensack because his presuit demand was excessive. In two issues, Lautensack argues that the evidence conclusively proved his attorney’s fees in an amount double what the jury awarded to him and that the trial court erred by refusing to reopen testimony so that Lautensack’s counsel could testify about appellate attorney’s fees. We modify the trial court’s judgment and affirm it as modified.

II. Factual and Procedural Background

In 1999, Lautensack hired Hernandez to replace the slate tile roof on Lautensack’s residence at a cost of $20,000. The new roof had many leaks that Hernandez was unable to stop. In 2002, Hernandez told Lautensack that the leaks were the result of hail damage and offered to replace the roof for $9,100 in labor charges if Lauten-sack provided new slate tiles at a cost of $25,000. Unhappy with Hernandez’s prior work, Lautensack hired another roofer, Kip Petty, to install a new cement tile roof for $32,300. Petty documented several defects in Hernandez’s previous roofing job, including lack of proper underlayment, lack of metal flashing, and improper tile spacing. Petty replaced the roof in September 2002.

Lautensack sent Hernandez a claim notice letter on February 12, 2003, by certified and regular mail. The letter described various problems with the roof, alleged breaches of express warranties and DTPA violations, and threatened litigation unless Hernandez paid Lautensack $41,880. The certified letter was returned unclaimed; the regular letter was not returned. Hernandez did not reply.

*775 Lautensack sued Hernandez on April 17, 2003, for breach of contract, misrepresentation, fraud, and deceptive trade practices and sought actual damages, attorney’s fees, and exemplary damages. Hernandez responded with a plea in abatement claiming that Lautensack had failed to serve the requisite presuit notice under the Residential Construction Liability Act (“RCLA”). See Tex. PROP.Code Ann. §§ 27.001-003 (Vernon Supp.2005), .0031 (Vernon 2000), .004 (Vernon Supp.2005), .0041 (Vernon 2000), .0042 (Vernon Supp.2005, .005-.006 (Vernon 2003), .007 (Vernon Supp.2005). Though Lautensack contended that his first letter was sufficient notice under the RCLA, he eventually sent a second notice letter in response to Hernandez’s plea in abatement.

The case was ultimately tried to a jury. The jury returned a verdict in favor of Lautensack on all causes of action and awarded him $24,750 in actual damages plus $10,680 in attorney’s fees. The jury also found that Lautensack’s RCLA notice was untimely because it did not give Hernandez the opportunity to inspect the alleged roof defects and offer to repair them. For reasons not relevant to this appeal, the trial court disregarded the jury’s answers to the breach of warranty and DTPA issues. The trial court then signed a judgment in favor of Lautensack for the amounts awarded by the jury. Both parties appealed.

III. Discussion

A. Hernandez’s Issues

1. Timeliness of RCLA notice

In his first issue, Hernandez argues that the trial court erred by rendering judgment for Lautensack because the jury found that Lautensack’s presuit notice failed to meet the requirements of the RCLA. We disagree.

Section 27.004 of the RCLA provides that a claimant seeking damages arising from a contractor’s construction defect must give the contractor written notice of the alleged defect more than sixty days before filing suit. Tex. Prop.Code Ann. § 27.004(a). After receiving notice, the contractor has thirty-five days to inspect the property and forty-five days to make a written offer of settlement. Id. § 27.004(a)-(b). Under the RCLA as amended in 2003, failure of the claimant to give the requisite presuit notice results in dismissal of the suit. Id. § 27.004(d). But as Hernandez concedes in his brief, the prior version of the RCLA applicable to this suit contained no dismissal provision; instead, it provided for abatement of a suit where the claimant failed to provide the requisite presuit notice. See Act of May 17, 1995, 74th Leg., R.S., ch. 414, § 10, 1995 Tex. Gen. Laws 2988, 2996 (amended 2003) (current version at Tex. PROP.Code Ann. § 27.004(d)).

The trial court submitted the following question to the jury as part of the charge:

Do you find that, 60 days preceding the filing of this suit by Philip Lauten-sack against Roy Hernandez, Philip Lautensack gave written notice by Certified Mail/Return Receipt Requested to Roy Hernandez specifying, in reasonable detail, the construction defects that are the subject of the complaint at a time when Roy Hernandez could have performed any of the following:
a. Within 35 days of receipt of the written notice, Roy Hernandez had a reasonable opportunity to inspect the property, to determine the nature and cause of the construction defect and the nature and extent of repairs necessary to remedy the construction defect?
*776 [[Image here]]
b. Within 45 days of receipt of the written notice, make an offer to repair, or to have repaired by an independent contractor at Roy Hernandez’s expense, the construction defect described in the notice?

The jury answered “no” to both parts of the question.

Hernandez argues that the jury’s answers to this question compel a judgment in his favor. Hernandez does not argue that the content of Lautensack’s notice was deficient; rather, he argues that by replacing the roof before he sent his notice letter, Lautensack deprived Hernandez of the opportunity to inspect the property and offer to repair the alleged defects under RCLA section 27.004.

We reject Hernandez’s argument for several reasons. First, the practical effect of Hernandez’s argument is to engraft the dismissal provision of the current RCLA onto the prior version that controls this case. This we cannot do. We must apply the law as the legislature wrote it. Reese v. Duncan, 80 S.W.3d 650, 658 (Tex.App.Dallas 2002, pet. denied). Second, the RCLA’s intent to give a contractor a reasonable opportunity to inspect the property upon request was effectuated under the facts of this case. The undisputed evidence at trial proved that Hernandez did in fact inspect the roof many times when he attempted to repair leaks before it was replaced and submitted a bid to replace the roof in September 2002.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amy Hale v. Brian Hale
Court of Appeals of Texas, 2024
Eduardo Del Bosque v. Juan Barbosa
Court of Appeals of Texas, 2023
Lori Stevens v. Thomas Stevens
Court of Appeals of Texas, 2021

Cite This Page — Counsel Stack

Bluebook (online)
201 S.W.3d 771, 2006 WL 949989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hernandez-v-lautensack-texapp-2006.