Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez

Court of Appeals of Texas·Decided February 27, 2025·No. 01-23-00493-CV·Published

Opinion

Opinion issued February 27, 2025

In The

Court of Appeals

For The

First District of Texas

(2) without the actual damages award, the Martinezes were not entitled to an award of attorney’s fees. Because we conclude that there is some evidence of actual damages, but not enough to support the full amount awarded, we reverse the trial court’s judgment and remand for a new trial, unless the Martinezes accept the remittitur we suggest below, in which case we will modify the judgment and affirm as modified.

Background

In 2017, Noe and Judy Martinez, who are husband and wife, owned and resided in a 2,486-square foot home in Friendswood, Texas. During Hurricane Harvey, the home flooded, damaging it. The Martinezes’ daughter, Elsa Baughman, recommended that her parents hire Demiraj to repair their home. He operated a construction business and had performed satisfactory past work for Baughman.

After he represented that he could complete the necessary construction work, the Martinezes contracted with Demiraj to repair and renovate their home. The parties agreed that the Martinezes would buy the construction materials for the project, and Demiraj would provide the labor. The parties signed three contracts defining the scope of the construction services Demiraj would provide.

The first contract, dated December 27, 2017, provided that, for $43,000, Demiraj would “[i]nstall all new 8 ft sheetrock, insulation tape, float and texture” the walls and ceilings throughout the home and garage. The second contract, dated

February 5, 2018, provided that Demiraj would “[p]rimer and paint the walls, ceilings and garage” for $9,800. The third contract, dated March 2, 2018, provided that Demiraj would perform the following work for $65,000: (1) install tile and a bathtub in the guest bathroom; (2) install shower tile in the master bathroom; (3) install new wood frames around all windows in the home; (4) install laminate flooring throughout “the main section of the home”; (5) install new padding and carpeting in the bedrooms; (6) add tile around the living room fireplace; (7) “[p]rep and paint all new cabinets” in the kitchen, laundry room, and bathrooms; (8) repair the front door to close properly; (9) install “all mirrors, appliances and accessories in the proper areas throughout the home”; and (10) “[t]ouch up paint throughout the home [to make] ready for move in.”

Under the contracts, the Martinezes agreed to pay a total of $117,800. Over time, the Martinezes paid Demiraj $112,800 of the $117,800. They also paid Demiraj an additional $7,850 for work he performed outside the scope of the contracts and for materials he purchased. Altogether, the Martinezes paid Demiraj $120,650. Despite being paid this amount, Demiraj asked the Martinezes for additional funds. At that point, the Martinezes were already dissatisfied with the quality of Demiraj’s work, and Demiraj had completed only fifty percent of the project. Demiraj told the Martinezes that, if they gave him another $65,000, he could finish the project in ten days. Given his past performance, the Martinezes decided to terminate Demiraj.

A couple of weeks later, the Martinezes contracted with All Star Construction to complete the project, which included repairing Demiraj’s defective work. The contract detailed the scope of the work that All Star would perform and reflected that the Martinezes agreed to pay All Star $45,000. The parties agreed that All Star would provide the labor and the Martinezes would provide the construction materials, which ultimately cost them $53,863.77. Altogether, the project’s completion, including repairing Demiraj’s defective work, cost the Martinezes $98,863.77 ($45,000 + $53,863.77).

In August 2018, the Martinezes’ attorney sent Demiraj a demand letter. The letter asserted that Demiraj breached the contracts and misrepresented the amount and quality of work he performed. The letter asked Demiraj to pay the Martinezes the cost they incurred to complete the work, plus their attorney’s fees.

In June 2021, the Martinezes sued Demiraj. As in their demand letter, the Martinezes alleged that Demiraj failed to perform the contracts and made misrepresentations about the work he performed at their home. They also alleged that they “expend[ed] ninety-eight thousand eight hundred sixty-three dollars and seventy-seven cents ($98,863.73)1 to complete the work.” They asserted several

1 Although the words in the petition stated “ninety-eight thousand eight hundred sixty-three dollars and seventy-seven cents,” the parenthetical numerals incorrectly stated $98,863.73. (Emphasis added.) This same mistake also appeared in the Martinezes’ demand letter. As discussed below, the evidence at trial showed that the Martinezes paid $98,863.77 to repair and complete the construction work.

causes of action, including breach of contract, breach of express and implied warranties, negligence, fraud, and violation of the Deceptive Trade Practices Act (DTPA). The Martinezes sought actual damages as well as exemplary and punitive damages and their attorney’s fees. Demiraj answered, generally denying the claims and raising several affirmative defenses.

The trial court conducted a bench trial in March 2023. The Martinezes, Baughman, and Demiraj testified. The contracts between the Martinezes and Demiraj, detailing the scope of the work he agreed to perform, were admitted into evidence. Going through each contract, Noe identified the work Demiraj failed to complete. For example, Demiraj had not installed the sheetrock as agreed in the first contract, had not painted the walls, ceiling, and garage as agreed in the second contract, and had not completed tiling the master bathroom or painting the kitchen cabinets as agreed in the third contract. Noe testified that “every room was started, except the TV room; but it was never completed.” He estimated that Demiraj completed around fifty percent of the work listed in the contracts. He also testified that parts of Demiraj’s completed work were defective and needed repair. For instance, Demiraj installed laminate flooring incorrectly, requiring fifty percent of it to be replaced.

Noe testified that, with fifty percent of the work remaining, Demiraj presented him with an invoice stating that he needed an additional $65,000 to complete the

work. Demiraj told Noe that, with the additional funds, he would complete the work in ten days. Given Demiraj’s past performance, Noe was skeptical that the work would be completed that quickly and terminated him.

Noe stated that they hired All Star in early April 2018. The contract with All Star was admitted into evidence and listed the work that All Star would perform for $45,000. The Martinezes’ attorney asked Noe whether $45,000 was a reasonable cost for the work. Demiraj objected, asserting that Noe was not qualified to make a reasonableness determination. The trial court overruled the objection, and Noe testified that it was a reasonable cost because $45,000 was $20,000 less than the $65,000 Demiraj requested to finish the project.

Noe also testified that he purchased the construction materials to complete the project and confirmed that the materials cost $53,863.77. Copies of the receipts for the materials were admitted into evidence. Noe testified that, adding the costs of the labor and materials together, the total cost to complete the project was $98,863.77.

Free access — add to your briefcase to read the full text and ask questions with AI

Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez, (Tex. Ct. App. 2025).

Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez (Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
ERI Consulting Engineers, Inc. v. Swinnea
318 S.W.3d 867 (Texas Supreme Court, 2010)
Cooke County Tax Appraisal District v. Teel
129 S.W.3d 724 (Court of Appeals of Texas, 2004)
Hernandez v. Lautensack
201 S.W.3d 771 (Court of Appeals of Texas, 2006)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
Perry Homes v. Alwattari
33 S.W.3d 376 (Court of Appeals of Texas, 2001)
City of Tyler v. Likes
962 S.W.2d 489 (Texas Supreme Court, 1998)
In Re Bain
144 S.W.3d 236 (Court of Appeals of Texas, 2004)
King Ranch, Inc. v. Chapman
118 S.W.3d 742 (Texas Supreme Court, 2003)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
CCC Group, Inc. v. South Central Cement, Ltd.
450 S.W.3d 191 (Court of Appeals of Texas, 2014)
Stroud v. Pechacek
120 S.W.2d 626 (Court of Appeals of Texas, 1938)
Cruz v. Andrews Restoration, Inc.
364 S.W.3d 817 (Texas Supreme Court, 2012)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)
Howard Industries, Inc. v. Crown Cork & Seal Co.
403 S.W.3d 347 (Court of Appeals of Texas, 2013)