Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez

CourtCourt of Appeals of Texas
DecidedFebruary 27, 2025
Docket01-23-00493-CV
StatusPublished

This text of Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez (Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez, (Tex. Ct. App. 2025).

Opinion

Opinion issued February 27, 2025

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-23-00493-CV ——————————— EDMOND DEMIRAJ D/B/A ALB PAINTING AND REMODELING, Appellant V. NOE MARTINEZ & JUDY MARTINEZ, Appellees

On Appeal from County Court at Law No. 2 Galveston County, Texas Trial Court Case No. CV-0088626

MEMORANDUM OPINION

Appellant Edmond Demiraj, doing business as ALB Painting and Remodeling

(Demiraj), challenges the trial court’s judgment awarding appellees Noe and Judy

Martinez actual damages and attorney’s fees. In two issues, Demiraj contends that

(1) the evidence was legally insufficient to support the award of actual damages and, (2) without the actual damages award, the Martinezes were not entitled to an award

of attorney’s fees. Because we conclude that there is some evidence of actual

damages, but not enough to support the full amount awarded, we reverse the trial

court’s judgment and remand for a new trial, unless the Martinezes accept the

remittitur we suggest below, in which case we will modify the judgment and affirm

as modified.

Background

In 2017, Noe and Judy Martinez, who are husband and wife, owned and

resided in a 2,486-square foot home in Friendswood, Texas. During Hurricane

Harvey, the home flooded, damaging it. The Martinezes’ daughter, Elsa Baughman,

recommended that her parents hire Demiraj to repair their home. He operated a

construction business and had performed satisfactory past work for Baughman.

After he represented that he could complete the necessary construction work,

the Martinezes contracted with Demiraj to repair and renovate their home. The

parties agreed that the Martinezes would buy the construction materials for the

project, and Demiraj would provide the labor. The parties signed three contracts

defining the scope of the construction services Demiraj would provide.

The first contract, dated December 27, 2017, provided that, for $43,000,

Demiraj would “[i]nstall all new 8 ft sheetrock, insulation tape, float and texture”

the walls and ceilings throughout the home and garage. The second contract, dated

2 February 5, 2018, provided that Demiraj would “[p]rimer and paint the walls,

ceilings and garage” for $9,800. The third contract, dated March 2, 2018, provided

that Demiraj would perform the following work for $65,000: (1) install tile and a

bathtub in the guest bathroom; (2) install shower tile in the master bathroom;

(3) install new wood frames around all windows in the home; (4) install laminate

flooring throughout “the main section of the home”; (5) install new padding and

carpeting in the bedrooms; (6) add tile around the living room fireplace; (7) “[p]rep

and paint all new cabinets” in the kitchen, laundry room, and bathrooms; (8) repair

the front door to close properly; (9) install “all mirrors, appliances and accessories

in the proper areas throughout the home”; and (10) “[t]ouch up paint throughout the

home [to make] ready for move in.”

Under the contracts, the Martinezes agreed to pay a total of $117,800. Over

time, the Martinezes paid Demiraj $112,800 of the $117,800. They also paid Demiraj

an additional $7,850 for work he performed outside the scope of the contracts and

for materials he purchased. Altogether, the Martinezes paid Demiraj $120,650.

Despite being paid this amount, Demiraj asked the Martinezes for additional funds.

At that point, the Martinezes were already dissatisfied with the quality of Demiraj’s

work, and Demiraj had completed only fifty percent of the project. Demiraj told the

Martinezes that, if they gave him another $65,000, he could finish the project in ten

days. Given his past performance, the Martinezes decided to terminate Demiraj.

3 A couple of weeks later, the Martinezes contracted with All Star Construction

to complete the project, which included repairing Demiraj’s defective work. The

contract detailed the scope of the work that All Star would perform and reflected

that the Martinezes agreed to pay All Star $45,000. The parties agreed that All Star

would provide the labor and the Martinezes would provide the construction

materials, which ultimately cost them $53,863.77. Altogether, the project’s

completion, including repairing Demiraj’s defective work, cost the Martinezes

$98,863.77 ($45,000 + $53,863.77).

In August 2018, the Martinezes’ attorney sent Demiraj a demand letter. The

letter asserted that Demiraj breached the contracts and misrepresented the amount

and quality of work he performed. The letter asked Demiraj to pay the Martinezes

the cost they incurred to complete the work, plus their attorney’s fees.

In June 2021, the Martinezes sued Demiraj. As in their demand letter, the

Martinezes alleged that Demiraj failed to perform the contracts and made

misrepresentations about the work he performed at their home. They also alleged

that they “expend[ed] ninety-eight thousand eight hundred sixty-three dollars and

seventy-seven cents ($98,863.73)1 to complete the work.” They asserted several

1 Although the words in the petition stated “ninety-eight thousand eight hundred sixty-three dollars and seventy-seven cents,” the parenthetical numerals incorrectly stated $98,863.73. (Emphasis added.) This same mistake also appeared in the Martinezes’ demand letter. As discussed below, the evidence at trial showed that the Martinezes paid $98,863.77 to repair and complete the construction work. 4 causes of action, including breach of contract, breach of express and implied

warranties, negligence, fraud, and violation of the Deceptive Trade Practices Act

(DTPA). The Martinezes sought actual damages as well as exemplary and punitive

damages and their attorney’s fees. Demiraj answered, generally denying the claims

and raising several affirmative defenses.

The trial court conducted a bench trial in March 2023. The Martinezes,

Baughman, and Demiraj testified. The contracts between the Martinezes and

Demiraj, detailing the scope of the work he agreed to perform, were admitted into

evidence. Going through each contract, Noe identified the work Demiraj failed to

complete. For example, Demiraj had not installed the sheetrock as agreed in the first

contract, had not painted the walls, ceiling, and garage as agreed in the second

contract, and had not completed tiling the master bathroom or painting the kitchen

cabinets as agreed in the third contract. Noe testified that “every room was started,

except the TV room; but it was never completed.” He estimated that Demiraj

completed around fifty percent of the work listed in the contracts. He also testified

that parts of Demiraj’s completed work were defective and needed repair. For

instance, Demiraj installed laminate flooring incorrectly, requiring fifty percent of it

to be replaced.

Noe testified that, with fifty percent of the work remaining, Demiraj presented

him with an invoice stating that he needed an additional $65,000 to complete the

5 work. Demiraj told Noe that, with the additional funds, he would complete the work

in ten days. Given Demiraj’s past performance, Noe was skeptical that the work

would be completed that quickly and terminated him.

Noe stated that they hired All Star in early April 2018. The contract with All

Star was admitted into evidence and listed the work that All Star would perform for

$45,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
ERI Consulting Engineers, Inc. v. Swinnea
318 S.W.3d 867 (Texas Supreme Court, 2010)
Cooke County Tax Appraisal District v. Teel
129 S.W.3d 724 (Court of Appeals of Texas, 2004)
Hernandez v. Lautensack
201 S.W.3d 771 (Court of Appeals of Texas, 2006)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
Perry Homes v. Alwattari
33 S.W.3d 376 (Court of Appeals of Texas, 2001)
City of Tyler v. Likes
962 S.W.2d 489 (Texas Supreme Court, 1998)
In Re Bain
144 S.W.3d 236 (Court of Appeals of Texas, 2004)
King Ranch, Inc. v. Chapman
118 S.W.3d 742 (Texas Supreme Court, 2003)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
CCC Group, Inc. v. South Central Cement, Ltd.
450 S.W.3d 191 (Court of Appeals of Texas, 2014)
Stroud v. Pechacek
120 S.W.2d 626 (Court of Appeals of Texas, 1938)
Cruz v. Andrews Restoration, Inc.
364 S.W.3d 817 (Texas Supreme Court, 2012)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)
Howard Industries, Inc. v. Crown Cork & Seal Co.
403 S.W.3d 347 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Edmond Demiraj D/B/A ALB Painting and Remodeling v. Noe Martinez & Judy Martinez, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edmond-demiraj-dba-alb-painting-and-remodeling-v-noe-martinez-judy-texapp-2025.