Tubal Cain Industries, Inc. v. J.W. Garrett & Son, Inc. D/B/A G&G Enterprises Construction Corporation

CourtCourt of Appeals of Texas
DecidedDecember 4, 2025
Docket09-23-00368-CV
StatusPublished

This text of Tubal Cain Industries, Inc. v. J.W. Garrett & Son, Inc. D/B/A G&G Enterprises Construction Corporation (Tubal Cain Industries, Inc. v. J.W. Garrett & Son, Inc. D/B/A G&G Enterprises Construction Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tubal Cain Industries, Inc. v. J.W. Garrett & Son, Inc. D/B/A G&G Enterprises Construction Corporation, (Tex. Ct. App. 2025).

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

________________ NO. 09-23-00368-CV ________________

TUBAL CAIN INDUSTRIES, INC., Appellant

V.

J.W. GARRETT & SON, INC. D/B/A G&G ENTERPRISES CONSTRUCTION CORPORATION, Appellee

________________________________________________________________________

On Appeal from the 172nd District Court Jefferson County, Texas Trial Cause No. E-209,041 ________________________________________________________________________

MEMORANDUM OPINION

Appellee J.W. Garrett & Son, Inc. d/b/a G&G Enterprises Construction

Corporation (“G&G” or “Appellee”) sued Tubal Cain Industries, Inc. (“Tubal” or

“Appellant”) for breach of contract. G&G based its claim on Tubal’s handling of its

successful bid to construct a transportation facility for the West Orange Cove

Consolidated Independent School District (“ISD”). The case was tried to a jury,

which returned a verdict in G&G’s favor as to liability, damages, and attorney’s fees.

1 The trial court entered a judgment for $206,636, plus interest and attorney’s

fees, based on the jury’s verdict. After Tubal’s Motion for New Trial was overruled

by operation of law, Tubal appealed the trial court’s judgment, arguing that “there

was legally insufficient evidence as to the reasonableness of the amount [G&G]

spent ‘out-of-pocket’ to complete the project.” Tubal contends that since G&G is not

entitled to recover damages, it is not entitled to recover its attorney’s fees.

We affirm the trial court’s judgment.

BACKGROUND

ISD constructed several buildings financed through a bond package worth

twenty-four million dollars. G&G, the general contractor, awarded Tubal the bid to

construct ISD’s transportation facility. The January 29, 2021 contract between G&G

and Tubal called for Tubal “to provide all necessary labor and services to supply one

100’ wide x 226’ long ‘Butler’ brand pre-engineered metal building to serve as a

Transportation Facility for the West Orange-Cove CISD.” The contract further

specified such matters as the type of framing materials, the type of coating, and the

wind speed rating. The original contract price listed is $291,450, but this figure was

later revised to $290,236.50.

Tubal then contracted with Butler to provide the building, with a planned

delivery date of October 22, 2021. When delays extended Butler’s delivery time to

February 2022, Tubal decided to manufacture the building instead of buying it from

2 Butler, but rising steel costs precluded Tubal from doing so at the original contract

price. Tubal therefore requested G&G to approve a change order for $206,636 to

account for this cost increase, but G&G declined to approve the change order. G&G

eventually contracted with Alliance Steel Building Systems (“Alliance”) to complete

the building at a cost of $255,660 and sued Tubal to recover damages and attorney’s

fees. We summarize the evidence below.

G&G Witnesses

Ashley Hillsten’s Testimony

Ashley Hillsten (“Hillsten”) testified that she was G&G’s Senior Quality

Manager, a position she described as being the liaison between the subcontractor and

the architect. In this position, Hillsten was responsible for ensuring “that everything

[that] is coming into the project, conforms to the plans and specs of the job.”

Hillsten discussed schedules, noting that it was necessary to coordinate all the

subcontractors “from the ground up.” She indicated that it would take two to three

weeks for the architect to approve the drawings, but there were delays due to Tubal

“not following the procedures of Butler.” Hillsten considered Tubal at fault for the

schedule delays and design and planning errors. Eventually, according to Hillsten,

Tubal abandoned the project. In December 2021, G&G contracted with Alliance.

Hillsten recalled that Alliance provided the materials in early March 2022.

3 Steven Weldon’s Testimony

Steven Weldon (“Weldon”), a project manager with G&G, testified that he

oversaw all of the ISD’s bond projects. Although Weldon was not involved with the

contract negotiations between G&G and its subcontractors, he testified that it was

Tubal, not G&G, that chose Butler as the brand of metal building it would supply.

Tubal could have used Butler, Mueller, or Alliance to provide the metal building, so

long as the building complied with the plans and specifications. Weldon also

testified that it was Tubal that supplied the schedule it received from Butler.

Although “[i]t is common[]” to revise schedule dates, Weldon stated that Tubal did

not come close to meeting the schedule. In particular, Weldon testified that G&G

did not receive shop drawings by the scheduled date of March 30 and had yet to

provide those plans by May 11. Weldon later acknowledged, however, that the late

drawings would have been Butler’s work—not Tubal’s. Weldon further

acknowledged having threatened to cancel the contract “for just cause” and having

intended that Tubal take that threat seriously, despite Weldon lacking the authority

to do so. G&G later retained other contractors, including Alliance Steel and Boren

Construction, to complete the project.

Colin Garrett’s Testimony

Colin Garrett (“Garrett”) is the president and COO of G&G, a commercial

and industrial general contractor. Garrett described G&G’s business as building

4 buildings, roads, fencing, and infrastructure items necessary to support building

services. In 2018, the ISD chose G&G as the construction manager for the

approximately nine projects in its bond program, and in 2021, G&G accepted

Tubal’s bid to supply the pre-engineered metal building for the transportation center.

After Garrett and Baker clarified whether certain building components were or were

not included in Tubal’s bid, Tubal and G&G agreed on a price of $291,450.

Baker then contacted Butler for a price, but when Tubal learned that

“somewhere in the bidding process[,]” Tubal “had missed a lot of items[,]” Tubal

requested a price increase of $44,000 and advised Garrett that the metal soffit would

cost $1,700. Garrett responded by reminding Tubal “that the price they gave is a

fixed price that I gave to the district and I am now at risk for it and the fact that

mistakes were made on their bid can’t be [foisted] on me because my price is already

set with the school district.” Baker then negotiated further with Butler and G&G,

eventually agreeing to reduce Tubal’s profit. G&G then agreed to absorb $11,000 of

the cost increase, and the project proceeded.

When asked about Weldon’s threat to cancel the contract, Garrett confirmed

that Tubal “missed every single deadline that they gave to us[,]” they never provided

G&G a complete set of drawings, and did not provide all the necessary structural

steel, but Weldon lacked the power to cancel G&G’s purchase order. Garrett further

stated that he was not considering cancelling the contract at that time, although he

5 had testified otherwise during his deposition. When asked whether it was reasonable

for Tubal to have believed Weldon’s threat, Garrett responded that he would not

have believed it if he were in Tubal’s position.

G&G eventually retained Alliance to complete the project, at a cost of

$255,660. G&G chose to pay Alliance more than Tubal sought because, in Garrett’s

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Hernandez v. Lautensack
201 S.W.3d 771 (Court of Appeals of Texas, 2006)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Kroger Texas Ltd. Partnership v. Suberu
216 S.W.3d 788 (Texas Supreme Court, 2006)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
2 Fat Guys Investment, Inc. v. Klaver
928 S.W.2d 268 (Court of Appeals of Texas, 1996)
Arthur Andersen & Co. v. Perry Equipment Corp.
945 S.W.2d 812 (Texas Supreme Court, 1997)
Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC
363 S.W.3d 901 (Court of Appeals of Texas, 2012)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)
Ashford Partners, Ltd. v. Eco Resources, Inc.
401 S.W.3d 35 (Texas Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Tubal Cain Industries, Inc. v. J.W. Garrett & Son, Inc. D/B/A G&G Enterprises Construction Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tubal-cain-industries-inc-v-jw-garrett-son-inc-dba-gg-texapp-2025.