Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC

363 S.W.3d 901, 2012 WL 952821, 2012 Tex. App. LEXIS 2210
CourtCourt of Appeals of Texas
DecidedMarch 22, 2012
Docket09-11-00284-CV
StatusPublished
Cited by8 cases

This text of 363 S.W.3d 901 (Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC, 363 S.W.3d 901, 2012 WL 952821, 2012 Tex. App. LEXIS 2210 (Tex. Ct. App. 2012).

Opinion

OPINION

CHARLES KREGER, Justice.

This case requires us to decide whether a materialman to a subcontractor must give notice to the original contractor to perfect a lien and to recover on fund-trapping and retainage claims against the landowner. Because the statute that creates the rights of derivative suppliers requires timely notice to perfect a lien, we hold that a failure to provide notice in accordance with the statute precludes recovery.

Background

As a derivative claimant seeking to recover on invoices for materials provided to a subcontractor on a commercial construction contract, the appellant, Morrell Masonry Supply, Inc. (“Morrell”), brought statutory fund-trapping and retainage claims against the owner, Lupe’s Shenandoah Reserve, LLC (“Lupe’s”), and its insurer, Berkley Regional Insurance Company (“Berkley”). See Tex. Prop.Code Ann. §§ 53.084, 53.105, 53.151 (West 2007 & *904 Supp. 2011). 1 After denying Morrell’s motion for summary judgment, the trial court granted an interlocutory take-nothing partial summary judgment on Morrell’s claim for $14,021.08 for materials provided in October 2008. See Tex. Prop.Code Ann. § 53.160 (West Supp. 2011). The remaining issues were tried to the court, which (1) ordered Lupe’s to unconditionally tender to Morrell the sum of $6,698.25 for materials provided in November 2008, (2) awarded to Morrell attorneys’ fees in the amount of $2,000 for fees incurred collecting the invoice for materials provided in November 2008, (3) ordered that Morrell take nothing on its claim against Lupe’s for materials provided in October 2008, (4) ordered the release and discharge of Mor-rell’s mechanic’s and materialman’s lien upon payment of $6,698.25, (5) ordered the release of the indemnity bond and discharge from liability of Berkley and the original contractor, Comanche Construction, L.P. (“Comanche”), and (6) awarded to Lupe’s attorneys’ fees and expenses in the amount of $32,452.93 incurred defending against Morrell’s claims relating to the October 2008 invoices. Morrell raises five issues on appeal.

Pre-Lien Notice and Fund-Trapping

Morrell alleged that Lupe’s hired Comanche as a general contractor to construct improvements on the property subject to Morrell’s lien claim. Comanche hired Joyce’s Stucco Design (“Joyce’s”) to complete a portion of the improvements. Joyce’s obtained materials from Morrell but refused to pay for them. The summary judgment record established that on January 13, 2009, Morrell mailed a notice of claim to Lupe’s, Comanche, and Joyce’s, for unpaid invoices totaling $20,719.33. Morrell’s pleadings allege invoices in the sum of $14,021.08 were dated October 2008 and invoices totaling $6,698.25 reflect the billed price for materials delivered in November 2008.

To perfect a lien under Chapter 53 of the Texas Property Code, a person must comply with Subchapter C of Chapter 53. See Tex. Prop.Code Ann. § 53.051-058 (West 2007 & Supp. 2011). Section 53.056 of the Property Code governs the notice required for a derivative claimant’s lien to be valid. See id. § 53.056(a). (“[A] claimant other than an original contractor must give the notice prescribed by this section for the lien to be valid.”). First, “[tjhe claimant must give the notice [to the original contractor] not later than the 15th day of the second month following each month in which all or part of the claimant’s labor was performed or material delivered.” Id. § 53.056(b). Then “[t]he claimant must give the same notice to the owner or reputed owner and the original contractor not later than the 15th day of the third month following each month in which all or part of the claimant’s labor was performed or material or specially fabricated material was delivered.” Id. The notice that Mor-rell mailed to Comanche and Lupe’s was timely as a three-month notice but was untimely as a two-month notice. See id.

Morrell contends that its failure to notify Comanche of Morrell’s lien claim by December 15, 2008 does not affect the validity of its lien. Morrell reasons that it perfected its fund-trapping claim by sending to both Lupe’s and Comanche notice of its claim for materials delivered in October 2008 within ninety days after that indebtedness accrued. See id. § 53.053(c). Mor-rell contends that its lien is valid because Comanche failed to dispute the claim by sending written notice to Lupe’s within thirty days of Morrell’s January 13, 2009 notice. See id. § 53.083(b). However, *905 Section 58.083(d) provides that a demand cannot be made unless the lien has been secured. See id. § 53.083(d) (“Unless the lien has been secured, the demand may not be made after expiration of the time within which the claimant may secure the lien for the claim.”). Under the express conditions of the statute, Morrell’s right to trap funds payable by the owner to the original contractor depends upon Morrell having “secured” a lien. See id.

Morrell argues that this court’s holding in Don Hill Construction Company v. Dealers Electrical Supply Company governs this case as binding precedent. See 790 S.W.2d 805 (Tex.App.-Beaumont 1990, no writ). In Don Hill, the materialman who supplied a subcontractor sent a late first notice of non-payment to the original contractor. Id. at 806. This Court held that the materialman’s failure to provide the first notice to the original contractor did not affect the liability of an owner who received the three-month notice. Id. at 809-10. The original contractor received the three-month notice but did not dispute the claim. Id. at 810. The opinion refers to Section 53.084, which states that the owner’s property is subject to a claim for money paid to the original contractor after the owner becomes authorized to withhold funds, but such opinion fails to explain how the lien had been secured as required by the statute. Id.; see Tex. Prop.Code Ann. § 53.084(b).

“Because a subcontractor is a derivative claimant and, unlike a general contractor, has no constitutional, common law, or contractual lien on the property of the owner, a subcontractor’s lien rights are totally dependent on compliance with the statutes authorizing the lien.” First Nat’l Bank in Graham v. Sledge, 653 S.W.2d 283, 285 (Tex.1983). “[Substantial compliance with the statutes is sufficient to perfect a lien under the Act.” Id. “To determine whether the subcontractors have valid liens, we must compare the steps the subcontractors took to perfect their liens with the statutory requirements.” Id. at 286.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
363 S.W.3d 901, 2012 WL 952821, 2012 Tex. App. LEXIS 2210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrell-masonry-supply-inc-v-lupes-shenandoah-reserve-llc-texapp-2012.