MORRELL MASONRY SUPPLY, INC. v. Loeb

349 S.W.3d 664, 2011 WL 2899003
CourtCourt of Appeals of Texas
DecidedSeptember 28, 2011
Docket14-10-00117-CV
StatusPublished
Cited by4 cases

This text of 349 S.W.3d 664 (MORRELL MASONRY SUPPLY, INC. v. Loeb) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MORRELL MASONRY SUPPLY, INC. v. Loeb, 349 S.W.3d 664, 2011 WL 2899003 (Tex. Ct. App. 2011).

Opinion

OPINION

JEFFREY V. BROWN, Justice.

Appellant Morrell Masonry Supply, Inc., appeals the judgment from a bench trial in which the trial judge concluded the appellant should take nothing in its breach-of-contract claim against the Loebs. On appeal, Morrell contends the trial court erred by (1) failing to take full judicial notice of a construction contract between the Loebs and Cellar Door Homes, Inc.; (2) concluding Morrell never gave the Loebs timely notice of its lien claim; (3) concluding Mor-rell never gave timely notice nor perfected a claim to any retainage funds required to be held by the Loebs; (4) concluding Mor-rell’s lien claim on the Loebs’ homestead was null and void; and (5) awarding attorney’s fees to the Loebs. We affirm.

I

This is a construction-industry contract case. Cedrick and Sabrina Loeb, husband and wife, contracted with Cellar Door Homes, Inc., to build them a new home. Cellar Door, the original contractor for the project, in turn hired a stucco subcontractor who purchased materials on credit from Morrell. 1 But the subcontractor never paid for the materials, leaving a balance of $8,476.74.

Morrell sent the Loebs and Cellar Door notice of its claim against the stucco subcontractor via certified mail. The notice further informed the Loebs that, as owners of the property, they may be held personally liable for the debt and a lien may be attached to their property. The notice included copies of unpaid invoices ranging from August 21 to November 10, 2007. The Loebs signed for the notice of the unpaid balance on January 15, 2008. After receiving the notice, the Loebs authorized the release of the remaining $54,514 balance of their construction funds to Cellar Door. On February 11, 2008, Morrell attempted to file a lien on the Loebs’ homestead, and on March 12, 2008, Morrell sued the Loebs and Cellar Door, seeking foreclosure on its materialman’s lien. Morrell also sought quantum-meruit damages as well as damages for misapplication of construction-trust funds under Chapter 162 of the Texas Property Code, and further requested an award of statutory interest on the unpaid balance.

After a bench trial for which Cellar Door never appeared, the trial court concluded Morrell should take nothing and *667 awarded the Loebs attorney’s fees. The trial judge filed findings of fact and conclusions of law reflecting the court’s conclusion that Morrell did not give the Loebs timely notice of its lien claim or its claim to retainage funds the Loebs were statutorily required to withhold. The trial court further concluded Morrell never perfected a valid lien on the Loebs’ homestead and that its lien claim was null and void because it failed to satisfy requirements outlined by the Property Code.

II

A

We first address Morrell’s second issue, in which it argues the trial court erred in concluding Morrell never gave the Loebs timely notice of its lien claim. Because a derivative claimant has no contractual relationship with the property owner, the claimant is required to give the property owner timely notice of an unpaid balance before attempting to file a lien against the property. 2 See Tex. Prop.Code § 53.252(b). A claimant must serve timely notice for a subsequently filed lien to be valid. See Tex. Prop.Code § 53.252(a). Section 53.252 of the Property Code requires claimants other than the original contractor to provide the property owner with written notice of the unpaid balance “not later than the 15th day of the second month following each month in which all or part of the claimant’s labor was performed or material or specially fabricated material was delivered.” Tex. Prop.Code § 53.252(b).

The $8,476.74 unpaid balance Morrell claims it is owed is reflected through a series of thirteen invoices beginning on August 21, 2007, and ending on November 10, 2007. The trial court found Morrell failed to give the Loebs timely notice of the unpaid balance documented by the individual invoices except for the last invoice, which is dated November 10, 2007, and reflects a balance of $326.60. 3 Morrell gave the Loebs notice of its lien claim via certified mail in a letter dated January 9, 2008, with the “green card” reflecting the Loebs received the notice on January 15, 2008. The first twelve invoices are dated in the months of August, September, and October of 2007. Accordingly, the notice deadline was October 15, 2007 for the August invoices; November 15, 2007 for the September invoices; and December 15, 2007 for the October invoices. See Tex. Prop.Code § 53.252(b). The due date for the lone November 2007 invoice was January 15, 2008; therefore, the notice of lien claim was sufficient only as to the November 2007 invoice for $326.60. Id. The trial court did not err in calculating the statutory deadlines for notice of a lien claim under section 53.252(a) of the Property Code.

Additionally, the trial found the pre-lien claim notice insufficient because it did not include the complete statutory notice required by section 53.254(g) of the Property Code, which we include here in full:

*668 For the lien on a homestead to be valid, the notice required to be given to the owner under Section 53.252 must include or have attached the following statement:
“If a subcontractor or supplier who furnishes materials or performs labor for construction of improvements on your property is not paid, your property may be subject to a lien for the unpaid amount if:
(1) after receiving notice of the unpaid claim from the claimant, you fail to withhold payment to your contractor that is sufficient to cover the unpaid claim until the dispute is resolved; or
(2) during construction and for 30 days after completion of construction, you fail to retain 10 percent of the contract price or 10 percent of the value of the work performed by your contractor. “If you have complied with the law regarding the 10 percent retainage and you have withheld payment to the contractor sufficient to cover any written notice of claim and have paid that amount, if any, to the claimant, any lien claim filed on your property by a subcontractor or supplier, other than a person who contracted directly with you, will not be a valid lien on your property. In addition, except for the required 10 percent retainage, you are not liable to a subcontractor or supplier for any amount paid to your contractor before you received written notice of the claim.”

Tex. Prop.Code § 53.254(g) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sommers v. Aguirre (In re Santoyo)
540 B.R. 284 (S.D. Texas, 2015)
Monaco v. Monaco (In re Monaco)
514 B.R. 477 (W.D. Texas, 2014)
Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC
363 S.W.3d 901 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
349 S.W.3d 664, 2011 WL 2899003, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrell-masonry-supply-inc-v-loeb-texapp-2011.