Hadnot v. Wenco Distributors

961 S.W.2d 232, 1997 WL 167401
CourtCourt of Appeals of Texas
DecidedJuly 23, 1997
Docket01-96-00317-CV
StatusPublished
Cited by16 cases

This text of 961 S.W.2d 232 (Hadnot v. Wenco Distributors) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hadnot v. Wenco Distributors, 961 S.W.2d 232, 1997 WL 167401 (Tex. Ct. App. 1997).

Opinion

OPINION

HEDGES, Justice.

Appellants, Thomas and Gay Hadnot, appeal a judgment rendered in favor of appel-lees, a group of four subcontractors. Appel-lees sued the Hadnots to recover amounts owed to them for materials and labor provided for the Hadnots’ new home and to foreclose upon liens that appellees had on the new home. After a bench trial, the trial court found that the Hadnots owed appellees for the materials and labor and entered a judgment establishing and foreclosing appel-lees’ liens. On appeal, the Hadnots argue that (1) the trial court erred in not making various findings of fact and conclusions of law; (2) there was no evidence to support the judgment; and (3) the trial court erred in awarding attorney’s fees to the appellees. We reform the judgment and, as reformed, affirm.

FACTS

On July 16,1993, Thomas and Gay Hadnot entered into a mechanic’s lien contract with The Magnificent Seven Corporation, a Texas corporation d/b/a Gibraltar Homes (“Gibraltar”) to build a new home (the property) for $189,260. On March 21,1994, Gibraltar completed the house. That afternoon, the Had-nots paid Gibraltar in full, including $20,000 in “extras” for the house and then closed their permanent home loan. On April 11, 1994, appellee Hall’s Carpet Haus, Inc. (“Hall”) sent the Hadnots notice of an unpaid indebtedness for labor and materials it supplied to the property. On April 22, 1994, appellee M & M Lighting, Inc. (“M & M Lighting”) sent its notice, on April 27, 1994, appellee Wenco Distributors (‘Wenco”) sent its notice, and on April 28,1994, and again on June 3, appellee Dan’s Plumbing, Inc. (“Dan”) sent its notice. The Hadnots received Hall’s and Dan’s notices “timely,” Wenco’s notice on May 3, and M & M Lighting’s notice on May 4. On May 3, Wenco and M & M Lighting filed mechanic’s liens on the property. Hall and Dan filed mechanic’s Hens on the property May 13 and June 17, respectively. All appellees later sued the *234 Hadnots to collect the unpaid indebtedness and to establish and foreclose their liens. After a bench trial, the trial court rendered judgment for the appellees on their money claims and their foreclosures.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

In point of error one, the Hadnots contend that the trial court erred in not making a finding of fact that appellees’ claims against Gibraltar, the general contractor, had been reduced to a final judgment. Specifically, the Hadnots argue that appellees were required to pursue a final judgment on their claims against Gibraltar before the Hadnots would be liable to appellees for any unpaid indebtedness against the property under Tex. PROP.Code Ann. § 58.084(b) (Vernon 1995).

The record belies the Hadnots’ literal contention. Included in the trial court’s findings of fact were the following:

3. Gibraltar is not a party to this suit, and none of the Plaintiffs and Cross-Defendants [Appellees] have obtained a final judgment against Gibraltar for their claims against Gibraltar for materials which such Plaintiffs and Cross-Defendants [Appel-lees] sold to Gibraltar for use in the construction of the Hadnot Residence and which indebtedness forms the basis of each of the Mechanics’ Liens Claims which the various Plaintiffs and Cross-Defendants [Appellees] have caused to be filed of record against the property on which the Hadnot Residence is located.
4. None of the Plaintiffs and Cross-Defendants had any suit pending against Gibraltar on the date of the trial of this case, for their claims against Gibraltar for materials which were sold by the Plaintiffs [Ap-pellees] to Gibraltar for use in the construction of the Hadnot Residence.

If we were to agree with the Hadnots’ contention that the appellees must have pursued claims against Gibraltar to a final judgment before proceeding against the Hadnots, then the above findings would support that contention. The essence of the Hadnots’ contention in point of error one, then, is not that the trial court erred in not making a finding of fact, but rather that the trial court erred in rendering judgment for appellees because the trial court’s findings of fact established that the Hadnots were not liable.

Sources of Funds

Under the mechanic’s, contractor’s, and materialman’s lien statutes, 1 there are two sources of funds to which a derivative claimant may look for recovery from an owner. First Nat’l Bank v. Sledge, 653 S.W.2d 283, 286 (Tex.1983); see Tex. PROP.Code Ann. § 53.101 et seq (Vernon 1995); Tex. PROP. Code Ann. § 53.081 et seq (Vernon 1995).

Ten Percent Retainage

Under section 53.101 (“Statutory Retain-age Statute”), an owner, under an original contract for which a mechanic’s lien may be claimed, is required to retain 10 percent of the contract price of the work to the owner or 10 percent of the value of the work during the progress of work and for 30 days after the work is completed. Tex. Prop.Code Ann. § 53.101 (Vernon 1995). The retained funds secure the payment of artisans and mechanics who perform labor or service and the payment of other persons who furnish material, material and labor, or specially fabricated material for any contractor, subcontractor, agent, or receiver in the performance of the work. Tex. Prop.Code Ann. § 53.102 (Vernon 1995). A claimant has a lien on the retained funds if the claimant (1) sends the notices required by this chapter in the time and manner required; and (2) files an affidavit claiming a lien not later than the 30th day after the work is completed. Tex. Prop.Code Ann. § 53.103 (Vernon 1995). If the owner does not comply with this subchapter, the claimants complying with this chapter have a lien, at least to the extent of the amount that should have been retained from the original contract under which they are claiming, against the house, building, structure, fixture, or improvements and all of its properties and against the lot or lots of land necessarily connected. Tex. Prop.Code Ann. § 53.105(a) (Vernon 1995).

*235 If the lien claim arises from a debt incurred by the original contractor, the claimant must give notice to the owner or reputed owner, with a copy to the original contractor. Tex. Prop.Code Ann. § 53.056(c) (Vernon 1995). The claimant must give the same notice to the owner or reputed owner and the original contractor not later than the 15th day of the third month following each month in which all or part of the claimant’s labor was performed or material or specially fabricated material was delivered. Tex. Prop. Code Ann. § 53.056

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Long Q. Pham and Thao M. Silva v. Harris County Rentals, L.L.C.
455 S.W.3d 702 (Court of Appeals of Texas, 2014)
MORRELL MASONRY SUPPLY, INC. v. Loeb
349 S.W.3d 664 (Court of Appeals of Texas, 2011)
Stewart Title Guaranty Co. v. Hadnot
101 S.W.3d 642 (Court of Appeals of Texas, 2003)
Raymond v. Rahme
78 S.W.3d 552 (Court of Appeals of Texas, 2002)
Stolz v. Honeycutt
42 S.W.3d 305 (Court of Appeals of Texas, 2001)
Douglas Harris Aiken v. State
Court of Appeals of Texas, 2000
Aiken v. State
36 S.W.3d 131 (Court of Appeals of Texas, 2000)
Crain v. UPLC
11 S.W.3d 328 (Court of Appeals of Texas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
961 S.W.2d 232, 1997 WL 167401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hadnot-v-wenco-distributors-texapp-1997.