James Mechanical Contractors, Inc. v. Tate

647 S.W.2d 347, 1982 Tex. App. LEXIS 5503
Court of Appeals of Texas·Decided December 9, 1982·No. 2351 CV·Published·Cited by 4 cases

Opinion

OPINION

YOUNG, Justice.

James Mechanical Contractors, Inc., brought an action against Mike Tate for the enforcement of a mechanic’s and material-men’s lien. He appeals from a take nothing judgment. We affirm.

The record shows that James is a plumbing subcontractor, who entered into an agreement with Roy Jackson Construction Company, a general contractor, to install the plumbing in Mike Tate’s new home. This contract provided that the work would be done and payment made in three stages. Each payment was to be $8,152.00. James did the work and received the first two payments less a 10% retainage. Jackson made the payments; the appellant had no contract with Tate, the home owner.

In November of 1979, Tate terminated his agreement with Jackson and hired another general contractor. Although James had completed its plumbing work by this time, Jackson had not paid him for the third stage of his work nor had he remitted the 10% retainage withheld from the first two stages. The third stage of the work was done by James in August and September of 1979.

James filed an affidavit for a mechanic’s and materialmen’s lien on December 7,1979 and mailed a single copy to Tate. He also sent Tate notice and demand for payment on December 5, 1979.

The trial court concluded that James did not give Tate proper notice of its claim as required by statute. The applicable statute, Tex. Rev. Civ. Stat.Ann. Art. 5453 (Vernon Supp.1982) in pertinent part provides:

“The lien provided for in Article 5452 (describing liens) may be fixed and secured in the following manner:
1. Every ... subcontractor who may be entitled to a lien under this Act, not later than ninety (90) days, after the indebtedness accrues as defined hereinafter in Article 5467, shall file his affidavit claiming a lien, to be recorded in a book kept by the county clerk for that purpose in the office of the county clerk of the *349 county m which such property is located ... and he shall send to the owner by certified or registered mail, addressed to his last known business or residence address, two (2) copies of such affidavit claiming a lien....
2. If the claimant for such lien is other than an original contractor, such claim shall not be valid or enforceable unless the claimant shall also have complied with the applicable notice requirements hereafter set forth which shall be conditions precedent to the validity of such claims:
⅝: ⅜ ⅜ * ⅜ ⅜
b. Excepting instances of retainages for which notices have been given in accordance with the preceding subpara-graph, the claimant shall give the applicable notice or notices described, as follows:
(1) Where the claim consists of a lien claim arising from a debt incurred by a subcontractor, the claimant shall give written notice of the unpaid balance of such claim to the original contractor not later than thirty-six (36) days after the tenth (10th) day of the month next following each month in which claimant’s labor was done or performed in whole or in part or his material delivered in whole or in part; and claimant shall give a like notice to owner not later than ninety (90) days after the tenth (10th) day of the month next following each month in which the claimant’s labor was done or performed in whole or in part or his material delivered in whole or in part.
(2) Where the claim consists of a lien claim arising from a debt incurred by the original contractor, no such notice need be given to the contractor but notice to the owner, as prescribed in paragraph 2b(l) of this Article will be sufficient.
Such notices shall be sent by certified or registered mail, addressed to the owner, and where required by this Article to the original contractor, at their last known business or residence address. A copy of the statement or billing in the usual and customary form shall suffice as a notice under this subparagraph; provided, however, if such statement or billing is to be effective to authorize an owner to retain funds for the payment of such claim as provided in Article 5463 of this Act, it shall contain or be accompanied by some form of statement to an owner to the effect that if the bill remains unpaid he may be personally liable and his property subjected to a lien unless he withholds payments from the contractor for the payment of such statement or unless the bill is otherwise paid or settled.”

Tex.Rev.Civ.Stat.Ann. Art. 5467 (Vernon Supp.1982), provides that indebtedness accrues on the tenth day of the month next following the month in which the labor was performed or the material furnished.

In order to comply with the statute, James was required to file its affidavit not later than ninety days after the tenth day of the month after the labor was performed. The appellant clearly met this deadline for the work done in August and September of 1979 by filing the affidavit on December 7, 1979. Although James should have mailed two copies of the affidavit to Tate, the notice and demand for payment requirements were complied with.

When considering mechanic’s and materialmen’s lien statutes, including those governing affidavits necessary to perfect liens, substantial compliance is required. Conn, Sherrod & Co. v. Tri-Electric Supply Co., 535 S.W.2d 31, 35 (Tex.Civ.App.—Tyler 1976, writ ref’d n.r.e.). James met all the requirements of Art. 5453 except that it sent only one copy of the affidavit to Tate. We hold that this was substantial compliance.

Free access — add to your briefcase to read the full text and ask questions with AI

James Mechanical Contractors, Inc. v. Tate, 647 S.W.2d 347, 1982 Tex. App. LEXIS 5503 (Tex. Ct. App. 1982).

647 S.W.2d 347 (James Mechanical Contractors, Inc. v. Tate) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hadnot v. Wenco Distributors
961 S.W.2d 232 (Court of Appeals of Texas, 1997)
Tribble & Stephens Co. v. Consolidated Services, Inc.
744 S.W.2d 945 (Court of Appeals of Texas, 1987)
Cabintree, Inc. v. Schneider
728 S.W.2d 395 (Court of Appeals of Texas, 1986)