First National Bank in Graham v. Sledge

653 S.W.2d 283, 26 Tex. Sup. Ct. J. 463, 1983 Tex. LEXIS 302
CourtTexas Supreme Court
DecidedJune 22, 1983
DocketC-536
StatusPublished
Cited by80 cases

This text of 653 S.W.2d 283 (First National Bank in Graham v. Sledge) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Bank in Graham v. Sledge, 653 S.W.2d 283, 26 Tex. Sup. Ct. J. 463, 1983 Tex. LEXIS 302 (Tex. 1983).

Opinion

CAMPBELL, Justice.

This is a mechanic’s and materialman’s statutory lien case. The First National Bank in Graham sued the owner, Guy Meac-ham, and five subcontractors to remove a cloud from title to land caused by lien affidavits filed by the subcontractors. Alternatively, the Bank sought declaratory judgment that the mechanic’s and material-man’s contract lien which it holds is superi- or to the statutory liens of the subcontractors. The subcontractors counterclaimed against the Bank for foreclosure of their mechanic’s and materialman’s liens and cross-claimed against Meacham for attorney’s fees. The trial court rendered judgment for the subcontractors on both claims. The court of civil appeals affirmed the trial court judgment. 616 S.W.2d 954. We reform the judgments of the courts below with respect to the subcontractors’ lien claims and, as reformed, affirm. We reverse the judgments of the courts below with respect to attorney’s fees and render *285 judgment that the subcontractors take nothing on their cross-claim.

Meacham, the owner of two lots in Graham, Texas, contracted with Harris, a general contractor, to build a house on each lot. The contract price was $23,383 per house. Meacham and Harris executed a mechanic’s lien contract for each lot and Meacham gave Harris a mechanic’s lien note for each contract. Harris assigned the mechanic’s lien contracts and notes to the First National Bank as collateral for interim construction money advanced to Harris. Harris completed one house, but took bankruptcy before completing the other. The subcontractors, unpaid, filed lien affidavits in the Young County lien records. The subcontractors then mailed a copy of each lien affidavit to Meacham.

Our first question is whether the subcontractors have perfected statutory liens under the Hardeman Act. 1 Because a subcontractor is a derivative claimant and, unlike a general contractor, has no constitutional, common law, or contractual lien on the property of the owner, a subcontractor’s lien rights are totally dependent on compliance with the statutes authorizing the lien. Da-Col Paint Manufacturing Co. v. American Indemnity Co., 517 S.W.2d 270 (Tex.1974). However, substantial compliance with the statutes is sufficient to perfect a lien under the Act. Conn, Sherrod & Co. v. Tri-Electric Supply Co., 535 S.W.2d 31 (Tex.Civ.App.—Tyler 1976, writ ref’d n.r.e.).

We have set out the applicable statutes in the margin. 2 These statutes are very lengthy, have been subjected to several re *286 visions, and are not exactly a model of clarity.

The Act provides two methods by which a subcontractor can perfect a lien on the owner’s property. Article 5463 is a “trapping” statute. It provides the subcontractors can trap, in the owner’s hands, funds payable to the general contractor if the owner receives notice from the subcontractors that they are not being paid. If the owner pays any money to the general contractor after receiving notice from the subcontractors, the owner’s property will be subject to a lien to the extent of the money paid. Article 5469, often referred to as the “retainage” statute, is a duty statute. It provides that it shall be the duty of the owner to retain 10% of the contract price owing to the general contractor, and that the fund be retained in the owner’s hands for 30 days after the work is completed. This duty is imposed on the owner with or without notice of a claim. If the owner fails in this duty to retain, then the owner may be liable and his property subject to a lien, at least to the extent of 10%, to secure payment of the subcontractor’s claims. The amount trapped under article 5463 may exceed the 10% required to be retained by article 5469.

To determine whether the subcontractors have valid liens, we must compare the steps the subcontractors took to perfect their liens with the statutory requirements. The subcontractors last furnished labor or material in October 1973. By November 1,1973, they had filed their lien affidavits in the mechanic’s and materialman’s lien records of Young County. The form of each of the lien affidavits is essentially the same. Each affidavit claimed a lien for “labor performed and materials furnished,” and each contained a numbered paragraph 1 giving the “items of the claim” as in the following example:

AMOUNT DATE OF

CLAIMED ITEM OF THE CLAIM PERFORMANCE

$465.00 Labor and Materials October 26,1972

Total of such amount claimed $465.00. A copy of invoice is attached hereto and marked “Exhibit A”, and made a part hereof as though copied in full.

The only notices sent to Meaeham within the statutory time limit consisted of one *287 copy of each subcontractor’s lien affidavit without the invoice copies attached. These notices did not contain the statutory warning that unless Meacham paid the claim or it was otherwise settled he might be held personally liable and his property subjected to a lien.

We hold the subcontractors have not perfected a lien under article 5463. Article 5463, paragraph 1 provides:

When notices of claims sent under the provisions of paragraph 2 of Article 5453 of this Act are received by the owner, he shall be authorized to retain in his hands the amount or amounts of money necessary to pay said claims from payments or part-payments to the original contractor....

What are the notice requirements of paragraph 2 of article 5453? It provides, if the lien claimant is a subcontractor, the claim

shall not be valid or enforceable unless the claimant shall also have complied with the applicable notice requirements hereafter set forth which shall be conditions precedent to the validity of such claims[.]

The notice requirement “hereafter set forth” is paragraph 2b(2) of article 5453, which provides in part:

A copy of the statement or billing in the usual and customary manner shall suffice as a notice under this subparagraph; provided, however, if such statement or billing is to be effective to authorize an owner to retain funds for the payment of such claim as provided in Article 5463 of this Act, it shall contain or be accompanied by some form of statement to an owner to the effect that if the bill remains unpaid he may be personally liable and his property subjected to a lien unless he withholds payments from the contractor for the payment of such statement or unless the bill is otherwise paid or settled.

The statutory warning is a condition precedent; without it no lien can be imposed under article 5463. See Trinity Universal Insurance Co. v. Palmer, 412 S.W.2d 691 (Tex.Civ.App.—San Antonio 1967, writ ref’d n.r.e.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schear Hampton Drywall, LLC v. Founders Commercial, LTD
Court of Criminal Appeals of Texas, 2018
Sommers v. Aguirre (In re Santoyo)
540 B.R. 284 (S.D. Texas, 2015)
Long Q. Pham and Thao M. Silva v. Harris County Rentals, L.L.C.
455 S.W.3d 702 (Court of Appeals of Texas, 2014)
Crawford Services, Inc. v. Skillman International Firm, L.L.C.
444 S.W.3d 265 (Court of Appeals of Texas, 2014)
Lyda Swinerton Builders, Inc. v. Cathay Bank
409 S.W.3d 221 (Court of Appeals of Texas, 2013)
Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, LLC
363 S.W.3d 901 (Court of Appeals of Texas, 2012)
MORRELL MASONRY SUPPLY, INC. v. Loeb
349 S.W.3d 664 (Court of Appeals of Texas, 2011)
Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc.
295 S.W.3d 763 (Court of Appeals of Texas, 2009)
Truss World, Inc. v. ERJS, INC.
284 S.W.3d 393 (Court of Appeals of Texas, 2009)
Mustang Tractor & Equipment Co. v. Hartford Accident & Indemnity Co.
263 S.W.3d 437 (Court of Appeals of Texas, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
653 S.W.2d 283, 26 Tex. Sup. Ct. J. 463, 1983 Tex. LEXIS 302, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-bank-in-graham-v-sledge-tex-1983.