Addison Urban Development Partners, LLC v. Alan Ritchey Materials Company, LC

437 S.W.3d 597, 2014 WL 2946019, 2014 Tex. App. LEXIS 7156
CourtCourt of Appeals of Texas
DecidedJuly 1, 2014
Docket05-13-00122-CV
StatusPublished
Cited by6 cases

This text of 437 S.W.3d 597 (Addison Urban Development Partners, LLC v. Alan Ritchey Materials Company, LC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Addison Urban Development Partners, LLC v. Alan Ritchey Materials Company, LC, 437 S.W.3d 597, 2014 WL 2946019, 2014 Tex. App. LEXIS 7156 (Tex. Ct. App. 2014).

Opinion

OPINION

Opinion by

Justice FITZGERALD.

This appeal follows a bench trial involving a dispute over a statutory construction materials lien. In eight issues, Addison Urban Development Partners, LLC (“Addison”) asserts the trial court erred in awarding judgment to Alan Ritchey Materials Company, LC (“Ritchey”). We affirm the trial court’s judgment.

BACKGROUND

Addison owns the real property known as the Meridian Square Project (the “Property”), a subdivision development in Addison, Texas. Addison contracted with ForceCon Services, LLC (“ForceCon”) for paving, excavation, street lights, and other work in constructing improvements on the Property (the “Project”). Pursuant to its contract with Addison, ForceCon provided concrete for use on the Project.

Concrete consists of several materials, including sand and gravel. ForceCon ordered ingredients for concrete from several materialmen, and prepared the concrete for use in the Project through a process called “batching.” ForceCon was forced to batch concrete for the Project at an off-site batch plant because Addison limited ForceCon’s workspace in its paving subcontract. Addison knew its concrete was not being batched on the Project site.

Ritchey is one of the materialmen that contracted with ForceCon to supply materials to make concrete for the Project. The materials to be provided included concrete sand and 1" and 1 1/2" rock gravel. 1 Pursuant to the contract, ForceCon was to pay a unit price per ton of material delivered for the Project. This unit price included a fuel surcharge that was tied to a price index related to diesel fuel. Variations in the fuel surcharge would cause the final per-ton price of the delivered material to increase or decrease.

ForceCon ordered materials from Rit-chey from July 22, 2009 through September 11, 2009 for a total price of $114,470.66. Despite demands for payment, Ritchey was not paid for any of these materials. Therefore, Ritchey provided statutory notice to ForceCon and Addison concerning ForceCon’s failure to pay. Ritchey then filed a lien in the total amount of $114,470.66, and notified Addison of the filing.

Addison initiated this lawsuit against Ritchey, ForceCon, and another subcontractor. With regard to Ritchey, Addison claimed that the total value of the materials used on the Project had a total contract value of $65,155.67, and Ritchey’s $114,470.66 lien on the Project exceeded that amount. Ritchey answered and coun *600 terclaimed against Addison for foreclosure of the lien and cross-claimed against ForceCon for breach of contract and a sworn account. The parties were subsequently realigned, with Ritchey designated as plaintiff and Addison as defendant. The claims between the other subcontractor and Addison were settled at mediation, and the court granted a default judgment in favor of Ritchey against ForceCon. Thus, only Ritchey’s claims against Addison remained.

The parties filed a joint trial stipulation of facts and a stipulation of evidence. The parties also filed a document entitled “Agreed Motion for Procedure for Resolution Based Upon Joint Trial Stipulations.” The motion requested that the court admit the stipulated evidence, and set deadlines for briefing on the stipulated evidence and the submission of attorney’s fees affidavits. The trial court granted the motion and admitted the stipulated evidence.

The court signed a final judgment on October 31, 2012. The judgment incorporates the interlocutory default judgment awarding Ritchey judgment against Force-Con, and awards Ritchey attorney’s fees against ForceCon. The judgment further awards Ritchey $114,470.66, plus pre- and post-judgment interest jointly and severally against Addison and ForceCon, and attorney’s fees against Addison. The judgment concludes that Ritchey’s lien against the Property is valid and enforceable, and decrees that judgment foreclosing the lien is granted. Addison moved for a new trial, and the trial court made findings of fact and conclusions of law.

STANDARD OF REVIEW

Before we begin our analysis, we must first determine the standard of review. Addison asserts this case was submitted to the trial court as an agreed case under rule 263. See Tex.R. Civ. P. 263. Ritchey disagrees, arguing that the parties did not agree to all the facts. Ritchey relies on two items that purportedly support its position; a single sentence from the stipulation that states “Ritchey contends that ... materials were ordered and delivered for use on the project” and the fact that Addison raises factual sufficiency points on appeal. We are not persuaded by Ritchey’s argument. The case was submitted to the court on the parties’ joint trial stipulation and the stipulated evidence. The joint trial stipulation presented to the court states, in pertinent part, “[w]ith these stipulations, Alan Ritchey Materials and Addison believe that all that remain are issues of law.” In addition, the parties’ agreed motion for resolution based on joint trial stipulations states, “[with the exception of attorney’s fees, to be submitted at a later date], the parties believe that all evidence ... needed for adjudication of this matter is now before the Court.”

“An agreed statement of facts under rule 263 is similar to a special verdict; it is the parties’ request for judgment under the applicable law.” State Farm Lloyds v. Kessler, 932 S.W.2d 732, 735 (Tex.App.-Fort Worth 1996, writ denied) (citing Chiles v. Chubb Lloyds Ins. Co., 858 S.W.2d 633, 634 (Tex.App.-Houston [1st Dist.] 1993, writ denied)). In a rule 263 agreed case, the only issue on appeal is whether the district court properly applied the law to the agreed facts. See id.; Chiles, 858 S.W.2d at 635. In such a case, this Court is limited to consideration of those agreed facts. See Taylor v. First Cmty. Credit Union, 316 S.W.3d 863, 866 (Tex.App.-Houston 2010, no pet.). Such a review is less deferential to the trial court, because a “trial court has no discretion in deciding what the law is or in properly applying it.” Kessler, 932 S.W.2d at 735 (citing Walker v. Packer, 827 S.W.2d 833, 840 (Tex.1992)). If the trial court files *601 findings of fact in an agreed case, they are disregarded by the appellate court. Davis v. State, 904 S.W.2d 946, 950 (Tex.App.Austin 1995, no writ). Rule 263 provides in its entirety:

Parties may submit matters in controversy to the court upon an agreed statement of facts filed with the clerk, upon which judgment shall be rendered as in other cases; and such agreed statement signed and certified by the court to be correct and the judgment rendered thereon shall constitute the record of the cause.

Tex.R. Civ. P. 263.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
437 S.W.3d 597, 2014 WL 2946019, 2014 Tex. App. LEXIS 7156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/addison-urban-development-partners-llc-v-alan-ritchey-materials-company-texapp-2014.