Adams and Reese LLP, Adam Massey, and Cassandra Walsh v. Emerald Electrical Consultants LLC

CourtCourt of Appeals of Texas
DecidedApril 2, 2024
Docket14-22-00741-CV
StatusPublished

This text of Adams and Reese LLP, Adam Massey, and Cassandra Walsh v. Emerald Electrical Consultants LLC (Adams and Reese LLP, Adam Massey, and Cassandra Walsh v. Emerald Electrical Consultants LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adams and Reese LLP, Adam Massey, and Cassandra Walsh v. Emerald Electrical Consultants LLC, (Tex. Ct. App. 2024).

Opinion

Affirmed and Memorandum Opinion filed April 2, 2024.

In The

Fourteenth Court of Appeals

NO. 14-22-00741-CV

ADAMS AND REESE LLP, ADAM MASSEY, AND CASSANDRA WALSH, Appellants

V.

EMERALD ELECTRICAL CONSULTANTS LLC, Appellee

On Appeal from the 113th District Court Harris County, Texas Trial Court Cause No. 2022-25539

MEMORANDUM OPINION

Emerald Electrical Consultants LLC sued its attorneys Adam Massey and Cassandra Walsh, and the attorneys’ firm Adams and Reese LLP, for legal malpractice. The Firm and the attorneys moved to dismiss the claims pursuant to the Texas Citizens Participation Act (TCPA) on the ground that Emerald’s suit was based on or in response to their exercise of the right to petition. 1 In a single issue, they challenge the trial court’s failure to grant the motion. We affirm.

I. THE TEXAS CITIZENS PARTICIPATION ACT

The TCPA was enacted “to encourage and safeguard the constitutional rights of persons to petition,” among other rights, while “protect[ing] the rights of a person to file meritorious lawsuits for demonstrable injury.”2 If a legal action is “based on or is in response to” a party’s exercise of a protected right, the party, with exceptions inapplicable here, may move to dismiss the legal action.3 The movant bears the initial burden demonstrate that the legal action is based on or is in response to the party’s exercise of the rights or conduct protected by the statute. 4 The burden then shifts to the respondent to prove that an exemption applies,5 or alternatively, to establish “by clear and specific evidence a prima facie case for each essential element of the claim in question.”6 A prima facie case is established if the evidence is “sufficient as a matter of law to establish a given fact if it is not rebutted or contradicted.” 7 If the respondent establishes a prima facie case, then the burden shifts back to the movant

1 See TEX. CIV. PRAC. & REM. CODE §§ 27.001–011. After this suit was filed, the TCPA was amended to exempt legal-malpractice claims. See id. § 27.010(a)(13). Because the amendment applies only to an action filed on or after September 1, 2023, we apply the prior version of the TCPA, under which legal-malpractice claims were not categorically exempt. 2 Id. § 27.002. 3 Id. § 27.003(a). 4 Id. § 27.005(b). 5 See id. § 27.010 (setting forth exemptions); Toth v. Sears Home Improvement Prods., Inc., 557 S.W.3d 142, 152–53 (Tex. App.—Houston [14th Dist.] 2018, no pet.) (respondent has the burden to prove the exemption applies). 6 TEX. CIV. PRAC. & REM. CODE § 27.005(c). 7 Landry’s, Inc. v. Animal Legal Def. Fund, 631 S.W.3d 40, 45–46 (Tex. 2021) (quoting In re Lipsky, 460 S.W.3d 579, 590 (Tex. 2015) (orig. proceeding)).

2 to establish “an affirmative defense or other grounds on which the moving party is entitled to judgment as a matter of law.”8

II. BACKGROUND

Emerald Electrical Consultants LLC is a Georgia company that constructs electrical substations and provides related consulting and technical services. In 2021, Emerald began working on the “Golden Pass Project,” constructing an electrical substation in Texas as a subcontractor to Canyon Power Solutions, LLC.

A. The Firm’s Initial Advice

In May 2021, Emerald contacted the Florida office of law firm Adams & Reese LLP (“the Firm”), seeking advice “to ensure that payments to Emerald for services performed on the Golden Pass Project, while then not yet due, would be made in full and on time when due.” The Firm included Adam Massey, an attorney from the Firm’s Texas office, in a conference call with Emerald. According to Emerald, the Firm, including Massey, advised Emerald that liens related to the Golden Pass Project “could be perfected within 45 days after Emerald’s work on the project was completed and to revisit the issue then, when and/or if Emerald was not paid.”

But, under the applicable version of the Texas Property Code, if a lien claim arises from a debt incurred by a subcontractor, the claimant must give written notice of the unpaid balance to the original contractor “not later than the 15th day of the second month following each month in which all or part of the claimant’s labor was performed or material delivered.”9 The claimant must give the same notice to the

8 Id. § 27.005(d). 9 For this prior version of Texas Property Code § 53.056, see Act of May 19, 1997, 75th Leg., R.S., ch. 526, § 8, sec. 53.056(a), 1997 TEX. GEN. LAWS 1880, 1882 (amended 2021), and Act of May 28, 1989, 71st Leg., R.S., ch. 1138, § 8, sec. 8, secs. 53.056(b)–(e), 1989 TEX. GEN. 3 original contractor and to the owner or reputed owner “not later than the 15th day of the third month following each month in which all or part of the claimant’s labor was performed or material or specially fabricated material was delivered.”10 The claimant “must file an affidavit with the county clerk of the county in which the property is located . . . not later than the 15th day of the fourth calendar month after the day on which the indebtedness accrues.”11 According to Emerald, the Firm did not mention at that time the need to send notice letters to protect Emerald’s lien rights on the Golden Pass Project.

B. The Notice Letters

Canyon did not pay Emerald, and on July 20, 2021, Emerald contacted the Firm “to ensure collection of its invoices.” The Firm put Emerald in touch with Cassandra Walsh from the Firm’s Texas office. Although Emerald’s outstanding invoices from the Golden Pass Project ultimately covered the period from March through August of 2021, the Firm advised Emerald that the deadlines to serve the “second-month letter,” to serve the “third-month letter,” and to file a lien affidavit were, respectively, August 15, 2021, September 15, 2021, and October 15, 2021. Emerald directed the Firm to send the necessary letters and file the lien affidavit, “if and/or when necessary.”

After the Firm sent out second- and third-month notice letters in accordance with that schedule, Emerald and Canyon attempted to resolve the dispute through mediation on October 5, 2021. The Firm advised Emerald at the mediation that “its

LAWS 4693, 4696 (repealed 2021). The 2021 amendments apply only to original contracts entered into on or after January 1, 2022. 10 Id. 11 See prior version of Texas Property Code § 53.052, Act of May 19, 1997, 75th Leg., R.S., ch. 526, § 5, 1997 TEX. GEN. LAWS 1880, 1881 (amended 2021).

4 lien rights were fully intact” and it was in a strong position to collect the full amount owed. Mediation was unsuccessful.

C. Canyon’s Federal Suit

The day after the unsuccessful mediation, Canyon sued Emerald in a Texas federal district court. Two days after Canyon filed suit, Walsh received a letter from the first-tier subcontractor identifying three problems with the notice letters on the Golden Pass Project. First, the project address was wrong. Second, liens could not include amounts invoiced in March, April, or May, because the deadline for notices for those amounts had passed before any notice letters were sent. And third, the notice letters had not been sent to the original contractor, identified as “CCZJV.” Although Emerald told Walsh it could not independently prove that its invoices were received by the original contractor, the Firm filed a lien affidavit for the full amount invoiced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Da-Col Paint Manufacturing Co. v. American Indemnity Co.
517 S.W.2d 270 (Texas Supreme Court, 1974)
Julie Hersh v. John Tatum and Mary Ann Tatum
526 S.W.3d 462 (Texas Supreme Court, 2017)
American Indemnity Co. v. Da-Col Paint Manufacturing Co.
508 S.W.2d 944 (Court of Appeals of Texas, 1974)
In re Lipsky
460 S.W.3d 579 (Texas Supreme Court, 2015)
Levatino v. Apple Tree Café Touring, Inc.
486 S.W.3d 724 (Court of Appeals of Texas, 2016)
QTAT BPO Solutions, Inc. v. Lee & Murphy Law Firm, G.P.
524 S.W.3d 770 (Court of Appeals of Texas, 2017)
Toth v. Sears Home Improvement Prods., Inc.
557 S.W.3d 142 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Adams and Reese LLP, Adam Massey, and Cassandra Walsh v. Emerald Electrical Consultants LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adams-and-reese-llp-adam-massey-and-cassandra-walsh-v-emerald-electrical-texapp-2024.