Da-Col Paint Manufacturing Co. v. American Indemnity Co.

517 S.W.2d 270, 18 Tex. Sup. Ct. J. 130, 1974 Tex. LEXIS 342
CourtTexas Supreme Court
DecidedDecember 11, 1974
DocketB-4704
StatusPublished
Cited by25 cases

This text of 517 S.W.2d 270 (Da-Col Paint Manufacturing Co. v. American Indemnity Co.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Da-Col Paint Manufacturing Co. v. American Indemnity Co., 517 S.W.2d 270, 18 Tex. Sup. Ct. J. 130, 1974 Tex. LEXIS 342 (Tex. 1974).

Opinion

POPE, Justice.

The legal questions presented are whether a supplier of paint gave timely notice to the proper parties such as will support its claim against the surety on a Hardeman Act payment bond, and whether the claimant may recover against the surety on a bond executed by a sham contractor as principal.

Da-Col Paint Manufacturing Company instituted suit against C. Hayman Construction Company for payment for paint it delivered to Hayman. Da-Col also joined as defendants, Shiloh Terrace Apartments, a partnership, and American Indemnity Company, the surety upon the apparent original contractor’s Hardeman Act bond. Da-Col recovered a joint and several judgment on a jury verdict against Hayman and American Indemnity, but the court of civil appeals reversed and rendered judgment that Da-Col take nothing against American Indemnity. 508 S.W.2d 944. We reverse the judgment of the court of civil appeals and affirm that of the trial court.

Shiloh Terrace Apartments, a partnership composed of Homer Caston, Jr., G. C. Butler and J. E. Andrews, entered into a contract with Pala, Inc., whereby Pala agreed to construct an apartment complex for Shiloh Terrace. Pala’s stockholders were Caston (50%), Butler (49%) and Butler’s wife (1%). Pala subcontracted the painting work to C. Hayman Construction Company, to whom plaintiff Da-Col, in September, 1969, supplied paint worth $3,687.42 and in October, 1969, supplied paint worth $6,634.11. The arrangement, at the beginning, therefore, was in the sequence of Shiloh (owner), Pala (original contractor), Hayman (subcontractor), Da-Col (materialman).

Pala, as the original contractor, executed a Hardeman Act payment bond with American Indemnity as its surety. The purpose of such a bond is to insulate the owner from suits and his property from liens by the substitution of the payment bond. Vernon’s Tex.Rev.Civ.Stat.Ann. art. 5472d (Supp.1974). When Hayman failed to pay for the September and October deliveries of paint, Da-Col, on November 26, 1969, gave notice by certified mail to Shiloh, the owner, and mailed copies to Caston and Butler, but did not send a notice to Pala, the original contractor.

Da-Col obtained a judgment upon a jury verdict jointly and severally against Hay-man and American Indemnity in the amount of $16,530.53. The court of civil appeals, in reversing the judgment, held that Da-Col’s claim against American Indemnity failed because Da-Col did not give notice of its claim to Pala, the original contractor within thirty-six days, citing Article 5453(2) (b) (1).

The statutes which are here applicable are Article 5472d, which permits the sub *272 stitution of a Hardeman Act payment bond to secure the payment of liens and claims; Article 5453, which states the general rules for securing a lien; and Article 5452-1, the sham contractor statute.

Article 5472d provides that an original contractor may execute a bond in favor of the owner which will operate to insulate the owner and his property from suits for payment for labor or materials. Any claim for payment for labor or materials must be satisfied from the payment bond. A claimant such as Da-Col, however, must protect its claim on the bond by giving the notice required by Article 5472d, which incorporates by reference the notice requirements of Article 5453.

Article 5453 (2) (b)(1), T ex.Rev.Civ. Stat.Ann. (Supp.1974) provides that written notice of an unpaid balance due for labor or materials must be given to the owner within ninety days and to the original contractor within thirty-six days, both periods to run after the tenth day of the month following the month in which the materials were delivered or the labor performed. 1 While it is undisputed that timely notice was sent to the owner, Shiloh, American Indemnity argues that Da-Col’s failure to send notice to the original contractor, Pala, defeats Da-Col’s claim on Pala’s bond.

Da-Col urges that it can assert its claim against the Hardeman Act bond because it complied with the notice requirements of Article 5453. It argues that the sham contractor statute, Article 5452-1, operated to relieve them from the requirement of giving notice to Pala. The court of civil appeals held that the sham contractor statute does not affect the notice requirements of Article 5453 and that Da-Col’s failure to give notice to Pala was fatal to its claim on the bond. We hold that where Article 5452-1 applies, notice to the owner is also notice to the sham original contractor.

The jury found that the original contractor, Pala, was controlled by the owner, Shiloh. This finding made Article 5452-1 applicable. Article 5452-1 is as follows:

Whenever any owner of real property shall enter into any contract with a corporation for the construction or repair of any house, building or improvements thereon, and said owner can effectively control the corporation with whom such *273 contract is made, through the ownership of voting stock therein, interlocking directorships or otherwise then . . . any person, firm or corporation who, under a direct contractual relationship with said . . . corporation and who may . . . furnish labor or material to be used in the prosecution of the work under such contract shall be deemed to be in a direct contractual relationship with the owner and may perfect his lien against the property in the same manner as any other original contractor. [Emphasis added.]

Article 5452-1 was designed to elevate from subcontractor or materialman to original contractor any party dealing directly with an original contractor, where that original contractor acquired his status by virtue of a sham relationship with the owner. Whether one is considered an original contractor or a subcontractor is of fundamental importance. A subcontractor does not have a constitutional lien, First Nat’l Bank v. Lyon-Gray Lumber Co., 110 Tex. 162, 217 S.W. 133 (1919), and faces a more onerous burden in perfecting a statutory lien. Tex.Rev.Civ.Stat.Ann. art. 5453 (Supp.1974).

Prior to 1965, it was a common practice for owners to preclude those with whom they dealt from enjoying the more advantageous position of original contractor by assuming that position themselves through a sham original contractor. Youngblood, Mechanics’ and Materialmen’s Liens in Texas, 26 SW.L.J. 665, 671 (1972). In 1965, the Legislature discouraged the practice by passing Article 5452-1, which gives the subcontractor or materialman his true status of original contractor where the owner is found to control the nominal or sham original contractor.

American Indemnity is correct in its contention that Article 5452-1 is not a notice statute. Fundamental to the operation of the statute, however, is the recognition that the owner and sham contractor are one and the same. This being so; it is illogical to require that notice be given the owner in his capacity as owner, and a separate notice given him in his capacity as original contractor.

It was also unnecessary for Da-Col to give a thirty-six day notice to Hayman, the original contractor by operation of law. Article 5453(2) (b) (2) provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc.
295 S.W.3d 763 (Court of Appeals of Texas, 2009)
Exchanger Contractors Inc. v. Comerica Bank-Texas
330 F.3d 339 (Fifth Circuit, 2003)
Convoy Servicing Co. v. Trailmobile Trailer, LLC
234 F. Supp. 2d 826 (N.D. Illinois, 2002)
Southwest Properties, L.P. v. Lite-Dec of Texas, Inc.
989 S.W.2d 69 (Court of Appeals of Texas, 1999)
South Coast Supply Co. v. a & M Operating Co.
182 B.R. 986 (E.D. Texas, 1993)
Lee v. Ardoin
677 S.W.2d 686 (Court of Appeals of Texas, 1984)
First National Bank in Graham v. Sledge
653 S.W.2d 283 (Texas Supreme Court, 1983)
Argonaut Ins. Co. v. ABC Steel Products Co., Inc.
582 S.W.2d 883 (Court of Appeals of Texas, 1979)
Berger Engineering Co. v. Village Casuals, Inc.
576 S.W.2d 649 (Court of Appeals of Texas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
517 S.W.2d 270, 18 Tex. Sup. Ct. J. 130, 1974 Tex. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/da-col-paint-manufacturing-co-v-american-indemnity-co-tex-1974.