Precision Roofing Inc. v. David Zavelson and Tracy Zavelson

Court of Appeals of Texas·Decided November 9, 2018·No. 03-17-00550-CV·Published

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-17-00550-CV

Precision Roofing, Inc., Appellant v.

David Zavelson and Tracy Zavelson, Appellees

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 261ST JUDICIAL DISTRICT NO. D-1-GN-16-000909, HONORABLE KARIN CRUMP, JUDGE PRESIDING

MEMORANDUM OPINION

In this residential-construction case, a subcontractor and the property owners dispute the validity of the subcontractor’s statutory lien. See generally Tex. Prop. Code §§ 53.001-.287 (“Mechanic’s, Contractor’s or Materialman’s Liens”). The subcontractor, Precision Roofing, Inc. (Precision), filed suit to foreclose its lien on the property of David and Tracy Zavelson. The Zavelsons filed a summary motion to remove the lien. See id. § 53.160 (authorizing summary motion to remove invalid or unenforceable lien). Both parties filed cross-motions for summary judgment. The trial court granted the motion to remove the lien, granted the Zavelsons’ motion for summary judgment, and denied Precision’s. For the reasons that follow, we will modify the judgment to reduce the award of attorney’s fees and costs and affirm as modified.

FACTUAL AND LEGAL BACKGROUND We begin by setting out the governing statutory framework. A subcontractor such as Precision is considered a derivative claimant because, “unlike a general contractor, [it] has no constitutional, common law, or contractual lien on the property of the owner.” First Nat. Bank in Graham v. Sledge, 653 S.W.2d 283, 285 (Tex. 1983). As a result, a derivative claimant’s right to recover against the property owner depends entirely on the lien statutes. Id.; Ready Cable, Inc. v. RJP S. Comfort Homes, Inc., 295 S.W.3d 763, 765 (Tex. App.—Austin 2009, no pet.). Chapter 53 entitles a person who supplies labor or furnishes materials to construct or repair a “house, building, or improvement” pursuant to a contract with the property owner, the owner’s agent, or the original contractor to a lien on that property and on “each lot of land necessarily connected” under certain circumstances. See Tex. Prop. Code §§ 53.021-.023.

Subchapter C sets out the procedures necessary to perfect the lien. See id. § 53.051 (“To perfect the lien, a person must comply with this subchapter.”); see generally id. §§ 53.051-.058 (“Procedure for Perfecting Lien”). As a general rule, a claimant must timely file an affidavit with specified contents in the real property records of the county where the property is located and send a copy of the affidavit to the owner. See id. §§ 53.052, .054, .055. Additional procedures apply to certain derivative claimants. See generally id. §§ 53.056-.058 (setting specialized notice requirements). Subchapter K contains additional procedures that are applicable if the claim arises from a “residential construction project.” See id. § 53.251(b) (“A person must comply with this subchapter in addition to the other applicable provisions of this chapter to perfect a lien that arises

from a claim resulting from a residential construction project.”); see generally id. §§ 53.251-.260 (“Residential Construction Projects”).

A derivative claimant may also “seek recovery from ‘trapped’ funds held by the property owner or funds ‘retained’ by the owner.” Pham v. Harris Cty. Rentals, L.L.C., 455 S.W.3d 702, 707 (Tex. App.—Houston [1st Dist.] 2014, no pet.). Subchapter E addresses “retained” funds, which are “withheld from the original contractor either under a contractual agreement or under section 53.101.” Id.; see generally Tex. Prop. Code §§ 53.101-.107 (“Required Retainage for Benefit of Lien Claimants”). Section 53.101 requires an owner to retain ten percent of the contract price during work “under an original contract for which a mechanic’s lien may be claimed” to “secure the payment of artisans and mechanics who perform labor or service.” See Tex. Prop. Code §§ 53.101, .102. “A claimant has a lien on the retained funds” if it “sends the notices required by this chapter in the time and manner required,” and timely “files an affidavit claiming a lien.” Id. § 53.103. However, if the owner fails or refuses to retain funds:

[T]he claimants complying with Subchapter C or this subchapter have a lien, at least to the extent of the amount that should have been retained from the original contract under which they are claiming, against the house, building, structure, fixture, or improvement and all of its properties and against the lot or lots of land necessarily connected.

Id. § 53.105(a).

We now turn to the partes’ dispute. In October of 2014, David Zavelson—but not Tracy—signed a contract with Cox Development Corporation to remodel and expand their home (the

Property) in Travis County. Cox subcontracted “roofing and flashing services” to Precision. In December of 2014, David Zavelson terminated the contract with Cox.

Shortly after David terminated the contract, Precision filed two affidavits in the real property records of Travis County claiming a lien on both the Property and the retainage in the total amount of $15,374. Precision subsequently filed suit to foreclose on the lien. Because David’s contract with Cox did not contain a retainage clause, Precision relied entirely on the statutory retainage provisions in Chapter 53. The Zavelsons argued in their answer to the lawsuit that the lien was invalid because the Property was their homestead and the prerequisites to attaching a lien to a homestead had not been met. Under Subchapter K, in addition to complying with the applicable notice and filing requirements, “[t]o fix a lien on a homestead, the person who is to furnish material or perform labor and the owner must execute a written contract setting forth the terms of the agreement.” Id. § 53.254(a). And, “[i]f the owner is married, the contract must be signed by both spouses.” Id. § 53.254(c). The Zavelsons asserted that this requirement was not met because Tracy did not sign the contract with Cox.

The parties subsequently stipulated that Tracy did not sign the contract, and that the lien would be unenforceable against the Property if the trial court determined that it was the Zavelsons’ homestead. In addition, the parties stipulated that David did not retain any funds but that if he had, “the total statutory retainage amount . . . would have been at least $18,589.77.” Almost a month later, Precision filed a “Partial Release Regarding Affidavits Claiming Lien” in the real

property records of Travis County releasing its lien against the Property but not the retainage.1 See id. § 53.157(1) (providing that lien can be released by “recording a lien release signed by the claimant”).

Precision then filed a motion for summary judgment arguing that the Zavelsons were liable for the $18,589.77 that Section 53.101 required David to retain. The Zavelsons filed a combined summary motion to remove the lien and a cross motion for summary judgment. Precision argued that the statutory duty to retain applied to David and that the Zavelsons were “personally liable” for that amount under Section 53.057(f). In response, the Zavelsons argued that Section 53.101 did not apply in this case because “no liens can exist against the retainage alone without an underlying lien against the Property.” They also argued that even if the duty did apply, Chapter 53 provided only one remedy: a lien on the Property under Section 53.105. And the Zavelsons asserted that because Precision had already released its lien on the Property, they were entitled to summary judgment. Both parties also sought an award of attorney’s fees. See id. § 53.156 (authorizing trial court to award attorney’s fees “in any proceeding to declare that any lien or claim is invalid or unenforceable in whole or in part”).

The trial court issued an order that removed the lien on the Property, granted the Zavelsons’ motion for summary judgment and denied Precision’s, and awarded the Zavelsons $15,374 in attorney’s fees and conditional appellate fees. This appeal followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Precision Roofing Inc. v. David Zavelson and Tracy Zavelson, (Tex. Ct. App. 2018).

Precision Roofing Inc. v. David Zavelson and Tracy Zavelson (Precision Roofing Inc. v. David Zavelson and Tracy Zavelson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Daughters of Charity Health Services of Waco v. Linnstaedter
226 S.W.3d 409 (Texas Supreme Court, 2007)
20801, INC. v. Parker
249 S.W.3d 392 (Texas Supreme Court, 2008)
Wesco Distribution, Inc. v. Westport Group, Inc.
150 S.W.3d 553 (Court of Appeals of Texas, 2004)
W & W Floor Covering Co. v. Project Acceptance Co.
412 S.W.2d 379 (Court of Appeals of Texas, 1967)
First National Bank in Dallas v. Whirlpool Corp.
517 S.W.2d 262 (Texas Supreme Court, 1974)
First National Bank in Graham v. Sledge
653 S.W.2d 283 (Texas Supreme Court, 1983)
Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc.
295 S.W.3d 763 (Court of Appeals of Texas, 2009)
Exchange Savings & Loan Ass'n v. Monocrete Pty. Ltd.
629 S.W.2d 34 (Texas Supreme Court, 1982)
Long Q. Pham and Thao M. Silva v. Harris County Rentals, L.L.C.
455 S.W.3d 702 (Court of Appeals of Texas, 2014)
Matthew Lippincott and Creg Parks v. Warren Whisenhunt
462 S.W.3d 507 (Texas Supreme Court, 2015)
Lyda Swinerton Builders, Inc. v. Cathay Bank
409 S.W.3d 221 (Court of Appeals of Texas, 2013)
Matthews ex rel. M.M. v. Kountze Independent School District
484 S.W.3d 416 (Texas Supreme Court, 2016)
ExxonMobil Pipeline Co. v. Coleman
512 S.W.3d 895 (Texas Supreme Court, 2017)
In re M & O Homebuilders, Inc.
516 S.W.3d 101 (Court of Appeals of Texas, 2017)
Twin Creeks Golf Group, L.P. v. Sunset Ridge Owners Ass'n
537 S.W.3d 535 (Court of Appeals of Texas, 2017)
City of Richardson v. Oncor Elec. Delivery Co.
539 S.W.3d 252 (Texas Supreme Court, 2018)
Youngkin v. Hines
546 S.W.3d 675 (Texas Supreme Court, 2018)
Fort Worth Transp. Auth. v. Rodriguez
547 S.W.3d 830 (Texas Supreme Court, 2018)