Precision Roofing Inc. v. David Zavelson and Tracy Zavelson

CourtCourt of Appeals of Texas
DecidedNovember 9, 2018
Docket03-17-00550-CV
StatusPublished

This text of Precision Roofing Inc. v. David Zavelson and Tracy Zavelson (Precision Roofing Inc. v. David Zavelson and Tracy Zavelson) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Precision Roofing Inc. v. David Zavelson and Tracy Zavelson, (Tex. Ct. App. 2018).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-17-00550-CV

Precision Roofing, Inc., Appellant

v.

David Zavelson and Tracy Zavelson, Appellees

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 261ST JUDICIAL DISTRICT NO. D-1-GN-16-000909, HONORABLE KARIN CRUMP, JUDGE PRESIDING

MEMORANDUM OPINION

In this residential-construction case, a subcontractor and the property owners dispute

the validity of the subcontractor’s statutory lien. See generally Tex. Prop. Code §§ 53.001-.287

(“Mechanic’s, Contractor’s or Materialman’s Liens”). The subcontractor, Precision Roofing, Inc.

(Precision), filed suit to foreclose its lien on the property of David and Tracy Zavelson. The

Zavelsons filed a summary motion to remove the lien. See id. § 53.160 (authorizing summary

motion to remove invalid or unenforceable lien). Both parties filed cross-motions for summary

judgment. The trial court granted the motion to remove the lien, granted the Zavelsons’ motion for

summary judgment, and denied Precision’s. For the reasons that follow, we will modify the

judgment to reduce the award of attorney’s fees and costs and affirm as modified. FACTUAL AND LEGAL BACKGROUND

We begin by setting out the governing statutory framework. A subcontractor such

as Precision is considered a derivative claimant because, “unlike a general contractor, [it] has no

constitutional, common law, or contractual lien on the property of the owner.” First Nat. Bank in

Graham v. Sledge, 653 S.W.2d 283, 285 (Tex. 1983). As a result, a derivative claimant’s right to

recover against the property owner depends entirely on the lien statutes. Id.; Ready Cable, Inc. v.

RJP S. Comfort Homes, Inc., 295 S.W.3d 763, 765 (Tex. App.—Austin 2009, no pet.). Chapter 53

entitles a person who supplies labor or furnishes materials to construct or repair a “house, building,

or improvement” pursuant to a contract with the property owner, the owner’s agent, or the original

contractor to a lien on that property and on “each lot of land necessarily connected” under certain

circumstances. See Tex. Prop. Code §§ 53.021-.023.

Subchapter C sets out the procedures necessary to perfect the lien. See id. § 53.051

(“To perfect the lien, a person must comply with this subchapter.”); see generally id. §§ 53.051-.058

(“Procedure for Perfecting Lien”). As a general rule, a claimant must timely file an affidavit with

specified contents in the real property records of the county where the property is located and send

a copy of the affidavit to the owner. See id. §§ 53.052, .054, .055. Additional procedures apply to

certain derivative claimants. See generally id. §§ 53.056-.058 (setting specialized notice

requirements). Subchapter K contains additional procedures that are applicable if the claim arises

from a “residential construction project.” See id. § 53.251(b) (“A person must comply with this

subchapter in addition to the other applicable provisions of this chapter to perfect a lien that arises

2 from a claim resulting from a residential construction project.”); see generally id. §§ 53.251-.260

(“Residential Construction Projects”).

A derivative claimant may also “seek recovery from ‘trapped’ funds held

by the property owner or funds ‘retained’ by the owner.” Pham v. Harris Cty. Rentals, L.L.C.,

455 S.W.3d 702, 707 (Tex. App.—Houston [1st Dist.] 2014, no pet.). Subchapter E addresses

“retained” funds, which are “withheld from the original contractor either under a contractual

agreement or under section 53.101.” Id.; see generally Tex. Prop. Code §§ 53.101-.107 (“Required

Retainage for Benefit of Lien Claimants”). Section 53.101 requires an owner to retain ten percent

of the contract price during work “under an original contract for which a mechanic’s lien may be

claimed” to “secure the payment of artisans and mechanics who perform labor or service.” See Tex.

Prop. Code §§ 53.101, .102. “A claimant has a lien on the retained funds” if it “sends the notices

required by this chapter in the time and manner required,” and timely “files an affidavit claiming a

lien.” Id. § 53.103. However, if the owner fails or refuses to retain funds:

[T]he claimants complying with Subchapter C or this subchapter have a lien, at least to the extent of the amount that should have been retained from the original contract under which they are claiming, against the house, building, structure, fixture, or improvement and all of its properties and against the lot or lots of land necessarily connected.

Id. § 53.105(a).

We now turn to the partes’ dispute. In October of 2014, David Zavelson—but not

Tracy—signed a contract with Cox Development Corporation to remodel and expand their home (the

3 Property) in Travis County. Cox subcontracted “roofing and flashing services” to Precision. In

December of 2014, David Zavelson terminated the contract with Cox.

Shortly after David terminated the contract, Precision filed two affidavits in the real

property records of Travis County claiming a lien on both the Property and the retainage in the total

amount of $15,374. Precision subsequently filed suit to foreclose on the lien. Because David’s

contract with Cox did not contain a retainage clause, Precision relied entirely on the statutory

retainage provisions in Chapter 53. The Zavelsons argued in their answer to the lawsuit that the lien

was invalid because the Property was their homestead and the prerequisites to attaching a lien to a

homestead had not been met. Under Subchapter K, in addition to complying with the applicable

notice and filing requirements, “[t]o fix a lien on a homestead, the person who is to furnish material

or perform labor and the owner must execute a written contract setting forth the terms of the

agreement.” Id. § 53.254(a). And, “[i]f the owner is married, the contract must be signed by both

spouses.” Id. § 53.254(c). The Zavelsons asserted that this requirement was not met because Tracy

did not sign the contract with Cox.

The parties subsequently stipulated that Tracy did not sign the contract, and that the

lien would be unenforceable against the Property if the trial court determined that it was the

Zavelsons’ homestead. In addition, the parties stipulated that David did not retain any funds but that

if he had, “the total statutory retainage amount . . . would have been at least $18,589.77.” Almost

a month later, Precision filed a “Partial Release Regarding Affidavits Claiming Lien” in the real

4 property records of Travis County releasing its lien against the Property but not the retainage.1

See id. § 53.157(1) (providing that lien can be released by “recording a lien release signed by

the claimant”).

Precision then filed a motion for summary judgment arguing that the Zavelsons were

liable for the $18,589.77 that Section 53.101 required David to retain. The Zavelsons filed a

combined summary motion to remove the lien and a cross motion for summary judgment. Precision

argued that the statutory duty to retain applied to David and that the Zavelsons were “personally

liable” for that amount under Section 53.057(f). In response, the Zavelsons argued that Section

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daughters of Charity Health Services of Waco v. Linnstaedter
226 S.W.3d 409 (Texas Supreme Court, 2007)
20801, INC. v. Parker
249 S.W.3d 392 (Texas Supreme Court, 2008)
Wesco Distribution, Inc. v. Westport Group, Inc.
150 S.W.3d 553 (Court of Appeals of Texas, 2004)
W & W Floor Covering Co. v. Project Acceptance Co.
412 S.W.2d 379 (Court of Appeals of Texas, 1967)
First National Bank in Dallas v. Whirlpool Corp.
517 S.W.2d 262 (Texas Supreme Court, 1974)
First National Bank in Graham v. Sledge
653 S.W.2d 283 (Texas Supreme Court, 1983)
Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc.
295 S.W.3d 763 (Court of Appeals of Texas, 2009)
Exchange Savings & Loan Ass'n v. Monocrete Pty. Ltd.
629 S.W.2d 34 (Texas Supreme Court, 1982)
Long Q. Pham and Thao M. Silva v. Harris County Rentals, L.L.C.
455 S.W.3d 702 (Court of Appeals of Texas, 2014)
Matthew Lippincott and Creg Parks v. Warren Whisenhunt
462 S.W.3d 507 (Texas Supreme Court, 2015)
Lyda Swinerton Builders, Inc. v. Cathay Bank
409 S.W.3d 221 (Court of Appeals of Texas, 2013)
Matthews ex rel. M.M. v. Kountze Independent School District
484 S.W.3d 416 (Texas Supreme Court, 2016)
ExxonMobil Pipeline Co. v. Coleman
512 S.W.3d 895 (Texas Supreme Court, 2017)
In re M & O Homebuilders, Inc.
516 S.W.3d 101 (Court of Appeals of Texas, 2017)
Twin Creeks Golf Group, L.P. v. Sunset Ridge Owners Ass'n
537 S.W.3d 535 (Court of Appeals of Texas, 2017)
City of Richardson v. Oncor Elec. Delivery Co.
539 S.W.3d 252 (Texas Supreme Court, 2018)
Youngkin v. Hines
546 S.W.3d 675 (Texas Supreme Court, 2018)
Fort Worth Transp. Auth. v. Rodriguez
547 S.W.3d 830 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Precision Roofing Inc. v. David Zavelson and Tracy Zavelson, Counsel Stack Legal Research, https://law.counselstack.com/opinion/precision-roofing-inc-v-david-zavelson-and-tracy-zavelson-texapp-2018.