Lyda Swinerton Builders, Inc v. Cathay Bank

CourtCourt of Appeals of Texas
DecidedAugust 13, 2013
Docket14-12-00163-CV
StatusPublished

This text of Lyda Swinerton Builders, Inc v. Cathay Bank (Lyda Swinerton Builders, Inc v. Cathay Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyda Swinerton Builders, Inc v. Cathay Bank, (Tex. Ct. App. 2013).

Opinion

Affirmed in Part, Reversed and Remanded in Part, and Majority and Dissenting Opinions filed August 13, 2013.

In The

Fourteenth Court of Appeals

NO. 14-12-00163-CV

LYDA SWINERTON BUILDERS, INC, Appellant V.

CATHAY BANK, Appellee

On Appeal from the 113th District Court Harris County, Texas Trial Court Cause No. 2008-64001A

DISSENTING OPINION

In Part II of its opinion, the majority concludes that appellant Lyda Swinerton Builders, Inc. (the “Builder”) fully released its materialman’s and mechanic’s (“M&M”) lien, but “did not waive its right to file new M&M liens covering other property or securing payment for post-release expenses.” I would hold that these post-release amended M&M lien affidavits could not have created a new M&M lien. I would affirm summary judgment in favor of Cathay Bank (the “Bank”) on the basis that it established its lien priority as a matter of law because the Builder’s amended lien affidavits were ineffective to create new M&M liens. Therefore, I respectfully dissent.

Supplemental Background1

This case involves a parcel of land consisting of six contiguous tracts making up nearly 16.5 acres (the “Property”). According to the Builder’s M&M lien affidavits, these tracts are described as follows: Tract I – 0.8664 acre in area; Tract II – 0.1072 acre in area; Tract III – 10.4179 acres in area; Tract IV – 0.4236 acre in area; Tract V – 1.2451 acres in area; and Tract VI – 3.4235 acres in area.2

The Property was owned by Park 8 Place, L.P. (the “Developer”), which, as noted by the majority, is not a party to this suit. See ante, at 2. The Builder executed a contract with the Developer to make improvements to the Property in February 2007 (the “Project”). At the time that the Builder executed the contract, it had already begun working on the Project in January 2007. Further, the Builder acknowledges that, when it began work on the Project, the Bank had a deed of trust lien recorded on March 15, 2004, covering Tracts III, IV, and V, i.e., approximately 12.0866 acres of the property. The Bank’s deed of trust lien secured repayment of approximately $1.4 million it had loaned to the Developer’s predecessor-in-interest.

After the Builder began work, the Bank loaned the Developer additional funds. In May 2007, the Bank filed a deed of trust lien against Tract VI, securing the repayment of a loan of $800,700.00 made to the Developer. In August, the

1 I include my own background section to supplement the majority’s facts and to focus on those facts that are important to my resolution of this dispute. 2 The Builder numbers these tracts differently in an exhibit. The majority uses the numbers as referenced in the Builder’s exhibit, but I use the tract numbers referenced in the lien affidavits. This difference in numbering has no impact on the analysis.

2 Bank filed another deed of trust lien, covering the entire Property, securing the repayment of $502,000.00 loaned to the Developer.

The Developer stopped paying the Builder for its work on the Project in August 2007. Because of these payment issues, the Builder ceased working on the Project on October 4, 2007. On October 10, 2007, the Builder filed its first M&M lien affidavit, reflecting a lien of approximately $3.2 million and encumbering Tracts I and II of the property. Apparently, around this same time, the Builder, the Bank, and the Developer engaged in meetings regarding obtaining funding for the Project. On October 19, 2007, the Builder’s Houston operations manager, Brian Duncan, sent the following email to the Bank’s representatives:

We [the Builder] suspended all work on October 4th due to the outstanding payment issues. All of the subcontractors have demobilized from the site. No additional work has been performed since our meeting. We are preparing to take down the tower crane and remove the concrete forms for the tower structure by the end of the month. Previous emails indicate that Duncan had met with at least one of the Bank’s representatives earlier in October. The first email is dated October 11, 2007 and is from Duncan. In it, Duncan inquires about the availability of “the $1.5M funding,” asks for an update on the “status of the loan,” and requests that “the funds” be wired to the Builder’s bank. The subject line of this email, and the rest of the emails contained in the string, is “Park 8 [the Developer] Funding Status.”

The Bank subsequently loaned the Developer approximately $1.9 million. This loan closed on October 31, 2007.3 The HUD settlement statement from the

3 The record contains another email from Duncan, dated October 30, 2007, to an individual at the title company handling the closing of the loan between the Bank and the Developer. Attached to this email is an unexecuted release of the Builder’s lien. In the email, Duncan asks “what time tomorrow” he should come to the title company to sign the release and pick up the Builder’s check for $1,086,914.62.

3 closing of the Bank’s loan to the Developer reflects that the Builder received $1,086,914.62 from the loan funds.4 The record contains a “Release of Lien,” executed by the Builder, which reflects that, in consideration of $1.5 million,5 the Builder released its October 10, 2007 M&M lien described above (the “Released M&M Lien”). This lien release was signed on October 31 and filed on November 5, 2007 in the Harris County Property Records. Also on October 31, the Developer signed a deed of trust in favor of the Bank, covering the entirety of the Property and securing the Bank’s $1.9 million loan. This deed of trust was filed of record on November 5, 2007 (the “November deed of trust”).

After releasing its original M&M lien, the Builder maintained a presence on the Property and continued to submit bills to the Developer, but never recommenced work on the Project. On November 13, 2007, the Builder filed a “First Amended Affidavit for Mechanic’s and Materialman’s Lien,” which in its body specifically described and purported to amend the Released M&M Lien. This M&M lien purportedly encumbered Tracts I and II and claimed an indebtedness of $2,887,070.20, which included indebtedness of $2,141,529.88 remaining from the Released M&M Lien that was not paid through the loan funds. This amended M&M lien affidavit was followed by three more amended M&M lien affidavits, filed on June 12, 2008, October 23, 2008, and January 16, 2009, each encumbering Tracts I and II, as well as adding Tracts III through VI, each specifically referencing and purporting to amend a prior M&M lien affidavit, and

4 The majority states that the Bank paid the Builder these funds. See ante, at 4. More accurately, the money for this payment came from funds the Bank loaned to the Developer. This amount was paid during settlement of the loan directly to the Builder by the title company handling the loan closing. Thus it is more precise to state that the Developer paid these amounts. 5 Another subcontract, not a party to this dispute, was paid $413,085.38 out of the Developer’s loan funds and also released its M&M lien, which is why the release reflects $1.5 million.

4 each for an increased amount. The final indebtedness the Builder claimed is over $6.7 million.

On October 24, 2008, while still maintaining a presence on the Property and still incurring expenses, the Builder filed suit against the Developer for breach of contract and to foreclose on its M&M lien. In December 2008, the Bank intervened in the lawsuit, asserting a superior interest in some or all of the Property. The Builder finally demobilized from the Project in March 2010— nearly eighteen months after filing suit against the Developer. The Developer filed for bankruptcy protection, which temporarily abated proceedings in the underlying suit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Apex Financial Corp. v. Brown
7 S.W.3d 820 (Court of Appeals of Texas, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Lyda Swinerton Builders, Inc v. Cathay Bank, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyda-swinerton-builders-inc-v-cathay-bank-texapp-2013.