Donna T. Moore, David B. Moore and Provident Funding Associates, LP D/B/A Provident Home Loans v. Brenham Ready Mix, Inc.

463 S.W.3d 109, 2015 Tex. App. LEXIS 2242, 2015 WL 1059273
Court of Appeals of Texas·Decided March 10, 2015·No. NO. 01-13-00615-CV·Published·Cited by 5 cases

Opinion

*111 OPINION

Evelyn V. Keyes, Justice

In this case, Brenham Ready Mix, Inc., a supplier of ready-mix concrete and fill dirt for the development of a residential subdivision, sought to foreclose upon two materialman’s liens on two lots owned by Donna T. and David B. Moore and Provident Funding Associates, LP d/b/a Provident Home Loans 1 (collectively, “the individual homeowners”). After a bench trial, the trial court ruled that Brenham Ready Mix could foreclose upon its liens in the amount of $214,757.76 against each of the lots, and the court awarded $75,000 in trial-level attorney’s fees and $25,000 in conditional appellate attorney’s fees. In three issues on appeal, the individual homeowners contend that (1) the trial court erroneously enforced the full amount of the liens, which represented materials used for the entire development project, against their individual lots; (2) Brenham Ready Mix did not perfect its lien for the concrete because it did not substantially comply with the statutory notice requirements; and (3) the trial court erred in awarding attorney’s fees to Brenham Ready Mix due to the excessive-demand doctrine or, if the trial court properly awarded attorney’s fees, the court erred in the amount awarded because Brenham Ready Mix did not segregate its fees relating to each particular property.

We reverse and remand.

Background

Art DePue owned twenty-five acres of land in Prairie View, Texas. In 2002, De-Pue subdivided the land and filed a plat for the Brookside Meadow subdivision. De-Pue filed a replat of the subdivision in 2006, subdividing the land into seventy-one lots. L & F Homes and Development (“L & F”) was the initial original contractor for the construction project, which involved, among other things, building duplexes on each of the lots.

Brenham Ready Mix supplies ready-mix concrete and other materials for residential and commercial construction projects. In early 2006, Felix Meyer, Brenham Ready Mix’s president, met with David Solomon of L & F, who was the project manager for the Brookside Meadow project, and George Mott of Mott Concrete, Inc., the subcontractor that had a contract with L & F to provide and pour the concrete to be used for the slabs, sidewalks, and parking lots in the subdivision. Meyer quoted a price for concrete to Mott, and Brenham Ready Mix entered into a subcontract on an open-account basis with Mott to provide ready-mix concrete for the entire development. Brenham Ready Mix’s contract with Mott did not specify the amount of concrete to be used on each specific lot, and it did not “enter into any contracts that were specific to lots.”

The construction project was divided into three phases. Mott paid Brenham Ready Mix for the concrete provided for Phases One and Two, and there is no dispute in this litigation about those two phases. Phase Three involved thirty-seven lots, and Brenham Ready Mix delivered concrete for this phase in July and September 2007. 2 During construction, Mott *112 would inform Brenham Ready Mix of how much concrete it needed for the next day, Brenham Ready Mix would deliver that amount to the jobsite, and Mott would direct and pour the concrete. Brenham Ready Mix generally billed Mott monthly, although it occasionally billed more frequently if it had delivered a large volume of concrete. Mott failed to pay for $206,661.76 worth of the concrete deliveries in July and September. The trial court admitted several unpaid invoices from Brenham Ready Mix to Mott- dated throughout August, September, and October 2007.

During construction, DePue sold the Phase Three property to L & F, which then sold the property to Jim Fitchett on September 12, 2007. Around September 2007, Stability Homes replaced L <& F as the general contractor on the project. 3 Solomon, the project manager for L & F, remained the manager for the project.

After Mott failed to pay the outstanding invoices for the doncrete, Brenham Ready Mix retained attorney Katherine Kenjura to prepare a lien. Kenjura sent a notice letter regarding Brenham Ready Mix’s lien on the concrete to Mott, the subcontractor for the concrete, Stability Homes, the then-current general contractor for the project, and DePue, the former owner of the Phase Three properly, on November 21, 2007. She sent a second notice letter on December 18, 2007, to L & F, the former general contractor for the project, Stability Homes, and Mott. Meyer testified that Brenham Ready Mix provided its outstanding invoices solely to Mott. Thus, the November 21, 2007 notice letter was the first written notice Brenham Ready Mix provided to entities other than Mott. It had not sent any notice letters before Stability Homes became the general contractor for the project. And it did not send the November 21, 2007 notice letter to L & F. Instead, Solomon, the project manager for both L & F and Stability Homes, testified by deposition that Meyer spoke with him in “September, October, around the end of October, first of November of 2007” and informed him that Mott had not paid Brenham Ready Mix for the concrete.

By January 2008, Brenham Ready Mix had finished all of the concrete deliveries to the project. It then entered into a second contract, this time with Stability Homes, the general contractor, to provide fill dirt to the site. This contract, like Brenham Ready Mix’s initial contract with Mott, the concrete subcontractor, required Brenham Ready Mix to provide fill dirt to the entire development, not to specific lots within the development. Stability Homes failed to pay Brenham Ready Mix $8,096 for the fill-dirt deliveries, so Brenham Ready Mix filed another lien affidavit for these materials. All of the fill-dirt deliveries occurred in January 2008, and Kenjura sent the notice letter for this lien on January 30, 2008.

On January 9, 2008, Brenham Ready Mix filed an “Affidavit Claiming Mechanic’s and Materialman’s Lien” for the ready-' mix concrete, averring that it had an unpaid claim in the amount of $206,661.76 for labor and materials furnished. This affi *113 davit specifically listed each lot in Phase Three. Brenham Ready Mix listed L & F as the “owner or reputed owner” of the properly, identified Stability Homes as the original general contractor, and identified Mott as the subcontractor. The affidavit further stated that Brenham Ready Mix had sent notice of the claimed lien to L & F by certified mail on November 21, 2007, and December 18, 2007. Brenham Ready Mix sent notice of the lien affidavit to L & F, Stability Homes, and Mott.

Brenham Ready Mix filed an affidavit claiming a lien for the fill dirt on February 13, 2008. This affidavit again specifically listed each lot, named L & F as the owner or reputed owner, and listed Stability Homes as both the original general contractor and as subcontractor for the fill dirt. This affidavit stated that Brenham Ready Mix had sent notice of the claimed lien to L & F by certified mail on January 30, 2008.

Beginning in March 2008, individuals began to purchase lots in the subdivision from Jim Fitchett, who had purchased the property in September 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Donna T. Moore, David B. Moore and Provident Funding Associates, LP D/B/A Provident Home Loans v. Brenham Ready Mix, Inc., 463 S.W.3d 109, 2015 Tex. App. LEXIS 2242, 2015 WL 1059273 (Tex. Ct. App. 2015).

463 S.W.3d 109 (Donna T. Moore, David B. Moore and Provident Funding Associates, LP D/B/A Provident Home Loans v. Brenham Ready Mix, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related