Hayek v. Western Steel Company

478 S.W.2d 786, 15 Tex. Sup. Ct. J. 232, 1972 Tex. LEXIS 262
CourtTexas Supreme Court
DecidedMarch 15, 1972
DocketB-2882
StatusPublished
Cited by104 cases

This text of 478 S.W.2d 786 (Hayek v. Western Steel Company) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hayek v. Western Steel Company, 478 S.W.2d 786, 15 Tex. Sup. Ct. J. 232, 1972 Tex. LEXIS 262 (Tex. 1972).

Opinions

DANIEL, Justice.

This appeal involves the construction of the Mechanics’ and Materialmen’s Lien Act,1 particularly Articles 5452 and 5469. The Act,, among other things, provides statutory liens for those who labor or furnish materials for the construction or repair of any house, building or improvement. Respondents, as plaintiffs below, sued the Petitioner owners for the unpaid balance on steel and concrete furnished to Petitioners’ foundation contractor, claiming that Petitioners are liable therefor under Article 5469. It is unquestioned that under Article 5469 an owner who makes a general contract covering the entire construction of a house or other building must, for the protection of laborers and materialmen, retain in his hands for 30 days after the work is completed ten per cent (10%) of the contract price or value of the house or other building.2 If the owner fails to retain such fund, then all complying claimants “shall share ratably among themselves, with preference to artisans and mechanics ., liens at least to the extent of the aforesaid fund of ten per-cent (10%) which should have been retained as against the house, building ... or improvement and all of its properties . . .”

The question here is whether the Petitioner owners, who acted as their own builders through numerous separate original contracts, none of which were covered by surety bonds authorized by Article 5472d, had the same obligation under Article 5469 to retain or become liable for an amount equal to ten per cent (10%) of the value of their completed houses. This question was answered in the affirmative by the 156th District Court, San Patricio County, and judgment was rendered for the materialmen, who are Respondents here. Except for modification of the trial court’s judgment as to interest, the Court of Civil Appeals affirmed. 469 S.W.2d 206. We affirm the judgment of the Court of Civil Appeals.

This case actually involves twelve separate causes of action which were tried together with the consent of the parties. Each of the Petitioners owned one or more [788]*788tracts of land in various subdivisions located in San Patricio County upon which he constructed a house or apartment units. None of Petitioners entered into a general contract for the construction of his improvements at a fixed contract price, but each acted as his own builder for the particular house or other building on his own land. At a total cost of $500,346.97, Petitioners built eleven houses and one unit of apartment houses on their respective lots, with the “total cost and the reasonable value of the work” to complete each of the structures being separately itemized and stipulated. The cost and value of the eleven completed houses totaled $183,437.02 for an average of approximately $16,676.00 per house. The apartment house unit, owned and built by Petitioner Charles McEntire, was stipulated to have a total cost and value of $316,909.95.

Charles McEntire, who had the largest financial interest of any of the owner-builders, was an experienced builder and developer in the area. He testified that he had built about 150 houses since 1953. Although operating under five separate ownerships of land and improvements, Petitioners apparently cooperated in some of their efforts, including the timing of construction. Foundation work on the structures began in November of 1968; the last of the houses was completed in July of 1969; and the apartment house unit was completed in September of 1969. All had been sold before the trial on September 17, 1970.3

Each of the owner-builders contracted under separate agreements with Glenn McEntire, brother of Petitioner Charles McEntire, for the construction of a concrete foundation for a building with respect to each separately owned tract of land. They required no surety bonds for payment of liens as authorized by Article 5472d. Glenn McEntire purchased steel and concrete materials for the foundations from Respondents, Western Steel Company and Gulf Concrete Company, respectively, but failed to pay them in full for such materials. From the stipulations, and other evidence, it appears that total contract price agreed upon with Glenn McEntire was $49,581.00; that the total of Respondents’ unpaid claims for materials furnished Glenn McEntire amounted to $20,002.87; that each foundation was completed less than 30 days after delivery of the materials ; that each owner-builder paid Glenn McEntire in full before learning that he had not paid Respondents; and that both the notices of unpaid claims and the lien affidavits were given and filed by Respondents more than 30 days after the foundations were completed but prior to the completion of the respective buildings and less than 90 days after the respective indebtedness accrued.

It was further stipulated that the Petitioner owner-builders did not retain any funds during construction or for thirty days after the completion of construction of their respective buildings. They do not deny that Article 5469 and its ten per cent retainage fund applies to them as owner-builders, but they insist that it does not require them to hold or become liable for the same amount (10% of the total cost or value of each house) as if they had entered general “turn-key” contracts for the entire construction of their respective houses. They contend that if liable to Respondents for any amount, it is limited to ten per cent of their respective contract prices with Glenn McEntire for the foundation work, which would total $4,958.10 to be applied ratably on the unpaid claims of Respondents for $20,002.87. Under Respondents’ interpretation of. Article 5469, the Petitioners are liable on each building up to ten per cent of the cost or value thereof (a total of $50,034.69), which would enable each of their respective claims to be fully satisfied.

[789]*789The relevant portions of Articles 5452 and 5469, as amended in 1961, are as follows:

“Art. 5452. [5621] [3294] Lien prescribed.
“1. Any person or firm, lumber dealer or corporation, artisan, laborer, mechanic or sub-contractor who may labor, specially fabricate material, or furnish labor or material: (a) for the construction or repair of any house, building or improvement whatever', (b) for the construction or repair of levees or embankments to be erected for the reclamation of overflow lands along any river or creek; (c) or for the construction or repair of any railroad: within this state under or by virtue of a contract with the owner, owners, or his or their agent, trustee, receiver, contractor, contractors, or with any subcontractor; upon complying with the provisions of this Chapter shall have a lien on such house, building, fixtures, improvements, . . . and shall have a lien on the lot or lots of land necessarily connected therewith, . to secure payment: (a.) for the labor done or material furnished or both for such construction or repair; .
“2. For the purposes of this Act, the following definitions shall apply:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley Forge, Inc. v. CK Construction, Inc.
Court of Appeals of Texas, 2023
Trimcos, LLC v. Compass Bank
Court of Appeals of Texas, 2021
Shell Western E & P, Inc. v. Pel-State Bulk Plant, LLC
509 S.W.3d 581 (Court of Appeals of Texas, 2016)
Sommers v. Aguirre (In re Santoyo)
540 B.R. 284 (S.D. Texas, 2015)
Crawford Services, Inc. v. Skillman International Firm, L.L.C.
444 S.W.3d 265 (Court of Appeals of Texas, 2014)
Jewelry Manufacturer's Exchange, Inc. v. Tafoya
374 S.W.3d 639 (Court of Appeals of Texas, 2012)
Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc.
295 S.W.3d 763 (Court of Appeals of Texas, 2009)
In Re Huber Contracting, Ltd.
347 B.R. 205 (W.D. Texas, 2006)
New AAA Apartment Plumbers, Inc. v. DPMC-Briarcliff, L.P.
145 S.W.3d 728 (Court of Appeals of Texas, 2004)
San Antonio Credit Union v. O'CONNOR
115 S.W.3d 82 (Court of Appeals of Texas, 2003)
Texas Wood Mill Cabinets, Inc. v. Butter
117 S.W.3d 98 (Court of Appeals of Texas, 2003)
In Re Enron Corp.
295 B.R. 190 (S.D. New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
478 S.W.2d 786, 15 Tex. Sup. Ct. J. 232, 1972 Tex. LEXIS 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hayek-v-western-steel-company-tex-1972.