Jewelry Manufacturer's Exchange, Inc. v. Tafoya

374 S.W.3d 639, 2012 WL 2878160, 2012 Tex. App. LEXIS 5651
CourtCourt of Appeals of Texas
DecidedJuly 16, 2012
DocketNo. 05-11-00065-CV
StatusPublished
Cited by2 cases

This text of 374 S.W.3d 639 (Jewelry Manufacturer's Exchange, Inc. v. Tafoya) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jewelry Manufacturer's Exchange, Inc. v. Tafoya, 374 S.W.3d 639, 2012 WL 2878160, 2012 Tex. App. LEXIS 5651 (Tex. Ct. App. 2012).

Opinion

OPINION

Opinion by Justice MARTIN RICHTER.

In this appeal from a traditional summary judgment, Jewelry Manufacturer’s Exchange contends the trial court erred in granting summary judgment in favor of Herman Tafoya and in subsequently dismissing the case. We reverse the summary judgment and remand this case to the trial court for further proceedings. Background

Jewelry Manufacturer’s Exchange, Inc. (“JME”) hired George Benfante (“Ben-fante”) as a general contractor to perform remodeling work on JME’s retail leasehold property. The initial contract between Benfante and JME totaled $19,116.75. JME modified the contract with Benfante adding $4,250 in additional charges for a total amount of $23,366.75. Subsequently, Benfante subcontracted the electrical work to be performed under the contract with Herman Tafoya, d/b/a Abundant Light Electric (“Tafoya”). The proposal submitted by Tafoya to Benfante estimated the electrical work would cost $21,320.14. After partially performing on the contract, Tafoya submitted two invoices and was [641]*641paid a total of $7,250. Tafoya received a third payment from Benfante for $6,000 in the form of a check that was returned because the bank account on which it had been written was closed. Tafoya completed 80% of the remodel project and then stopped work on or about April 26, 2010.

After Tafoya stopped work, he obtained counsel and on May 20, 2010 sent notice with statutory fund-trapping language to Benfante, JME, and Eagle-Spring Creek, L.P. and Eagle Spring, GP, LLC, (“Eagle Spring” are owners of the retail property). Tafoya also filed an Affidavit Claiming Lien on May 24, 2010. After receiving notice from Tafoya, JME hired and paid $5,611.28 to replacement contractors who completed the electrical work. JME further paid $267.33 for construction materials and $2,420 for plumbing labor and materials to complete the remodel.

Tafoya subsequently sued Eagle Spring, Benfante, and JME under various theories of liability. Tafoya obtained a default judgment against Benfante and moved for summary judgment against Eagle Spring, and JME. After moving for summary judgment, Tafoya settled with Eagle Spring for an undisclosed amount which left JME as the last remaining defendant. The district court granted Tafoya’s summary judgment against JME and awarded Tafoya $10,635.24, pre-judgment interest of $1,211.54, and attorneys’ fees of $17,000 through trial (with additional amounts in the event of an appeal).

In four issues, JME asserts the trial court erred by granting Tafoya’s motion for summary judgment because (1) JME established a material fact existed regarding the retainage amount because completion of the project was not determined, (2) damages were improperly awarded for amounts under the fund-trapping statute, (3) pre-judgment interest was improperly awarded, and (4) a material fact issue remained regarding the reasonableness and necessity of Tafoya’s attorneys’ fees.

Standard of Review

We review a traditional summary judgment under well-established standards. See Tex.R. Civ. P. 166a(c); Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548 (Tex.1985). A summary judgment is properly granted when the movant establishes that there are no genuine issues of material fact and it is entitled to judgment as a matter of law. Nixon, 690 S.W.2d at 548. All evidence favorable to the non-movant will be taken as true when deciding whether there is a disputed material fact issue precluding summary judgment. Id. at 548-49. Every reasonable inference must be indulged in favor of the non-movant and any doubts resolved in its favor. Id. at 549. We review the summary judgment de novo to determine whether Tafoya’s right to prevail is established as a matter of law. See Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex.2005); Calpine Producer Servs., L.P. v. Wiser Oil Co., 169 S.W.3d 783, 786 (Tex.App.-Dallas 2005, no pet.).

Issues to be considered by the trial court in determining the motion for summary judgment must be presented in the motion or in an answer or other response to the motion. See Tex.R. Civ. P. 166a(c); McConnell v. Southside Indep. Sch. Dist., 858 S.W.2d 337, 340-43 (Tex.1993). A summary judgment cannot be affirmed on grounds not expressly set out in the motion or response. Stiles v. Resolution Trust Corp., 867 S.W.2d 24, 26 (Tex.1993). Analysis

In its first and second issues, JME complains the trial court erred in granting Tafoya’s summary judgment. JME claims it was error for the trial court to grant Tafoya the full amount of the lien because a fact issue existed over the percentage of [642]*642completion of the project for the purpose of determining the' proper amount of re-tainage.

The Property Code states:

(a) During the progress of work under an original contract for which a mechanic’s lien may be claimed and for 30 days after the work is completed, the owner shall retain:
(1) 10 percent of the contract price of the work to the owner; or
(2) 10 percent of the value of the work, measured by the proportion that the work done bears to the work to be done, using the contract price or, if there is no contract price, using the reasonable value of the completed work.
(b) In this section, “owner” includes the owner’s agent, trustee, or receiver.

Tex. Prop.Code Ann. § 53.101 (West 2007). The owner must retain ten percent of the project’s cost regardless of how many individual construction contracts were awarded. Hayek v. W. Steel Co., 478 S.W.2d 786, 792-93 (Tex.1972). Subcontractors rely on their statutory, derivative rights to collect funds due by the owner to the contractor or to impose a lien on the property. Stolz v. Honeycutt, 42 S.W.3d 305, 310 (Tex.App.-Houston [14th Dist.] 2001, no pet.).

The trial court awarded Tafoya $10,635.24 of which $2,336.68 (ten percent of the total contract price) was the retain-age amount. The summary judgment evidence is clear and uncontroverted as to the original contract amount between Benfante and JME as $19,116.77 with a 15% discount.1 It is also clear that modifications were made to the original contract with additional charges for a final amount of $23,366.75. Behzad Sarhady, vice-president of JME, testified he paid Benfante “in full for all of the electrical goods, materials, and services supplied to the JME premises.” However, the affidavits of the replacement contractors state they were hired by JME to complete the electrical work that Tafoya initiated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
374 S.W.3d 639, 2012 WL 2878160, 2012 Tex. App. LEXIS 5651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jewelry-manufacturers-exchange-inc-v-tafoya-texapp-2012.