Page v. Structural Wood Components, Inc.

102 S.W.3d 720, 46 Tex. Sup. Ct. J. 561, 2003 Tex. LEXIS 42, 2002 WL 32069568
CourtTexas Supreme Court
DecidedApril 3, 2003
Docket01-1122
StatusPublished
Cited by25 cases

This text of 102 S.W.3d 720 (Page v. Structural Wood Components, Inc.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page v. Structural Wood Components, Inc., 102 S.W.3d 720, 46 Tex. Sup. Ct. J. 561, 2003 Tex. LEXIS 42, 2002 WL 32069568 (Tex. 2003).

Opinions

Chief Justice PHILLIPS

delivered the opinion of the Court,

in which Justice HECHT, Justice OWEN, Justice O’NEILL, Justice SCHNEIDER, Justice SMITH, and Justice WAINWRIGHT joined.

Chapter 53 of the Property Code permits a construction subcontractor to claim a hen on funds retained by the owner if the subcontractor “(1) sends the notices required by this chapter in the time and manner required; and (2) files an affidavit claiming a hen not later than the 30th day after the work is completed.” Tex. PROP. Code § 53.103. In this case, the owner terminated the general contractor and hired other contractors to complete the project. The question before us is when, in fulfilling the affidavit requirement of the statute, “work” is completed. The subcontractor here filed its affidavit thirty-one days after the original contract was terminated but well before subsequent contractors finished the project. The court of appeals held that work is completed when the requirements of the initial contract are finished, either by the first contractor or by subsequent contractors. 57 S.W.3d 524. Because we conclude that work must be defined in relation to a particular contract, and that the work under that contract was completed when the contract was terminated, we hold that the affidavit was not timely filed. Consequently, we reverse the court of appeals’ judgment and render judgment that the subcontractor take nothing.

I

In 1997, Herman C. Page hired Mark Sepolio as general contractor on a $300,000 remodeling and expansion project for a building that Page owned in Houston. Se-polio in turn hired several subcontractors, including Structural Wood Components, Inc. (Structural Wood), to provide labor and materials. Structural Wood completed its portion of the job in mid-March, 1998. As work progressed on the construction, Page made periodic payments to Sepolio totaling $270,000. Before the project was finished, however, Page and Sepo-lio quarreled over the work, and Sepolio requested additional funds to finish the project. Page refused, and on April 14, 1998, he terminated Sepolio’s contract. Page then hired six new contractors to finish the construction. Without hiring additional subcontractors, the new contractors completed the project on July 21, 1998, for a total payment of $27,074.43.

Meanwhile, because Sepolio failed to pay in full for its labor and materials, Structural Wood filed an affidavit claiming a lien on the property on May 15, 1998, thirty-one days after Page terminated the contract with Sepolio. Structural Wood subsequently filed suit to foreclose on its lien. After a bench trial, the trial court concluded that the work was completed on July 21, 1998, when the replacement contractors finished the project. The trial court held Sepolio and Page jointly and severally liable to Structural Wood for $11,861 in actual damages plus pre- and post-judgment interest and costs. The court further ordered foreclosure of the lien on Page’s property and held Page individually [722]*722liable for $4,000 in attorney’s fees. Page appealed and the court of appeals reformed the judgment to eliminate the foreclosure order, holding that no evidence supported the trial court’s finding that Page had failed to retain ten percent of the contract price as required by section 53.101 of the Property Code. 57 S.W.3d at 529. However, based on section 53.103, the court of appeals upheld the personal judgment against Page, concluding that Structural Wood would still be entitled to a hen on retained funds as long as the lien affidavit was timely filed. Id. at 531-32. Like the trial court, the court of appeals interpreted the statutory definition of completion as the date when the additional contractors finished the project in July 1998. Id.

II

The Texas Property Code requires owners to retain either “10 percent of the contract price of the work to the owner” or “10 percent of the value of the work ... using the contract price or, if there is no contract price, using the reasonable value of the completed work” for “30 days after the work is completed.” Tex. Prop.Code § 53.101. These retained funds “secure the payment of artisans and mechanics who perform labor or service,” including subcontractors such as Structural Wood. Id. § 53.102. A subcontractor or other claimant who wants to make a claim on that retainage must properly give notice and file “an affidavit claiming a lien not later than the 30th day after the work is completed.” Id. § 53.103. The period during which a claimant can and must file a lien affidavit under section 53.103 is therefore the same period that an owner can and must hold retainage under section 53.101— thirty days after the completion of work. It is consequently in the best interest of all construction participants to know when the thirty-day period terminates — the owner so that it can release the remaining funds, the original contractor so that it can budget for its final payment, and the claimant so that it can file the lien affidavit before that date.

To determine when the thirty-day period ends, we look to the statutory definitions of “work” and “completion of an original contract.” The Property Code provides that “ ‘[cjompletion’ of an original contract means the actual completion of the work, including any extras or change orders reasonably required or contemplated under the original contract....” Tex. Prop.Code § 53.001(15).1 The Code defines “work” as “any part of construction of repair performed under an original contract.” Tex. PROp.Code § 53.001(14). The parties’ statutory interpretations focus on different words within these definitions.

Page focuses on the phrase “under an original contract”2 and contends that work under an individual contract should [723]*723be deemed completed when the contract is terminated or abandoned. He argues that just as a contract’s retainage amount will change when the contract price is later modified, so too should the retainage period change when the work is modified. Page argues that the work contemplated under a contract is necessarily completed when a contract is terminated, as no additional work is contemplated under that contract.

Structural Wood focuses on the word “contemplated” and counters that because the statute requires “actual completion of the work ... reasonably required or contemplated under the original contract,” a court should determine completion based on when all the work initially contemplated under the original contract is finished. In this case, the original contract contemplated the remodeling and expansion of the building, so the lien affidavit could be filed at any time within thirty days of the project’s completion. In accepting this interpretation, the court of appeals noted that the statute did not “specify that the work only be done by the contractor who started it, as opposed to a substitute contractor.” 57 S.W.3d at 531. Structural Wood argues that the alternative interpretation urged by Page works a hardship on subcontractors, who must file their lien affidavits in a shorter time and who may not know if an owner has terminated the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jewelry Manufacturer's Exchange, Inc. v. Tafoya
374 S.W.3d 639 (Court of Appeals of Texas, 2012)
Ready Cable, Inc. v. RJP Southern Comfort Homes, Inc.
295 S.W.3d 763 (Court of Appeals of Texas, 2009)
Entergy Gulf States, Inc. v. Summers
282 S.W.3d 433 (Texas Supreme Court, 2009)
Opinion No.
Texas Attorney General Reports, 2008
Untitled Texas Attorney General Opinion
Texas Attorney General Reports, 2008
In Re Kleibrink
346 B.R. 734 (N.D. Texas, 2006)
ADVANCE'D TEMPORARIES, INC. v. Reliance Surety Co.
165 S.W.3d 1 (Court of Appeals of Texas, 2005)
Montgomery v. R.E.C. Interests, Inc.
130 S.W.3d 444 (Court of Appeals of Texas, 2004)
Page v. Marton Roofing, Inc.
102 S.W.3d 733 (Texas Supreme Court, 2003)
Page v. Structural Wood Components, Inc.
102 S.W.3d 720 (Texas Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
102 S.W.3d 720, 46 Tex. Sup. Ct. J. 561, 2003 Tex. LEXIS 42, 2002 WL 32069568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-v-structural-wood-components-inc-tex-2003.