Page v. Structural Wood Components, Inc.

57 S.W.3d 524, 2001 Tex. App. LEXIS 5726, 2001 WL 950803
CourtCourt of Appeals of Texas
DecidedAugust 23, 2001
DocketNo. 14-00-00824-CV
StatusPublished
Cited by4 cases

This text of 57 S.W.3d 524 (Page v. Structural Wood Components, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page v. Structural Wood Components, Inc., 57 S.W.3d 524, 2001 Tex. App. LEXIS 5726, 2001 WL 950803 (Tex. Ct. App. 2001).

Opinion

OPINION

MAURICE AMIDEI, Justice (Assigned).

This is a mechanic’s and materialman’s lien case. Property-owner Herman C. Page appeals from a judgment awarding subcontractor Structural Wood Components, Inc. (‘Wood”) a judgment against Page for $11,861 in actual damages, $1,442 as pre-judgment interest, $4,000 in attorney’s fees, and foreclosure of Wood’s mechanic’s and materialman’s lien in Page’s real property. For the reasons stated below, we modify the judgment by removing the in rem relief against Page’s real property, and we affirm the judgment as modified.

Background

Page entered into a contract with Mark Sepolio, Sr. d/b/a Custom Concrete & Construction, Inc. (“Sepolio”) sometime prior to September 1, 1997 to remodel improvements on Page’s property at 3502 Dover, [526]*526Houston, Texas (“Property”). The parties fixed the contract price at $300,000. Page made periodic progress payments to Sepo-lio with the last payment being made on March 25, 1998. The total amount paid to Sepolio was $270,000. In April of 1998, Sepolio refused to finish the work on the Property unless Page advanced additional funds to him. Page considered that Sepo-lio was in breach of his contract, and Page’s tenant was threatening to cancel its lease unless the work was finished promptly. Therefore, Page terminated Sepolio’s contract on April 14, 1998 and has not paid Sepolio any money since that termination.

At trial, Page’s attorney-in-fact testified that $30,000 in retainage (10% of $300,000) had been held back from the payments to Sepolio. Immediately after termination, Page hired various substitute contractors to finish the work. Page paid these contractors a total of $27,074.43. The construction work was finished on July 21, 1998. Page made the payments to the substitute contractors from his operating account. There were no subcontractors performing work or supplying materials to any of the substitute contractors.

Wood was a subcontractor who agreed with Sepolio to provide goods and services to the project. When Sepolio defaulted in his payments to Wood, Wood filed a mechanic’s and materialman’s lien affidavit in the Real Property Records of Harris County on May 15,1998 (“Lien Affidavit”). Wood sent a copy of its notice of claim to Page by certified mail on May 15, 1998 and a copy of the Lien Affidavit to Page on May 18, 1998. On September 17, 1998, Page paid $3,582.74 to Sherwin Williams Company, another subcontractor on the project who had filed a lien affidavit on June 2,1998.

After a bench trial, the trial court granted Wood a judgment against Sepolio and Page jointly and severally for actual damages of $11,861, $1442 in prejudgment interest, postjudgment interest and court costs. The judgment also ordered Page to pay $4,000 in attorney’s fees to Wood, found that Wood’s mechanic’s and materi-alman’s lien in the Property (“Lien”) is valid, and ordered foreclosure of the Lien. The trial court filed findings of fact and conclusions of law.

Issues Presented

On appeal, Page asserts the following issues: (1) Is the trial court’s finding of fact number 4 erroneous because the Lien Affidavit did not contain a jurat? (2) Is the first sentence of the trial court’s finding of fact number 5 erroneous because the Lien Affidavit did not contain a jurat? (3) Is the last sentence of the trial court’s finding of fact number 7 erroneous because there was no evidence that Page used the remaining funds under the contract to pay other contractors to complete the work? (4) Is the trial court’s finding of fact number 10 erroneous because there was no evidence that Page failed to retain ten percent of the contract price? (5) In the alternative, are the findings complained of in issues 3 and 4 erroneous under a factual insufficiency analysis? (6) Did the trial court err in its conclusion of law number 1 that Wood complied with the requirements of the Texas Property Code as to the notice and filing of its Lien Affidavit and that Wood holds a valid Lien? (7) Did Page’s general denial put in issue the lack of a jurat in Wood’s Lien Affidavit? (8) Did the trial court abuse its discretion by overruling Page’s motion for leave to file a trial amendment raising the lack of a jurat? (9) Did Wood perfect its retainage lien as follows: (a) by proving that Page did not retain ten percent of the contract price until 30 days after completion of the job; and (b) by timely filing the Lien Affidavit and timely sending a copy of [527]*527the affidavit to Page? (10) Is Wood’s right to recover money from Page or to impose a lien on Page’s Property under the fund-trapping provisions of the Texas Property Code derivative of the original contractor’s right to recover against Page?

Standards of Review

In most of the issues that we rule on in this opinion, Page contends that there was no evidence to support the trial court’s findings in this case. The trial court’s findings of fact have the same force and dignity as a jury verdict, and this court reviews sufficiency challenges to findings of fact by the same standards that apply in reviewing a jury’s findings. Anderson v. City of Seven Points, 806 S.W.2d 791, 794 (Tex.1991).

When reviewing a no-evidence challenge, this court may consider only the evidence and reasonable inferences therefrom that support the challenged findings, and this court disregards all evidence and inferences to the contrary. Texarkana Memorial Hosp., Inc. v. Murdock, 946 S.W.2d 836, 838 (Tex.1997). This court may sustain a no-evidence challenge if the record reveals one of the following: (1) the complete absence of a vital fact; (2) the court is barred by rules of law or of evidence from giving weight to the only evidence offered to prove a vital fact; (3) the evidence offered to prove a vital fact is no more than a scintilla; or (4) the evidence established conclusively the opposite of the vital fact. Uniroyal Goodrich Tire Co. v. Martinez, 977 S.W.2d 328, 334 (Tex.1998). More than a scintilla of evidence exists where the evidence supporting the finding, as a whole, rises to a level that would enable reasonable and fair-minded people to differ in their conclusions. Merrell Dow Pharm., Inc. v. Havner, 953 S.W.2d 706, 711 (Tex.1997).

Also, to the extent that Page’s issues require a construction of Chapter 53 of the Texas Property Code, our objective is to determine and give effect to the legislature’s intent. See National Liability and Fire Ins. Co. v. Allen, 15 S.W.3d 525, 527 (Tex.2000). We presume that the legislature intended the plain meaning of its words. Id. If possible, we must ascertain the legislature’s intent from the language it used in the statute and not look to extraneous matters for an intent the statute does not state. Id. When interpreting a statute, we consider the entire act, its nature and object, and the consequences that would follow from each construction. Atascosa County v. Atascosa County Appraisal Dist., 990 S.W.2d 255, 258 (Tex.1999).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Page v. Structural Wood Components, Inc.
102 S.W.3d 720 (Texas Supreme Court, 2003)
Page, Herman v. Marton Roofing, Inc.
Court of Appeals of Texas, 2002
Page v. Marton Roofing, Inc.
102 S.W.3d 750 (Court of Appeals of Texas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
57 S.W.3d 524, 2001 Tex. App. LEXIS 5726, 2001 WL 950803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-v-structural-wood-components-inc-texapp-2001.