Page v. Marton Roofing, Inc.

102 S.W.3d 750, 2002 Tex. App. LEXIS 5614, 2002 WL 1764979
CourtCourt of Appeals of Texas
DecidedAugust 1, 2002
Docket01-01-00737-CV
StatusPublished
Cited by5 cases

This text of 102 S.W.3d 750 (Page v. Marton Roofing, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page v. Marton Roofing, Inc., 102 S.W.3d 750, 2002 Tex. App. LEXIS 5614, 2002 WL 1764979 (Tex. Ct. App. 2002).

Opinion

OPINION

TIM TAFT, Justice.

Appellant, Herman Page, challenges a summary judgment rendered against him and in favor of appellee, Marton Roofing, Inc. (MRI), in a lien-enforcement action. Page raises three issues on appeal: (1) the trial court erred as a matter of law in ruling that MRI timely filed a perfected hen; (2) the trial court erred as a matter of law in ruling that MRI comphed with the fund-trapping provisions of the Texas Property Code; and (3) the trial court *751 erred in awarding MRI costs and attorney’s fees. We affirm.

Facts

The material facts in this case are undisputed. In August 1997, Page entered into an oral contract (Original Contract) with Mark Sepolio, Sr., who was doing business as Custom Concrete & Construction (Sepo-lio). The Original Contract called for remodeling and expanding a building located at 3502 Dover, Houston, Texas, at the price of $300,000.00. Page made periodic payments totaling $270,000.00. MRI was a subcontractor of Sepolio under the Original Contract. MRI completed its portion of the Original Contract in March 1998. In April 1998, Sepolio demanded that Page advance additional funds to complete the work, and Page refused. Page terminated the Original Contract on April 14, 1998.

Page immediately found several other contractors to finish the project and paid them a total of $30,657.17, with the last payment made on July 21, 1998, when the project was completed. When Sepolio failed to pay MRI under the Original Contract, MRI sent notices of claims totaling $26,892.75 to both Sepolio and Page. MRI filed a mechanic’s and materialman’s lien affidavit on June 15, 1998 and sent a copy to Page. Both parties moved for summary judgment, and the trial court granted summary judgment in favor of MRI and awarded costs and attorney’s fees to MRI. •

Standard of Review

We follow the usual standards for reviewing a summary judgment under Texas Rule of Civil Procedure 166a(e). The mov-ant must show that (1) there is no genuine issue of material fact and (2) it is entitled to judgment as a matter of law. Nixon v. Mr. Prop. Mgmt. Co. Inc., 690 S.W.2d 546, 548-49 (Tex.1985). Proof that there are no disputed facts does not automatically entitle the movant to summary judgment; it must still show that, under those undisputed facts, Texas law directs judgment in its favor. St. Paul Ins. Co. v. Mefford, 994 S.W.2d 715, 718 (Tex.App.-Dallas 1999, pet. denied).

Lien Perfection

In his first issue, Page contends that MRI failed to file a timely lien affidavit. In his second issue, Page contends that MRI did not have a lawful fund-trapping claim because MRI’s right to the trapped funds is derivative of the original contractor; therefore, if the original contractor does not have a legal claim, neither does MRI.

A. Filing of Lien Affidavit

Because the Original Contract was entered into in August 1997, we apply the Property Code effective at that time. 1 Chapter 53 of the Texas Property Code provides the requirements for “retainage” and the means by which to secure a lien against such retained funds:

Section 53.101. Required Retainage
(a) During the progress of work under an original contract for which a mechanic’s lien may be claimed and for 30 days after the work is completed, the owner shall retain:
(1) 10 percent of the contract price of the work to the owner; or
(2) 10 percent of the value of the work, measured by the proportion that the work done bears to the work to be done, using the contract *752 price or, if there is no contract price, using the reasonable value of the completed work.
Section 58.103. Lien on Retained Funds A claimant has a lien on the retained funds if the claimant:
(1) sends the notices required by this chapter in the time and manner required; and
(2) files an affidavit claiming a lien not later than the 30th day after the work is completed.

Tex. Prop.Code Ann. §§ 53.101, 53.103 (Vernon 1995) (emphasis added).

The parties agree that Page maintained the proper retainage under section 53.101 and that MRI provided proper notice of claim on May 21, 1998. See Tex. Prop. Code Ann. §§ 53.101, 53.103(1) (Vernon 1995). Page, however, contends that MRI did not timely file the lien affidavit as required under section 53.103(2). See Tex. Prop.Code Ann. § 53.103(2) (Vernon 1995). In order to determine if the lien affidavit was timely filed, we must decide as a matter of law the meaning of “completion of work.” See id.

We look to the statute to define “completion of work.” Statutory language should be construed according to the rules of grammar and common usage. Tex. Gov’t Code Ann. § 311.011(a) (Vernon 1998). We should also consider that the purpose of the statute is to protect laborers and materialmen, and, consequently the statute should be interpreted liberally in their favor. TDIndus., Inc. v. NCNB Texas Nat’l Bank, 837 S.W.2d 270, 272 (Tex.App.-Eastland 1992, no writ).

The terms “completion” and “work” are defined in the statute. ‘Work” means “any part of construction or repair performed under an original contract.” Tex. Prop.Code Ann. § 53.001(14) (Vernon 1995). 2 At the time of the Original Contract’s signing, “completion” meant “the actual completion of the work, including any extras or change orders reasonably required or contemplated under the original contract, other than warranty or repair work.” Tex. Prop.Code Ann. § 53.106(e) (Vernon 1995). 3

Page contends that the work was completed when Sepolio demanded additional funds and Page refused by terminating the contract on April 14, 1998. MRI contends the work was completed on July 21, 1998, when the other subcontractors finished the work outlined under the Original Contract. MRI filed its lien affidavit on June 15, 1998. If the work was completed on April 14, 1998, then MRI did not timely file its lien affidavit. On the other hand, if the work was not completed until July 21, 1998, then MRI did timely file its lien affidavit.

In TDIndustries, the Eastland court of appeals found that section 53.106(e) expressly defines “completion” as when all of the work is to be completed under the original contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arias v. Brookstone, L.P.
265 S.W.3d 459 (Court of Appeals of Texas, 2008)
Page v. Marton Roofing, Inc.
102 S.W.3d 733 (Texas Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
102 S.W.3d 750, 2002 Tex. App. LEXIS 5614, 2002 WL 1764979, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-v-marton-roofing-inc-texapp-2002.