K & N Builders Sales, Inc. v. Dennis Baldwin and Rosella Baldwin

CourtCourt of Appeals of Texas
DecidedMarch 28, 2013
Docket14-12-00012-CV
StatusPublished

This text of K & N Builders Sales, Inc. v. Dennis Baldwin and Rosella Baldwin (K & N Builders Sales, Inc. v. Dennis Baldwin and Rosella Baldwin) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K & N Builders Sales, Inc. v. Dennis Baldwin and Rosella Baldwin, (Tex. Ct. App. 2013).

Opinion

Affirmed and Memorandum Opinion filed March 28, 2013.

In the

Fourteenth Court of Appeals

NO. 14-12-00012-CV

K&N BUILDER SALES, INC., Appellant V.

DENNIS BALDWIN AND ROSELLA BALDWIN, Appellees

On Appeal from the 334th District Court Harris County, Texas Trial Court Cause No. 2009-64811

MEMORANDUM OPINION

Appellant K&N Builder Sales, Inc. (K&N) appeals the judgment from a bench trial in which the trial court concluded that the affidavit filed on behalf of K&N did not create a valid lien on appellees Dennis and Roselle Baldwin’s property and awarded the Baldwins $11,141 in monetary damages. K&N argues that the trial court erred in finding that (1) K&N’s affidavit claiming a lien was untimely filed; (2) the Baldwins were entitled to a judgment against K&N; and (3) the contract between the Baldwins and the home builder GSG Builders, Inc. (GSG) was terminated on March 28, 2009. Because the record contains sufficient evidence to support the trial court’s findings and judgment, we affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

The Baldwins contracted with GSG in February 2008 to build a home in Houston, Texas. The contract called for a total amount of payments to GSG of $1,066,800, and for 10% retainage to be withheld from all payments to GSG. The Baldwins financed the contract with cash and also through a construction loan. On the Baldwins’ behalf, the bank withheld the 10% retainage.

One of the subcontractors, K&N, supplied appliances to the project on March 18 and 25, 2009. GSG owed K&N $27,740.71 for these appliances. The Baldwins moved into the completed home on March 28, 2009. Facing financial difficulties, GSG failed to pay money owed to various subcontractors, including K&N. Once the Baldwins found out that GSG had not paid its subcontractors, the Baldwins requested that the bank release the retainage, which amounted to $111,102, into escrow with the title company for the benefit of the unpaid subcontractors.

On May 15, 2009, K&N filed an affidavit claiming a lien on the property. On June 5, counsel for the Baldwins sent a letter to the subcontractors GSG had not paid, including K&N, instructing them not to file liens on the property, and informing them that the Baldwins had complied with section 53.101 of the Texas Property Code to withhold 10% of the contract price for the benefit of subcontractors, that the statutorily-retained funds would be available on or after July 17, and that they would be receiving 61.29% of the funds they were due. The Baldwins’ counsel also sent counsel for K&N a copy of the agreement paying the retainage into escrow. K&N refused to accept its pro rata share of the retained 2 funds ($17,002.28) and to release the lien. Because of K&N’s lien on the property, the Baldwins were unable to secure refinancing in the form of a conventional mortgage and thus reduce their interest rate from 5.75% to 4.789%; they paid extra interest on their note in the amount of $11,141.

The Baldwins filed suit against K&N seeking a declaratory judgment, discharge of the lien, and special damages for slander of title. K&N filed a counterclaim seeking to foreclose its lien on the property. After a bench trial, the trial court issued findings of fact and conclusions of law.

The trial court issued findings of fact that GSG was paid all monies due under the contract with the Baldwins, except for the $111,102 retainage; the Baldwins moved into the residence on March 28, 2009; GSG performed no work at the Baldwin residence after March 28; the contract between the Baldwins and GSG was terminated on March 28; K&N filed an affidavit claiming a lien on the Baldwins’ property on May 15; May 15 is more than 30 days after GSG completed its work on the Baldwins’ residence and more than 30 days after the contract between the Baldwins and GSG was terminated; and the Baldwins have paid $11,141 in interest charges they would not have incurred but for the lien K&N placed on the residence.

The trial court issued conclusions of law that because the Baldwins complied with the retainage provisions of the Property Code, the extent of their liability to derivative claimants was limited to the retained amount, plus any funds that should have been trapped under the Code; with regard to the contract between the Baldwins and GSG, all work done under the contract was completed by March 28, and any remaining portion of the contract was terminated on that date; K&N did not file its affidavit claiming a lien within 30 days from the date construction was completed, or the original contract terminated, as required by section 53.103(2)(A)

3 and (B) of the Code, and therefore, K&N’s filing did not have the effect of creating a valid lien on retainage; the Baldwins are entitled to a judgment declaring K&N’s lien affidavit void and without effect; and the Baldwins are entitled to judgment against K&N in the amount of $11,141 for the wrongful lien on their real property.

The trial court signed a final judgment declaring that K&N’s lien affidavit did not have the effect of creating a valid lien on the Baldwins’ property or on the statutory retainage; ordering that the Baldwins have final judgment against K&N for actual damages of $11,141, plus pre- and post-judgment interest; and ruling that K&N take nothing on its counterclaims. K&N timely appealed.

II. APPLICABLE LAW

Section 53.101 of the Texas Property Code provides that “[d]uring the progress of work under an original contract for which a mechanic’s lien may be claimed and for 30 days after the work is completed, the owner shall retain . . . 10 percent of the contract price of the work to the owner.” TEX. PROP. CODE ANN. § 53.101 (West 2007). “The retained funds secure the payment of artisans and mechanics who perform labor or service and the payment of other persons who furnish material, material and labor, or specially fabricated material for any contractor, subcontractor, agent, or receiver in the performance of the work.” Id. § 53.102. Section 53.103 provides:

A claimant has a lien on the retained funds if the claimant: (1) sends the notices required by this chapter in the time and manner required; and (2) files an affidavit claiming a lien not later than the 30th day after the earlier of the date: (A) the work is completed; (B) the original contract is terminated; or (C) the original contractor abandons performance under the

4 original contract.

Id. § 53.103; see Page v. Structural Wood Components, Inc., 102 S.W.3d 720, 722–23, 726 (Tex. 2003) (holding that subcontractor’s “affidavit was not timely filed in this case, as it was filed thirty-one days after [owner] terminated [general contractor]’s construction contract”). “[A] subcontractor’s lien rights are totally dependent on its compliance with the statutes authorizing the lien.” First Nat’l Bank v. Sledge, 653 S.W.2d 283, 285 (Tex. 1983).

III. STANDARD OF REVIEW

Findings of fact entered in a case tried to the court have the same force and dignity as a jury’s verdict on jury questions, and they are reviewable for legal and factual sufficiency by the same standards applied in reviewing evidence supporting a jury’s answer. See Catalina v. Blasdel, 881 S.W.2d 295, 297 (Tex. 1994). In determining if the evidence is legally sufficient, we must consider evidence in the light most favorable to the challenged finding and indulge every reasonable inference that would support it. City of Keller v. Wilson, 168 S.W.3d 802

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Page v. Structural Wood Components, Inc.
102 S.W.3d 720 (Texas Supreme Court, 2003)
Trenholm v. Ratcliff
646 S.W.2d 927 (Texas Supreme Court, 1983)
Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Stolz v. Honeycutt
42 S.W.3d 305 (Court of Appeals of Texas, 2001)
Kazmir v. Benavides
288 S.W.3d 557 (Court of Appeals of Texas, 2009)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
A. H. Belo Corp. v. Sanders
632 S.W.2d 145 (Texas Supreme Court, 1982)
Barrientos v. Nava
94 S.W.3d 270 (Court of Appeals of Texas, 2002)
Fidelity Mutual Life Insurance Co. v. Robert P. Kaminsky, M.D., P.A.
768 S.W.2d 818 (Court of Appeals of Texas, 1989)
TDIndustries, Inc. v. NCNB Texas National Bank
837 S.W.2d 270 (Court of Appeals of Texas, 1992)
First National Bank in Graham v. Sledge
653 S.W.2d 283 (Texas Supreme Court, 1983)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Federal Sign v. Texas Southern University
951 S.W.2d 401 (Texas Supreme Court, 1997)
Waggoner v. Morrow
932 S.W.2d 627 (Court of Appeals of Texas, 1996)
Williams v. Jennings
755 S.W.2d 874 (Court of Appeals of Texas, 1988)
Airway Insurance Co. v. Hank's Flite Center, Inc.
534 S.W.2d 878 (Texas Supreme Court, 1976)
Holley v. Watts
629 S.W.2d 694 (Texas Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
K & N Builders Sales, Inc. v. Dennis Baldwin and Rosella Baldwin, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-n-builders-sales-inc-v-dennis-baldwin-and-rosell-texapp-2013.