Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant)

CourtCourt of Appeals of Texas
DecidedNovember 19, 2025
Docket04-22-00756-CV
StatusPublished

This text of Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant) (Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant)) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant), (Tex. Ct. App. 2025).

Opinion

Fourth Court of Appeals San Antonio, Texas MEMORANDUM OPINION

No. 04-22-00756-CV

GRAPEVINE GROUP CONCRETE CONTRACTORS, INC., Appellant/Cross-Appellee

v.

YC PARTNERS, LTD. d/b/a Yantis Company and Yantis Corporation, Appellees/Cross-Appellants

From the 131st Judicial District Court, Bexar County, Texas Trial Court No. 2018-CI-05255 Honorable Aaron Haas, Judge Presiding

Opinion by: Lori Massey Brissette, Justice

Sitting: Irene Rios, Justice Lori Massey Brissette, Justice H. Todd McCray, Justice

Delivered and Filed: November 19, 2025

REVERSED AND REMANDED

This case involves a complex web of conduct that resulted in a subcontractor walking off

two jobs and a contractor having to incur additional expenses to complete both projects. The trial

court, as factfinder, was tasked with determining, among other things, which party was first to

materially breach the contracts and whether the contractor was liable for failure to pay the

subcontractor under the Texas Construction Trust Fund Act and Texas Prompt Pay Act. We reverse

the case and remand for a new trial on all issues. 04-22-00756-CV

BACKGROUND

YC Partners, Ltd. d/b/a Yantis Company and Yantis Corporation (collectively, “YC”), a

construction contractor, hired Grapevine Group Contractors, Inc. (“Grapevine”) as subcontractor

to complete concrete work relating to two projects known as the Bandera Road Subdivision Unit

2 (“Bandera”) and Toepperwein Bluffs (“Toepperwein”). 1 The parties entered into two

subcontracts, one for each project, with nearly identical terms. The Bandera subcontract had an

estimated value of $207,435.00, which eventually increased to $217,332.00, and the Toepperwein

subcontract had an estimated value of $175,447.00.

After working together and securing payment for the first invoices in September, the

parties’ relationship began deteriorating when YC disputed the progress estimates provided by

Grapevine on each project as well as the amount due. Despite these disputes, the parties continued

to work together, with Grapevine continuing its concrete work and YC continuing to discuss the

necessary revisions and inspecting the work as it progressed. Then, Matt Yantis—YC’s owner—

took the position that YC’s payment to Grapevine on the projects would be contingent on

Grapevine’s satisfaction of an invoice due to Curv Compliance, a separate company owned by

Yantis which had provided OSHA safety classes to Grapevine employees. Grapevine initially

agreed to this approach, but then later reconsidered, giving notice that it was stopping the work on

both projects and would be filing liens. YC bonded around the liens and hired C4 Construction

Services, LLC (“C4”) to complete the projects.

Grapevine sued YC for, among other things, breach of contract (as to both projects),

quantum meruit, failure to comply with the Texas Prompt Payment Act and the Texas Construction

Trust Fund Act, and attorney’s fees. YC countersued for breach of contract (as to both projects),

1 The Bandera subdivision where the Bandera project took place was owned by M/I Homes of San Antonio, LLC. The Toepperwein subdivision where the Toepperwein project took place was owned by LECA Construction, LLC.

-2- 04-22-00756-CV

removal of fraudulent liens, and attorney’s fees. After a bench trial, the trial court entered a final

judgment granting YC, after all offsets and credits due, 2 damages from Grapevine in the amount

of $31,806.37, prejudgment and post-judgment interest, and attorney’s fees and court costs of

$55,421.01 (along with conditional attorney’s fees). 3 The trial court also issued extensive findings

of fact and conclusions of law.

Both companies appeal the trial court’s ruling raising multiple points of error including:

(1) the sufficiency of the evidence to support the trial court’s determination of which party first

materially breached the subcontracts, (2) the sufficiency of evidence supporting YC’s damages,

(3) the trial court’s calculation of Grapevine’s damages, (4) the trial court’s ruling as to

Grapevine’s claim for quantum meruit, (5) the trial court’s conclusions as to several claims based

on the Texas Property Code, and (6) the award of attorney’s fees.

FIRST MATERIAL BREACH 4

Grapevine argues the evidence is legally and factually insufficient to support the trial

court’s findings that it was the first to materially breach the subcontracts. Further, Grapevine

challenges the trial court’s finding that YC’s non-payment of invoices was not a prior material

breach which excused Grapevine’s continued performance. Further, Grapevine asserts that, even

2 The trial court did not delineate in its final judgment the amount of damages awarded to YC or the amount of damages awarded to Grapevine, instead simply setting forth an amount due to YC after offsets and credits. 3 The court also denied Grapevine’s claims against the other defendants, M/I Homes of San Antonio, LLC, Roberto C. Leal, LECA Construction, LLC, and Fidelity and Deposit Company of Maryland and declared Grapevine’s liens void. 4 “In many disputes over failure of performance, both parties fail to finish performance, and the question is whether one of them is justified in so doing by the other party’s failure.” RESTATEMENT (SECOND) OF CONTRACTS § 237(b) (1981). “This task can be as enigmatic as the childhood question: ‘Which came first—the chicken or the egg?’” Principle of Cure and Its Implications upon Materiality—Principle of “First Uncured Material Breach” as Justification for Future Contract Nonperformance, 5 BRUNER & O’CONNOR CONSTRUCTION LAW § 18:16; see Mustang Pipeline Co., Inc. v. Driver Pipeline Co., Inc., 134 S.W.3d 195, 200 (Tex. 2004) (“In the standard contract dispute, one party cancels the contract or refuses to pay due to alleged breaches by the other; in such circumstances, jurors will often find both parties failed to comply with the contract (as the jury did here) unless instructed that they must decide who committed the first material breach.”).

-3- 04-22-00756-CV

if it did materially breach the subcontracts, YC’s continued performance forfeited its right to

discharge its obligations.

Standard of Review

Both parties sued, contending the other committed the first material breach. The trial court

found in favor of YC. Thus, we must review the evidence, first, to determine whether there is any

evidence to support the trial court’s finding that Grapevine was the first to materially breach the

subcontracts and, second, whether Grapevine conclusively proved that YC was, instead, the first

to materially breach the contracts. See Graham Cent. Station, Inc. v. Pena, 442 S.W.3d 261, 263

(Tex. 2014) (when attacking adverse finding on issue on which appellant did not have burden of

proof, it must demonstrate on appeal that no evidence supports adverse finding); Dow Chem. Co.

v. Francis, 46 S.W.3d 237, 241 (Tex. 2001) (per curiam) (when challenging adverse finding on

which appellant has burden of proof, it must demonstrate on appeal evidence establishes, as matter

of law, all vital facts in support of issue).

If a party attacks the legal sufficiency of an adverse finding on an issue on which it did not

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
Long Trusts v. Griffin
222 S.W.3d 412 (Texas Supreme Court, 2006)
Dealers Electrical Supply Co. v. Scoggins Construction Co.
292 S.W.3d 650 (Texas Supreme Court, 2009)
Hernandez v. Lautensack
201 S.W.3d 771 (Court of Appeals of Texas, 2006)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
McKee v. McNeir
151 S.W.3d 268 (Court of Appeals of Texas, 2004)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104 (Texas Supreme Court, 2010)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Hanks v. GAB Business Services, Inc.
644 S.W.2d 707 (Texas Supreme Court, 1982)
Graham Central Station, Inc. v. Jesus Peña
442 S.W.3d 261 (Texas Supreme Court, 2014)
Enzo Investments, LP v. Charles White
468 S.W.3d 635 (Court of Appeals of Texas, 2015)
Douglas W. STREBEL, Appellant, v. John C. WIMBERLY II, Appellee
371 S.W.3d 267 (Court of Appeals of Texas, 2012)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Grapevine Group Concrete Contractors, Inc. (Cross-Appellee) v. YC Partners, Ltd. D/B/A Yantis Company and Yantis Corporation (Cross-Appellant), Counsel Stack Legal Research, https://law.counselstack.com/opinion/grapevine-group-concrete-contractors-inc-cross-appellee-v-yc-partners-texapp-2025.