Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.

518 S.W.3d 432, 60 Tex. Sup. Ct. J. 861, 2017 WL 1534053, 2017 Tex. LEXIS 415
CourtTexas Supreme Court
DecidedApril 28, 2017
Docket16-0054
StatusPublished
Cited by68 cases

This text of 518 S.W.3d 432 (Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 60 Tex. Sup. Ct. J. 861, 2017 WL 1534053, 2017 Tex. LEXIS 415 (Tex. 2017).

Opinion

PER CURIAM

This contract dispute involves competing breach claims by a food-product manufacturer, Bartush-Schnitzius Foods Co. (Bar-tush), and a refrigeration contractor, Cim-co Refrigeration, Inc. (Cimco). The jury found that both parties failed to comply with their agreement and assessed damages accordingly, but the trial court rendered judgment solely for Bartush. The court of appeals reversed and remanded for entry of judgment solely in Cimco’s favor. We hold that neither the trial court nor the court of appeals properly effectuated the jury’s verdict. We reverse the court of appeals’ judgment and remand the case to that court to consider unaddressed issues.

In 2010, Bartush planned to expand its line of food products to include seafood dips. Manufacturing the dips required Bar-tush’s production facilities to maintain a constant temperature no higher than thirty-eight degrees—lower than Bartush’s existing refrigeration system could sustain. Bartush therefore contracted with Cimco to install a new system. Cimco sent Bar-tush an offer letter with three quoted options. The offer letter did not reference a particular temperature range. Bartush orally selected the most expensive of the three options, confirming the selection via email. Bartush then began paying Cimco in agreed-upon installments.

After installation, Bartush started to operate the new system at a temperature setting of thirty-five degrees. However, this resulted in ice forming on the fan motors because the system’s defrost unit was not designed to support operation at such a low temperature. The ice caused the motors to overheat and fail, leading to higher temperatures that at times climbed into the 50s and 60s. When Bartush discovered the problem, it had already paid Cim-co $306,758 on the contract but still owed $113,400. Bartush communicated with Cim-co about a repair, but after several weeks without receiving what it considered a workable plan, Bartush withheld further payment and contacted an independent refrigeration engineer. The engineer recommended a warm-glycol defrost unit, and Bartush contracted with Jax Refrigeration, Inc. to install the unit at a cost of $168,079. After the warm-glycol defrost unit was installed, the system was able to maintain the target temperature of thirty-five degrees.

In response to Bartush’s nonpayment, Cimco sued Bartush to recover the balance owed on the contract. 1 Bartush counterclaimed for breach of contract, seeking damages for, among other things, the costs associated with the warm-glycol defrost unit. 2 Bartush also alleged that its failure *435 to pay was justified by Cimco’s prior material breach, Cimco asserted that the equipment it installed was exactly as described in the accepted purchase order and denied that it had made any guarantee regarding the equipment’s capacity to maintain a specific temperature.

The parties’ claims were tried to a jury. The jury answered the relevant liability portions of the charge as follows:. ‘TES” to Question 1, which asked whether Bar-tush failed to comply with the agreement; “YES” to Question 2, which asked whether Cimco failed to comply with the agreement; “CIMCO” to Question 3, which asked who failed to comply with the agreement first; and “NO” to Question 4, which asked whether Bartush’s failure to comply was excused. The jury awarded Bartush $168,079 in damages (the cost of installing the warm-glycol defrost unit), plus $215,000 in trial and conditional appellate attorney’s fees. The jury also awarded Cimco $113,400 (the balance due on the contract). The jury did not answer the question regarding Cimco’s attorney’s fees because the question was conditioned in part on a finding that Bartush breached first.

Despite the jury’s findings that both parties failed to comply and Bartush’s failure to comply was not excused, the trial court stated in its final judgment that “it appears to the Court that the verdict of the jury was for [Bartush] and against [Cimco],” and rendered judgment in Bar-tush’s favor for $168,079 in damages, plus pre- and post-judgment interest, costs, and attorney’s fees. The judgment awarded nothing- to Cimco, and Cimco appealed.

The court of appeals reversed and remanded to the trial court for entry of judgment that Bartush take nothing and that Cimco recover $113,400 in damages, plus interest and costs. 518 S.W.3d 57, 2015 WL 7567463 (Tex. App.-Fort Worth 2015). The court of appeals held that the jury’s express finding that Bartush’s failure to comply was not excused necessarily included an implied finding that Cimco’s prior breach was nonmaterial. Id. at 59. The court further held that Bartush’s failure to pay the balance due was a material breach of the contract as a matter of law, which rendered irrelevant the jury’s finding that Cimco breached first and precluded Bartush’s recovery. Id. Finally, the court of appeals held that Cimco waived its challenge to the jury’s failure to award attorney’s fees. Id. at 62 n.9.

Both parties filed petitions for review. Bartush argues the trial court’s judgment should be reinstated because Cimco’s “first” breach was material as a matter of law and thus excused Bartush’s subsequent failure to comply with the agreement. Alternatively, Bartush argues that both damages awards should be given effect, resulting in Bartush’s net recovery of $54,679 in compensatory damages. Cimco responds that the court of appeals correctly concluded that Bartush’s material breach excused Cimco’s nonmaterial breach. 3 In a cross-petition, Cimco challenges the court of appeals’ holding that Cimco waived error regarding the jury’s failure to award attorney’s fees.

*436 We first address Bartush’s argument that the trial court properly rendered judgment entirely in its favor because Bartush’s failure to comply (i.e., nonpayment) was excused as a matter of law by Cimco’s prior material breach. “It is a fundamental principle of contract law that when one party to a contract commits a material breach of that contract, the other party is discharged or excused from further performance.” Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 196 (Tex. 2004) (citing Hernandez v. Gulf Grp. Lloyds, 875 S.W.2d 691, 692 (Tex. 1994)). By contrast, when a party commits a nonmaterial breach, the other party “is not excused from future performance but may sue for the damages caused by the breach.” Levine v. Steve Scharn Custom Homes, Inc., 448 S.W.3d 637, 654 (Tex. App.-Houston [1st Dist.] 2014, pet. denied). 4 The latter principle is consistent with settled Texas law regarding the elements of a contract claim. The claim requires a finding of breach, not a finding of material breach. See, e.g., Mays v. Pierce,

Related

Slant Operating v. Octane Energy Operating
2025 Tex. Bus. 54 (Texas Business Court, 2025)
In re: Orb Energy Co.
S.D. Texas, 2025
Lavender v. Bortz
S.D. Texas, 2025
Rahim Muhammedi v. Barkat G. Ali
Court of Appeals of Texas, 2025
Johns Law Firm v. Pawlik
Fifth Circuit, 2024

Cite This Page — Counsel Stack

Bluebook (online)
518 S.W.3d 432, 60 Tex. Sup. Ct. J. 861, 2017 WL 1534053, 2017 Tex. LEXIS 415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bartush-schnitzius-foods-co-v-cimco-refrigeration-inc-tex-2017.