Arrow Field Services, LLC v. Linde Engineering North America Inc.

CourtCourt of Appeals of Texas
DecidedDecember 17, 2024
Docket01-23-00023-CV
StatusPublished

This text of Arrow Field Services, LLC v. Linde Engineering North America Inc. (Arrow Field Services, LLC v. Linde Engineering North America Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrow Field Services, LLC v. Linde Engineering North America Inc., (Tex. Ct. App. 2024).

Opinion

Opinion issued December 17, 2024

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-23-00023-CV ——————————— ARROW FIELD SERVICES, LLC, Appellant V. LINDE ENGINEERING NORTH AMERICA, INC., Appellee

On Appeal from the 133rd District Court Harris County, Texas Trial Court Case No. 2019-89936

OPINION

In this commercial construction contract dispute, appellant Arrow Field

Services, LLC (Arrow) appeals the final judgment rendered on the jury’s verdict in

favor of appellee Linde Engineering North America, Inc. (Linde) on Linde’s claims

against Arrow for breach of contract and violation of the Texas Prompt Payment Act1 (PPA or the Act) and the awards to Linde of $20,739,741 in damages,

$17,683,501 in prejudgment interest, $4,616,760 in attorney’s fees, and $130,568 in

costs. In five issues, Arrow contends that (1) the PPA does not apply in this case

because the Act’s “mineral exemption” excludes the parties’ agreement and,

independently, the PPA does not apply extraterritorially to injuries that occur outside

Texas; (2) Linde failed to present legally sufficient evidence that Arrow is liable to

Linde for Base Costs exceeding the $124 million that Arrow has already paid; (3)

even if the PPA applies to the parties’ agreement, the jury’s award of $17,683,501

in prejudgment interest to Linde should be reversed based on (a) Linde’s uncured

defaults or (b) the trial court’s acceptance of a post-trial interest calculation

unsupported by any jury finding; (4) Linde failed to present legally sufficient

evidence that it is entitled to a $729,000 Safety Incentive; and (5) because Linde’s

PPA claim fails, the final judgment should be modified by deleting the award of

attorney’s fees and costs and recalculating the prejudgment interest. For the reasons

discussed below, we affirm in part, reverse and render in part, and reverse and

remand in part the trial court’s final judgment.

1 TEX. PROP. CODE §§ 28.001-.010. 2 Background

Arrow is a midstream company located in North Dakota that gathers oil and

rich natural gas and processes the natural gas to extract natural gas liquids (NGLs).2

Linde provides construction, procurement, engineering, and project management

services to clients in the oil and gas industries.

The EPC Agreement

In April 2018, Arrow and Linde executed a Target Price Agreement for

Engineering, Procurement, and Construction (EPC Agreement) for the Bear Den II

Plant, in Watford City, North Dakota.3 Under the EPC Agreement, Arrow hired

Linde as the general contractor on the project.4

Article 7 of the EPC Agreement, entitled “Total Contract Price and Payments

to Contractor,” provides in relevant part, as follows:

7.1 Total Contract Price. As compensation in full for the full and complete performance of the Work by Contractor and all of Contractor’s other

2 Arrow is a subsidiary of Crestwood Midstream Partners LP. Crestwood was a named defendant in the underlying suit but is not a party to this appeal. 3 Arrow had an existing plant at the time, the Bear Den I plant. From 2015 to 2017, the natural gas volumes produced by producers and gathered by Arrow in the field near the Bear Den I plant increased but the Bear Den I plant lacked the capacity to meet the increased volume. In 2017, Arrow decided to build the Bear Den II plant, a new, larger natural gas processing plant in the area to accommodate the increased volume. 4 Although Arrow initially hired Linde to engineer and build a unit of the plant called the “Core-Cryo,” which cryogenically freezes natural gas so that natural gas liquids separate out, Arrow later hired Linde as the general contractor for the balance of the plant. 3 obligations under this Agreement with respect to the Work, Owner shall pay and Contractor shall accept sum of: (a) a Fixed Fee as described in Section 7.1A, adjusted in accordance with the Incentive Plan set forth in Schedule C- 3; and (b) Base Costs as described in Section 7.1B (together, the “Total Contract Price”). ....

A. Fixed Fee. Owner shall pay Contractor a fixed fee as further defined in Schedule C-1 (“Fixed Fee”), subject to adjustment in accordance with the Incentive Plan set forth in Schedule C-3. The Fixed Fee shall be payable in each Invoice, with each such payment calculated as set forth in Schedule C-1. The Fixed Fee shall not be subject to adjustment except as specified in this Agreement.

B. Base Costs. Owner shall pay Contractor those costs, charges and expenses incurred by Contractor in the performance of the Work payable as “Base Costs” as defined in Schedule C-1. Base Costs shall be net of any interest, commission, offset credits, rebates or other direct or indirect payment received by Contractor from third parties incident to the performance of the Work. Contractor shall remit to Owner any such amounts received.

Section 3.1 of Schedule C-1, “Fixed Fee,” provides, in part, as follows:

Owner shall pay Contractor $9,579,980 USD for the satisfactory completion of all Work performed by Contractor (“Fixed Fee”). The Fixed Fee shall be inclusive of all profit for the Project, all Subcontractor mark-ups, certain of Contractor’s overhead costs, and other costs and expenses of Contractor performing the Work other than the Base Cost and, if applicable, the Incentive Plan Adjustment.

As to Base Costs, Section 5.1 of Schedule C-1 states:

Contractor shall only be entitled to be paid for the Base Cost incurred in the course of carrying out the Work under this Agreement if those disbursements:

(a) have been actually, reasonably and properly incurred for the sole purpose of carrying out the Work; and

4 (b) are enumerated as Base Costs in accordance with Schedule C- 2 and as further clarified in Table C-1.

Section 5.2 provides that “Owner shall reimburse Contractor as a Base Cost

for the actual invoiced cost to Contractor and paid by Contractor to Approved

Subcontractors engaged in accordance with Sections 2.3 and 2.4 of the Agreement.”

These reimbursable Base Costs included “[f]ees and expenses of Subcontractors

performing a portion of the Work.” In addition, the parties agreed on a list of

“Disallowed Costs” which were not reimbursable, including costs resulting from any

negligence of Linde.

Schedule C-3A sets forth a “Target Base Cost” for Linde’s work of

$65,691,533. The Total Base Cost actually incurred by Linde would be compared to

the Target Base Cost to determine the “Cost Adjustment Factor,” i.e., whether the

Fixed Fee would be adjusted upward or downward, and Section 2.3 delineates how

the Fixed Fee shall be adjusted. Linde warranted that it could perform the work at

the Target Price of $75,271,513 and within the schedule of key dates. 5

Schedule C-3, Section 3.1, “Safety Incentive Program,” provides:

The Parties agree the following safety incentive program shall apply to the Project: If, upon Final Completion, Contractor and Subcontractors and Sub-subcontractors combined have (i) a Total Recordable Incident Rate of less than or equal to 1.4, (ii) a Lost Time Case Rate of less than or equal to 0.67, and (iii) zero fatalities, then the Fixed Fee shall be

5 The “Target Price” is defined as the Target Base Cost ($65,691,533) plus the Fixed Fee ($9,579,980).

5 increased by an amount equal to one percent (1%) of the Target Base Cost.

From April 2018 through August 2019, Arrow paid Linde’s monthly invoices

in full. A dispute, however, subsequently arose over payments. In August 2019,

Arrow stopped paying Linde’s invoices and Linde stopped paying its subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Ford Motor Co. v. Ledesma
242 S.W.3d 32 (Texas Supreme Court, 2007)
TXI Transportation Co. v. Hughes
306 S.W.3d 230 (Texas Supreme Court, 2010)
Wal-Mart Stores, Inc. v. Miller
102 S.W.3d 706 (Texas Supreme Court, 2003)
Fitzgerald v. Advanced Spine Fixation Systems, Inc.
996 S.W.2d 864 (Texas Supreme Court, 1999)
Lee Lewis Construction, Inc. v. Harrison
70 S.W.3d 778 (Texas Supreme Court, 2002)
EI Du Pont De Nemours & Co. v. Robinson
923 S.W.2d 549 (Texas Supreme Court, 1996)
ExxonMobil Corp. v. Valence Operating Co.
174 S.W.3d 303 (Court of Appeals of Texas, 2005)
Tips v. Hartland Developers, Inc.
961 S.W.2d 618 (Court of Appeals of Texas, 1998)
Dynegy Midstream Services, Ltd. Partnership v. Apache Corp.
294 S.W.3d 164 (Texas Supreme Court, 2009)
Uniroyal Goodrich Tire Co. v. Martinez
977 S.W.2d 328 (Texas Supreme Court, 1998)
Exxon Pipeline Co. v. Zwahr
88 S.W.3d 623 (Texas Supreme Court, 2002)
Coastal Transport Co. v. Crown Central Petroleum Corp.
136 S.W.3d 227 (Texas Supreme Court, 2004)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Citizens Bank of Bryan v. First State Bank
580 S.W.2d 344 (Texas Supreme Court, 1979)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)
Shields Ltd. Partnership v. Bradberry
526 S.W.3d 471 (Texas Supreme Court, 2017)
Honors Acad., Inc. v. Tex. Educ. Agency
555 S.W.3d 54 (Texas Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Arrow Field Services, LLC v. Linde Engineering North America Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrow-field-services-llc-v-linde-engineering-north-america-inc-texapp-2024.