Equistar Chem v. Indeck Power Equip

CourtCourt of Appeals for the Fifth Circuit
DecidedApril 23, 2025
Docket21-20345
StatusUnpublished

This text of Equistar Chem v. Indeck Power Equip (Equistar Chem v. Indeck Power Equip) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Equistar Chem v. Indeck Power Equip, (5th Cir. 2025).

Opinion

Case: 21-20345 Document: 70-1 Page: 1 Date Filed: 04/23/2025

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

FILED No. 21-20345 April 23, 2025 Lyle W. Cayce Clerk Equistar Chemicals, L.P.,

Plaintiff—Appellee/Cross-Appellant,

versus

Indeck Power Equipment Company,

Defendant—Appellant/Cross-Appellee.

Appeal from the United States District Court for the Southern District of Texas USDC 4:19-CV-3757

Before Richman and Ho, Circuit Judges.* Priscilla Richman, Circuit Judge: This dispute arises out of a contract between Equistar Chemicals, L.P. and Indeck Power Equipment Company for two industrial steam boilers. The district court concluded that Indeck breached the contract and several warranties, and it awarded Equistar $644,859 in damages. We affirm.

* Judge Gregg Costa was a member of the panel but resigned from the court after oral arguments were heard. This case is decided by a quorum under 28 U.S.C. § 46(d).  This opinion is not designated for publication. See 5th Cir. R. 47.5. Case: 21-20345 Document: 70-1 Page: 2 Date Filed: 04/23/2025

No. 21-20345

I Equistar and Indeck signed a “Master Contract” in December 2015. Indeck agreed to provide two steam boilers, related equipment, and installation and start-up services at Equistar’s plant in Tuscola, Illinois. Several setbacks delayed the boilers’ installation and start-up. It took more than an extra month for Equistar to receive the boilers because Indeck did not release customs paperwork for the boilers’ shipment across the Canadian border. Equistar paid an additional month of railcar rental charges during the wait. Once the boilers arrived, the parties had planned on thirty- six days of work for Indeck’s service technicians to complete the installation. But it ended up taking 186 days to fix multiple defects. Relevant here, several of the boilers’ components were defectively manufactured. This led Indeck’s service technicians to spend substantial time addressing problems that should not have arisen or should have been remedied before Indeck delivered the equipment to Equistar. Indeck also had to redo the work of one of its technicians, further extending the setup process. Equistar sued Indeck in the Southern District of Texas. It asserted claims for breach of contract and warranty and sought reimbursement for the costs it incurred to remedy the boilers’ defects. After a bench trial, the district court issued a decision applying Texas law that concluded Indeck breached its warranties for several boiler components. The district court also concluded that Indeck breached the Master Contract due to the excessive rework performed by its technicians as well as the one-month shipping delay. The district court awarded $644,859 in damages to Equistar. Of that total, $600,859 was for the labor-related issues, and $44,000 was for the shipping delay. Indeck filed a Rule 59 motion for a new trial, which the court denied. This appeal followed.

2 Case: 21-20345 Document: 70-1 Page: 3 Date Filed: 04/23/2025

II Indeck raises four challenges. “When reviewing a bench trial, we test the district court’s findings of fact for clear error and its legal conclusions de novo.”1 The parties agree that Texas law governs this dispute.2 A We begin with Indeck’s argument that the Master Contract incorporated a support-labor clause from the Domestic Field Service Rate Sheet (the Rate Sheet). Indeck asserts that this clause prevents Equistar’s recovery of all labor-related damages. The clause specifies that “[a]ll labor including, but not limited to, standby labor, initial check-out, start-up, and testing required to assist the Field Service Consultant at any time, shall be supplied by [Equistar] at no cost to Indeck.” The district court determined that Indeck’s Rate Sheet did not modify the Master Contract, so it was not binding. Indeck argues that the court erred because the Rate Sheet was part of the Master Contract from the beginning, not a subsequent modification. It contends that the clause bars Equistar’s recovery of its labor-related damages. We need not determine whether the Master Contract incorporated the Rate Sheet because, even if it did, the support-labor clause does not bar Equistar’s recovery. The labor-related damages at issue are the extra work that Indeck’s technicians performed due to Indeck’s warranty and contract breaches, not the original work to install and start-up the boilers. Under Texas law, parties may contractually limit the damages that are recoverable.3

1 Conn Credit I, L.P. v. TF LoanCo III, L.L.C., 903 F.3d 493, 499 (5th Cir. 2018). 2 See id. (applying Texas law in similar circumstances because “[t]he parties d[id] not dispute the district court’s conclusion that Texas law govern[ed] this case”). 3 Glob. Octanes Tex., L.P. v. BP Expl. & Oil Inc., 154 F.3d 518, 523 (5th Cir. 1998).

3 Case: 21-20345 Document: 70-1 Page: 4 Date Filed: 04/23/2025

That did not happen in the support-labor clause. The clause simply addresses who must supply the labor to assist Indeck with the boilers’ setup, not who is responsible for damages in the event of a breach. B Indeck argues that Article 8(b) of the Master Contract required Equistar to dispute Indeck’s invoices in writing before Equistar sued for breach. Article 8(b) provides: In the event [Equistar] disputes any invoice amount, [Equistar] may . . . without waiver of any of its rights, including the right to seek reimbursement, pay the disputed amount and later seek reimbursement. In the event of a dispute, the Parties will promptly attempt to resolve the dispute . . . . Additionally, Article 24 requires that “all notices . . . shall be in writing.” Indeck contends that the notice requirement was a condition precedent to Equistar suing for breach and that because Equistar did not dispute any invoices in writing, its damages claims are barred. Under Texas law, “[a] condition precedent is ‘an event that must happen or be performed before a right can accrue to enforce an obligation.’”4 “[T]he conditional language must connect the condition precedent to the conditioned obligation.”5 “In order to make performance specifically conditional, a term such as ‘if’, ‘provided that’, ‘on condition that’, or some similar phrase of conditional language must normally be included.”6 “If no

4 Conn Credit I, 903 F.3d at 500 (quoting Associated Indem. Corp. v. CAT Contracting, Inc., 964 S.W.2d 276, 283 (Tex. 1998)). 5 Arbor Windsor Ct., Ltd. v. Weekley Homes, LP, 463 S.W.3d 131, 137 (Tex. App.— Houston [14th Dist.] 2015, pet. denied). 6 Conn Credit I, 903 F.3d at 500 (quoting Solar Applications Eng’g, Inc. v. T.A. Operating Corp., 327 S.W.3d 104, 109 (Tex. 2010)).

4 Case: 21-20345 Document: 70-1 Page: 5 Date Filed: 04/23/2025

such language is used, the terms will be construed as a covenant in order to prevent a forfeiture.”7 We agree with the district court that Article 8(b) does not contain a condition precedent. Assuming without deciding that Article 8(b) has a notice requirement that Equistar did not fulfill, there is no conditional language connecting that notice requirement to Equistar’s ability to seek a contractual remedy. Article 8(b) does not use the words “if,” “provided that,” “on the condition that,” “prior to,” or any other similar phrase to create a condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Criswell v. European Crossroads Shopping Center, Ltd.
792 S.W.2d 945 (Texas Supreme Court, 1990)
Solar Applications Engineering, Inc. v. T.A. Operating Corp.
327 S.W.3d 104 (Texas Supreme Court, 2010)
Associated Indemnity Corp. v. CAT Contracting, Inc.
964 S.W.2d 276 (Texas Supreme Court, 1998)
Arbor Windsor Court, Ltd. v. Weekley Homes, LP
463 S.W.3d 131 (Court of Appeals of Texas, 2015)
Cajun Constructors, Inc. v. Velasco Drainage District
380 S.W.3d 819 (Court of Appeals of Texas, 2012)
Conn Credit I, L.P. v. TF Loanco III, L.L.C.
903 F.3d 493 (Fifth Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Equistar Chem v. Indeck Power Equip, Counsel Stack Legal Research, https://law.counselstack.com/opinion/equistar-chem-v-indeck-power-equip-ca5-2025.