Citadel Construction Company v. Smith

483 S.W.2d 283, 1972 Tex. App. LEXIS 2143
CourtCourt of Appeals of Texas
DecidedJune 21, 1972
Docket11919
StatusPublished
Cited by12 cases

This text of 483 S.W.2d 283 (Citadel Construction Company v. Smith) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citadel Construction Company v. Smith, 483 S.W.2d 283, 1972 Tex. App. LEXIS 2143 (Tex. Ct. App. 1972).

Opinion

O’QUINN, Justice.

This lawsuit is between the general contractor and a subcontractor on a public project for the construction of a building in 1968 and 1969 at Southwest Texas State University in San Marcos, Texas. Other parties are the surety companies for the respective principal parties.

Citadel Construction Company, Inc., prime contractor on the project, brought this suit against Chester Smith, who was the subcontractor of all lath and plaster work on the building, alleging breach of contract. Citadel sought to recover $163,526.75 for reasonable cost of completing Smith’s contract, plus consequential damages in the sum of $23,874.01. After allowance of credit due Smith in the amount of $95,808.65, Citadel sought a net recovery of $91,592.11.

Chester Smith filed his counterclaim against Citadel in the sum of $66,703.96 for work and materials, $18,005.33 in re-tainage held by Citadel, and $2,298.55 as profit Smith alleged he would have earned if he had been permitted to complete the proj ect.

American General Insurance Company, as surety for Citadel, and United States *285 Fidelity and Guaranty Company, as surety for Smith, were made parties to the suit.

On trial Citadel took the position that Smith’s performance of his subcontract had been so slow that Citadel was forced to ask Smith to leave the job in February of 1969 and to complete the lath and plaster work at Citadel’s expense. Smith’s position was that his performance was at a proper rate and that if the rate of his performance was not satisfactory, this was due to Citadel’s lack of coordination and supervision of the job.

All issues submitted to the jury were answered favorably to Smith. Upon the jury’s findings, the trial court entered judgment against Citadel and American General, jointly and severally, in the sum of $60,312.50 plus interest.

Citadel and American General have appealed and bring four points of error.

Under the first two points appellants urge error in permitting appellees to introduce twelve exhibits that reflect claims Citadel initially made against Smith and against a tile subcontractor on the same job. The two claims were duplicated in part, and by the éxhibits appellees were able to show inconsistencies between the first claim against Smith and the claim upon which Citadel finally relied in the trial.

Exhibit 16 constitutes the details of the claim Citadel made against the tile subcontractor. Exhibits 17 through 27 are parts of a file maintained by Citadel containing material upon which Citadel based its claim against Smith. It is undisputed that the two claims contained charges for identical material and labor, and that the duplicated charges were not properly included in the claim against Smith. The duplications were in excess of $58,800.

Appellants’ position is that because ap-pellees were unable to show any inconsistency between Exhibit 16 and any claim urged by Citadel against Smith at the trial, or any evidence Citadel introduced in support of its claim against Smith, it was error to admit Exhibit 16 for impeachment purposes. Citadel’s principal witness as to the claim against Smith was B. F. Davidson, president of the company. Davidson’s testimony was given in support only of the claim ultimately stated in Citadel’s amended petition, and that claim did not include the duplications discovered before trial in the Smith claim and the claim against the tile subcontractor.

The position of appellees is that Exhibit 16 and Exhibits 17 through 27 were admissible to show a prior inconsistent statement of Davidson. The record shows that the materials found in all the exhibits were prepared and compiled for Citadel by a former employee, and that the materials in Exhibits 17 through 27 were delivered by Davidson to an accountant for Smith as the claim of Citadel against Smith. The accountant later obtained access to the materials found in Exhibit 16 which led to discovery of the extensive duplications amounting to more than $58,800.

Appellants contend that because Exhibits 17 through 27 are not “coextensive with Citadel’s claim in the instant suit,” the exhibits were admissible on the part of appel-lees only if inconsistent with Citadel’s claim under evidence Citadel introduced in the trial. Appellants admit the existence of duplications of many items from the initial claim against the tile subcontractor, as shown by Exhibit 16, in the initial claim against Smith, as reflected by Exhibits 17 through 27. But appellants argue: “To allow Exhibit 16, into evidence because it is inconsistent with Exhibit 17-27 is to allow Smith to pile an inconsistency on top of an inconsistency.”

Smith’s accountant was permitted to testify from the exhibits and to point out items in the Smith claim that were also found in the claim against the tile contractor.

Appellants objected to introduction of Exhibit 16, stating to the trial court, “ . . . the theory of admission of *286 . Exhibit No. 16 is that it is inconsistent with . . . Exhibit Nos. 17 through 27 . [and] the theory of admissibility propounded on Exhibits 17 through 27 is that it is inconsistent with what’s alrpady [already] in evidence We would . . . point out . that this is piling an inconsistency on an inconsistency and therefor is not relative or relevant to a prior inconsistent statement which has been made in this case from the witness stand or from any exhibit which has been admitted into evidence, and would object to the admission of . Exhibit No. 16 on this ground.”

Smith’s accountant testified that he had not examined the exhibits introduced by Citadel at the trial, and, being a witness placed under the rule (Rule 267, Texas Rules of Civil Procedure), was unable to say whether the claim represented by Exhibits 17 through 27 was the same claim Davidson had already testified to at the trial.

Appellants made objection, stating to the court, “ . . . we’re going to object to both Defendant’s Exhibit Nos. 16 and the group Exhibit 17 through 27 as wholly irrelevant to the matter at issue before this Court, and object to further testimony on the part of the witness for purposes stated he testified about . . . [and] point out . . . that Plaintiff’s Exhibit Nos. 1 through 110 have been offered, and marked, and in evidence in this case since . last week, with ample opportunity for this witness knowing that he was going to testify to have made an examination to see whether or not there was any relevancy to what he had to testify to as to what’s been admitted in evidence . . . ”

Appellees did not question Davidson while he was a witness at the trial about the materials Davidson had furnished Smith’s accountant prior to trial. These materials, as Exhibit 16 and Exhibits 17 through 27, were offered for the first time through the accountant as a witness.

It is settled that a proper predicate generally must be laid before a witness can be impeached by introduction of prior inconsistent statements. International & G. N. R. Co. v. Boykin, 99 Tex. 259, 89 S.W. 639, 640 (1905); Thompson v. Denham, 250 S.W.2d 460 (Tex.Civ.App. Galveston 1952, writ ref. n.r.e.); Carrick v. Hedrick, 351 S.W.2d 659 (Tex.Civ.App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramex Construction Co. v. Tamcon Services Inc.
29 S.W.3d 135 (Court of Appeals of Texas, 2000)
James Eric Mansfield v. David Dormire
202 F.3d 1018 (Eighth Circuit, 2000)
City of Corpus Christi v. Acme Mechanical Contractors, Inc.
736 S.W.2d 890 (Court of Appeals of Texas, 1987)
Corpus Christi v. Acme Mechanical Cont.
736 S.W.2d 894 (Court of Appeals of Texas, 1987)
Sims v. William S. Baker, Inc.
568 S.W.2d 725 (Court of Appeals of Texas, 1978)
Trucker's, Inc. v. South Texas Construction Co.
561 S.W.2d 855 (Court of Appeals of Texas, 1977)
City of Ingleside v. Stewart
554 S.W.2d 939 (Court of Appeals of Texas, 1977)
Bristol-Myers Co. v. Gonzales
548 S.W.2d 416 (Court of Appeals of Texas, 1976)
Mayfield v. Employers Reinsurance Corp.
539 S.W.2d 398 (Court of Appeals of Texas, 1976)
Lesikar Construction Company v. Acoustex, Inc.
509 S.W.2d 877 (Court of Appeals of Texas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
483 S.W.2d 283, 1972 Tex. App. LEXIS 2143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citadel-construction-company-v-smith-texapp-1972.