Blue Ribbon Staffing, LLC v. Flatiron Constructors, Inc.

CourtDistrict Court, W.D. Texas
DecidedJanuary 26, 2021
Docket5:20-cv-00686
StatusUnknown

This text of Blue Ribbon Staffing, LLC v. Flatiron Constructors, Inc. (Blue Ribbon Staffing, LLC v. Flatiron Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Ribbon Staffing, LLC v. Flatiron Constructors, Inc., (W.D. Tex. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF TEXAS SAN ANTONIO DIVISION

BLUE RIBBON STAFFING LLC, § § Plaintiff, § 5-20-CV-00686-RBF § vs. § § FLATIRON CONSTRUCTORS, INC. ET § AL. § § Defendants. § §

ORDER

Before the Court is Defendants’ Motion to Dismiss. See Dkt. No. 19. The Court has diversity jurisdiction over this action to recover on a public-works bond under Texas’s McGregor Act. See 28 U.S.C. § 1332. Authority to enter this Order stems from 28 U.S.C. § 636(c), as all parties have consented to U.S. Magistrate Judge jurisdiction. See Dkt. Nos. 8-9, 12. As discussed further below, Defendants’ Motion, Dkt. No. 19, is GRANTED. McGregor Act claims such as those lodged here must be properly perfected as a condition precedent to any recovery. Because Plaintiff Blue Ribbon Staffing LLC failed to properly perfect its claims as a matter of law, the claims to recover on the payment bond for work performed in July through October of 2019 are DISMISSED. Factual and Procedural Background Defendant Flatiron Constructors, Inc. served as a general or prime contractor (also called the primary contractor) on a public-works construction project to improve Loop 1604 in Bexar County, Texas. See Amend. Compl. (Dkt. No. 18) at 2. In accordance with Texas’s McGregor Act, Tex. Gov’t Code § 2253, Flatiron posted a payment bond for the project, listing the additional Defendants as bond sureties. See id. at 3. Flatiron is therefore the bond principal as well as the prime contractor. Flatiron subcontracted a portion of the project’s concrete work to non-party 2J Resources LLC. See id. 2J Resources, in turn, contracted with Plaintiff Blue Ribbon to provide labor from July through October 2019. See id.; Ex. 2. 2J Resources, however, allegedly never paid Blue Ribbon for the labor Blue Ribbon provided. See id. at 3. This case involves Blue Ribbon’s

efforts to recover on the payment bond from the bond sureties and principal. On April 23, 2020, Blue Ribbon sued Defendants in Bexar County state court. See Dkt. No. 1-1 at 3-7. Blue Ribbon seeks $123,704.90, plus interest, and attorneys’ fees pursuant to Chapter 38 of the Texas Civil Practice & Remedies Code. See Amend. Compl. (Dkt. No. 18). Blue Ribbon claims in its live complaint that it provided certain statutorily required “notices to Flatiron Constructors, Inc. and to the lead surety as contained in the attached Exhibit 2, which contains all of the unpaid invoices, and has complied with the statute for notice to the general or prime contractor and its sureties.” Id. at 3. Defendants timely removed the case based on diversity jurisdiction. See Dkt. No. 1.1

Defendants now move to dismiss Blue Ribbon’s claims for failure to satisfy the McGregor Act’s notice requirements. See Dkt. No. 19. Additionally, Defendants argue Blue Ribbon isn’t entitled to attorney fees under Chapter 38 of the Texas Civil Practice & Remedies Code. See id. Before taking up Defendants’ Motion to Dismiss, the Court provided Blue Ribbon an opportunity to amend its live pleadings to conform to federal pleading standards and respond to Defendants’ arguments for dismissal based on the asserted inadequacy of notice provided by Blue Ribbon in connection with its claims. See Dkt. Nos. 17 & 18.

1 Defendants subsequently amended their notice of removal to adequately allege the parties’ citizenship. See Dkt. No. 5. Analysis As evident on the face of Blue Ribbon’s live pleadings and the uncontested matters submitted by Blue Ribbon attached to its Amended Complaint, Blue Ribbon failed as a matter of law to timely provide the statutorily required notice of its claims for work performed in July, August, and September 2019. That notice is a condition precedent to the perfection of a cause of

action under the McGregor Act. Accordingly, those unperfected claims must be dismissed. The claim involving October 2019 work raises the novel issue of whether email notice under the McGregor Act could satisfy the Act’s notice requirements. After a careful review of the McGregor Act’s text, Fifth Circuit precedent, and relevant Texas Supreme Court decisions, the Court’s Erie guess is that the Texas Supreme Court would conclude that the email notice provided by Blue Ribbon doesn’t comply with the McGregor Act under a plain-text reading of its provisions. Blue Ribbon’s claims for October 2019 work must therefore also be dismissed. The attorney’s fees issue need not be addressed, as the McGregor Act provided the only basis for relief asserted by Blue Ribbon.

A. The McGregor Act and Its Notice Requirements. The parties agree that Texas’s McGregor Act governs this action and provides the sole cause of action through which Blue Ribbon seeks relief. Under the Act, as it pertains to this case, “[a] governmental entity that enters into a public works contract with a general contractor must . . . require the [prime] contractor to execute performance and payment bonds before work begins.” Capitol Indem. Corp. v. Kirby Rest. Equip. & Chem. Supply Co., 170 S.W.3d 144, 147 (Tex. App.—San Antonio 2005, pet. denied) (citing Tex. Gov’t Code § 2253.021). The parties further agree that Flatiron executed a payment bond and that the other Defendants are sureties on the bond. The McGregor Act, in addition to requiring a bond in circumstances such as these, also provides a cause of action for a “payment bond beneficiary who has provided public work . . . under a public work contract” to “sue the principal or surety, jointly or severally, on the payment

bond if the claim is not paid before the 61st day after the date the notice for the claim is mailed.” Tex. Gov’t Code § 2253.073. But under the Act, as Blue Ribbon concedes, “[a] payment bond claimant’s claim can fail if the claimant fails to provide timely or adequate notice” of the claim and, as a result, does not properly perfect the claim. Resp. at ¶ 9; see Capitol Indem.,170 S.W.3d at 147 (citing Tex. Gov’t Code § 2253.073 and noting, “[i]n order to bring suit against the surety on a payment bond, [however,] the beneficiary must first properly perfect the claim”). Indeed, providing the required notice is a condition precedent to perfecting a claim under the Act. See In re Contractor Tech., Ltd., 529 F.3d 313, 318-20 (5th Cir. 2008). In this regard, “[t]he statute is intended to provide a simple and direct method of giving notice and perfecting such claims.”

Capitol Indem., 170 S.W.3d at 147. The details of the timing and substance of the required notice vary depending on the relationship between the bond beneficiary and the prime contractor. 1. Notice from a beneficiary in direct privity with the prime contractor. For a payment-bond beneficiary who directly contracted with the prime contractor, the beneficiary “must mail to the prime contractor and surety written notice of the claim” within a three-month deadline, as provided below: NOTICE REQUIRED FOR CLAIM FOR PAYMENT FOR LABOR OR MATERIAL.

(a) To recover in a suit under Section 2253.073 on a payment bond for a claim for payment for public work labor performed or public work material delivered, a payment bond beneficiary must mail to the prime contractor and the surety written notice of the claim.

(b) The notice must be mailed on or before the 15th day of the third month after each month in which any of the claimed labor was performed or any of the claimed material was delivered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krieser Ex Rel. Krieser v. Hobbs
166 F.3d 736 (Fifth Circuit, 1999)
Howe v. Scottsdale Insurance Co.
204 F.3d 624 (Fifth Circuit, 2000)
Barfield v. Madison County, MS
212 F.3d 269 (Fifth Circuit, 2000)
Tanuja-Sahai v. Gonzales
488 F.3d 632 (Fifth Circuit, 2007)
Lone Star Fund v (U.S.), L.P. v. Barclays Bank PLC
594 F.3d 383 (Fifth Circuit, 2010)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Redland Insurance Co. v. Southwest Stainless, L.P.
181 S.W.3d 509 (Court of Appeals of Texas, 2005)
Suretec Insurance Co. v. Myrex Industries
232 S.W.3d 811 (Court of Appeals of Texas, 2007)
Featherlite Building Products Corp. v. Constructors Unlimited, Inc.
714 S.W.2d 68 (Court of Appeals of Texas, 1986)
United Fire & Casualty Co. v. Boring & Tunneling Co. of America
321 S.W.3d 24 (Court of Appeals of Texas, 2010)
Prairie View A&M University v. Diljit K. Chatha
381 S.W.3d 500 (Texas Supreme Court, 2012)
Employers' Liability Assur. Corp. v. Young County Lumber Co.
64 S.W.2d 339 (Texas Commission of Appeals, 1933)
City of Marshall v. City of Uncertain
206 S.W.3d 97 (Texas Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Blue Ribbon Staffing, LLC v. Flatiron Constructors, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-ribbon-staffing-llc-v-flatiron-constructors-inc-txwd-2021.