McCoy v. Nelson Utilities Services, Inc.

736 S.W.2d 160, 1987 Tex. App. LEXIS 8250
CourtCourt of Appeals of Texas
DecidedJuly 31, 1987
Docket12-86-0041-CV
StatusPublished
Cited by21 cases

This text of 736 S.W.2d 160 (McCoy v. Nelson Utilities Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCoy v. Nelson Utilities Services, Inc., 736 S.W.2d 160, 1987 Tex. App. LEXIS 8250 (Tex. Ct. App. 1987).

Opinion

*162 ON MOTION FOR REHEARING

SUMMERS, Chief Justice.

Our opinion dated June 30, 1987, is withdrawn, and the following is substituted.

This case involves the question of damages arising out of the breach of a construction contract and the superior right to retainage. We reform the judgment and as reformed, affirm.

On December 22, 1982, appellant R.J. Kelley (Kelley), the owner of the Meadow Acres Subdivision Number 2 in Henderson, Texas (Meadow Acres), filed suit against McCoy Construction Company, Inc. (McCoy Construction) seeking damages for breach of contract. On January 21, 1983, McCoy Construction filed a counterclaim seeking to recover the funds retained by Kelley under the contract, to fix a lien against Meadow Acres, and to recover reasonable attorney’s fees. On September 21, 1984, the appellee, Nelson Utilities Services, Inc. (Nelson Utilities), one of McCoy Construction’s suppliers, filed a petition in intervention seeking to recover from Kelley and McCoy Construction the unpaid balance due on McCoy Construction’s sworn account. On April 5, 1985, Nelson Utilities amended its petition in intervention to add appellants George McCoy and Johnny McCoy as defendants. On December 27, 1985, after a trial to the bench, the court rendered judgment that Kelley recover from McCoy Construction $37,437.93 as damages with six percent prejudgment interest; that Nelson Utilities recover from McCoy Construction, George McCoy, and Johnny McCoy, jointly and severally, $42,-409.93 as damages, six percent prejudgment interest, and $3,000.00 as attorney’s fees; and that Nelson Utilities recover from Kelley $12,818.22 as damages with six percent prejudgment interest. George McCoy and Johnny McCoy appeal that portion of the judgment awarding Nelson Utilities damages from them, but McCoy Construction does not appeal. Kelley appeals only the portion of the judgment awarding Nelson Utilities damages from him.

On July 22,1981, Kelley and McCoy Construction entered into an agreement whereby McCoy Construction would build the sewer system, the water system, and the streets of Meadow Acres for $261,865.32. The contract provided that McCoy Construction was to substantially complete the job within 120 working days following notice to commence work; that McCoy Construction was to provide, by the tenth of each month, written estimates to the supervising engineer, Ralph Stokes (Stokes), of the total value of work performed the preceding month; that after Stokes approved those estimates, Kelley was, by the fifteenth of the month, to pay McCoy Construction the amount of the approved statement less a ten percent retainage; that Stokes, within ten days following receipt of written notice of completion from McCoy Construction, was to inspect the work and, if substantially complete, issue to Kelley a certificate of completion; and that between thirty and thirty-five days following the issuance of the certificate of completion, Kelley was to pay McCoy Construction the balance due under the contract, including the contractual retainage. The contract was subsequently modified, reducing the contract price to $259,330.02. Construction began in August of 1981 and continued until March of 1982.

In March of 1982, a dispute over the partial payment due McCoy Construction for the work performed in February of 1982 arose. On March 1,1982, McCoy submitted an estimate, less ten percent retain-age, of $9,594.00, and this estimate was approved by Stokes on March 9,1982. In a letter dated March 18, 1982, McCoy Construction notified Kelley that it had not received payment for the March 1 estimate and that McCoy Construction would consider the project abandoned if payment was not received within ten days. In three letters dated March 19, 1982, McCoy Construction authorized Kelley to pay directly Earl Boothe, one of McCoy Construction’s subcontractors, out of the proceeds of the March 1 estimate. In a letter also dated March 19,1982, Kelley notified McCoy Construction that McCoy Construction had apparently abandoned the Meadow Acres project, and that if work did not resume by March 24, 1982, Kelley would conclusively *163 presume that McCoy Construction had breached the contract. Kelley also issued a cheek, dated March 12, 1982, to McCoy Construction and Earl Boothe for $9,594.00, the amount due on the March 1 estimate, but this check was not presented for payment until March 30, 1982. Finally, in a letter dated March 29, 1982, McCoy Construction notified Kelley that the project had been abandoned as the result of Kelley’s failure to timely pay the March 1 estimate and demanded payment within thirty days of $24,137.04, representing, according to McCoy Construction, the balance due under the contract.

As of March 29, 1982, Kelley had paid McCoy Construction $115,365.98 in partial payments and held $12,818.44 as contractual retainage. At that time, McCoy Construction was obligated to finish the project for $131,145.60. Moreover, McCoy Construction owed Nelson Utilities $42,409.93 for supplies used in the construction of the Meadow Acres project, ordered and delivered between August 24,1981, and October 10, 1981. On April 16, 1982, Kelley contracted with Reynolds-Land, Inc. to complete the work specified in the original con-' tract for $136,007.00 plus a reasonable force account with which to remedy prior construction deficiencies. Ultimately, Kelley paid Reynolds-Land, Inc. $165,922.26 to complete the Meadow Acres project.

Kelley brings three points of error, and McCoy Construction brings three points of error. In his first point, Kelley asserts that “the Trial Court erred in granting judgment in favor of Nelson Utilities Services, Inc., and against R.J. Kelley in that there was no evidence that Kelley was liable to Nelson under any conceivable theory of law.” Specifically, Kelley complains that there was “no evidence that Nelson perfected any statutory lien for material-men” and that there was “no evidence of any contractual relationship between Kelley and Nelson, therefore Nelson is not a subcontractor of Kelley.” In his third point of error, Kelley complains that “the Trial Court erred in granting judgment for Nelson Utilities Service, Inc., and against R.J. Kelley in that any finding of liability of Kelley would be against the great weight and preponderance of the evidence. We shall discuss these points together.

In this case, the trial court did not file written findings of fact and conclusions of law. 1 Therefore, the judgment of the trial court implies all necessary fact findings in support of the judgment. In the Interest of W.E.R., 669 S.W.2d 716, 717 (Tex.1984); Carter v. William Somerville and Sons, Inc., 584 S.W.2d 274, 276 (Tex. 1979); Goodyear Tire & Rubber Co. v. Jefferson Construction Co., 565 S.W.2d 916, 918 (Tex.1978); Buchanan v. Byrd, 519 S.W.2d 841, 842 (Tex.1975); Renfro Drug Co. v. Lewis, 149 Tex. 507, 235 S.W.2d 609, 613 (1951).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

White v. Salcedo
E.D. Texas, 2025
James Kevin Brown
E.D. Texas, 2022
Mark Young v. Bella Palma, LLC
Court of Appeals of Texas, 2022
Vrana v. Thornhill, Jr.
E.D. Texas, 2019
in Re Richard Scheller
Court of Appeals of Texas, 2009
Scoggins Construction Co. v. Dealers Electrical Supply Co.
292 S.W.3d 685 (Court of Appeals of Texas, 2008)
In Re Huber Contracting, Ltd.
347 B.R. 205 (W.D. Texas, 2006)
C & G, INC. v. Jones
165 S.W.3d 450 (Court of Appeals of Texas, 2005)
Exchanger Contractors Inc. v. Comerica Bank-Texas
330 F.3d 339 (Fifth Circuit, 2003)
Airtron, Inc. v. Faulkner (In Re Faulkner)
213 B.R. 660 (W.D. Texas, 1997)
Lively v. Carpet Services, Inc.
904 S.W.2d 868 (Court of Appeals of Texas, 1995)
Don Hill Construction Co. v. Dealers Electrical Supply Co.
790 S.W.2d 805 (Court of Appeals of Texas, 1990)
Quarles v. Champion International Corp.
760 S.W.2d 792 (Court of Appeals of Texas, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
736 S.W.2d 160, 1987 Tex. App. LEXIS 8250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccoy-v-nelson-utilities-services-inc-texapp-1987.