Vacuum Systems, Inc. v. Washburn

651 A.2d 377, 1994 Me. LEXIS 313
CourtSupreme Judicial Court of Maine
DecidedDecember 21, 1994
StatusPublished
Cited by4 cases

This text of 651 A.2d 377 (Vacuum Systems, Inc. v. Washburn) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vacuum Systems, Inc. v. Washburn, 651 A.2d 377, 1994 Me. LEXIS 313 (Me. 1994).

Opinion

GLASSMAN, Justice.

Vacuum Systems, Inc. appeals from a summary judgment entered in the Superior *378 Court (Somerset County, Chandler, J.) in favor of Robert W. Washburn on its complaint seeking damages for Washburn’s alleged professional negligence. We agree with Vacuum’s contention that the trial court erred by its determination that as a matter of law the notice pursuant to 14 M.R.S.A. § 871 (1980 & Supp.1994) 1 did not meet the requirements of that statute. Accordingly, we vacate the judgment.

The record reveals the following: Bridge Construction Corporation was the general contractor of a Maine Department of Transportation construction project in West Bux-ton and executed a contract payment bond with Aetna Casualty and Surety Company pursuant to the Public Works Contractors’ Surety Bond Law of 1971,14 M.R.S.A. § 871. H & L Concrete was a subcontractor for Bridge, and Vacuum was a subcontractor for H & L. Vacuum had no direct contractual relationship with Bridge.

Vacuum provided labor and materials to the project through July 31, 1989, for which it billed H & L. When H & L failed to pay, Vacuum wrote to Bridge. By its letter dated October 24, 1989, Vacuum advised Bridge that it had received no payment from H & L, that it had received no notification from H & L that its bill was disputed and that the letter was to serve as notification to Bridge that there could be pending litigation. This was followed by a letter dated October 25, 1989, advising Bridge, inter alia, that its bill to H & L was in the amount of $55,192.13. The parties stipulated that both letters were sent by first class mail and received by Bridge within 90 days from July 31, 1989.

Vacuum first contacted Washburn by telephone on October 25, 1989 and advised him concerning the nonpayment by H & L and that “we are nearing the 90-day period for notification.” The earliest Washburn could see Vacuum was October 30. On October 30, Washburn was furnished with the information on which Vacuum based its claim against Bridge on the surety bond. Based on his determination that Vacuum’s notice to Bridge precluded it from suing Bridge pursuant to 14 M.R.S.A. § 871, Washburn failed to file an action against Bridge on behalf of Vacuum. The subsequent action filed by Vacuum against Bridge, after Vacuum had retained other counsel, was barred by the one-year statute of limitations provided in 14 M.R.S.A. § 871. See Vacuum Sys., Inc. v. Bridge Constr. Co., 632 A.2d 442 (Me.1993).

In March 1993, Vacuum filed the instant complaint against Washburn. Vacuum alleged that by failing to bring a timely action against Bridge, Washburn caused Vacuum to lose its right to recover against Bridge. Asserting that at the time he was consulted by Vacuum its action against Bridge was barred because the notice did not comply with the requirements of section 871(4), Washburn moved for a summary judgment. After a hearing on the motion, the court determined as a matter of law that “the notice provisions of 14 M.R.S.A. § 871(4) must be strictly adhered to in order to accomplish the notice required,” and accordingly, at the time Vacuum hired Washburn its rights had already been foreclosed. From the summary judgment entered in favor of Washburn, Vacuum appeals.

Vacuum contends that notice served by first class mail that is actually received dur *379 ing the 90-day notice period is sufficient to meet the notice requirements of 14 M.R.S.A. § 871. It also contends that the contents of the two letters it sent Bridge are sufficient to meet the requirements of the statute. We agree with both contentions.

When, as here, there exist no genuine issues of material fact, we view the grant of a motion for a summary judgment to determine whether the trial court erred by concluding that Washburn is entitled to a judgment as a matter of law. See Fisherman’s Wharf Assocs. II v. Verrill & Dana, 645 A.2d 1133, 1135 (Me.1994).

The Public Works Contractors’ Surety Bond Law of 1971, 14 M.R.S.A. § 871 (1980 & Supp.1994) requires that any person who is awarded a contract by the State that exceeds $100,000 furnish a payment bond in the amount of the contract to protect suppliers of labor and materials to the contractor or subcontractor. The statute further allows subcontractors not in privity of contract with the general contractor to have a cause of action against the general contractor on such payment bond if certain notice requirements are satisfied. The notice must be given to the general contractor within 90 days of the last day on which the subcontractor furnished labor or materials and the statute provides that “[s]uch notice shall be served by registered or certified mail.” 14 M.R.S.A. § 871(4). The statute serves as a replacement for a materialman’s right to obtain a mechanic’s hen because one cannot secure a mechanic’s lien on state property.

Maine’s statute is modeled after the federal Miller Act, 40 U.S.C.S. §§ 270a-270d. See L.D. 375, Statement of Fact (105th Leg-is.1971) (“The proposed legislation is intended to provide limitation of action on state work similar to that which is provided on federal contracts which are covered by the so-called Miller Act.”). The Miller Act has similar, but not identical, language to the Maine statute relating to the method of service of notice. 2 When, as in this ease, we are dealing with issues of first impression, the use of federal precedent is appropriate as an aid in interpreting Maine’s statute. See, e.g., Bowen v. Dep’t of Human Serv., 606 A.2d 1051, 1053 (Me.1992). We find persuasive the reasoning of the United States Supreme Court in Fleisher Eng’g & Constr. Co. v. Hallenbeck, 311 U.S. 15, 61 S.Ct. 81, 85 L.Ed. 12 (1940). In that case the United States Supreme Court determined that actual notice served by a subcontractor by first class mail was sufficient to meet the notice requirement of the Miller Act. The Court drew a distinction between the provision in the Act stating that notice must be served within 90 days following the last date that labor or materials were furnished by a subcontractor as a condition precedent to the right to sue, and the provision relating to the method of serving notice, and stated,

We think the purpose of this provision as to the manner of service was to assure receipt of the notice, not to make the described method mandatory so as to deny the right of suit when the required written notice within the specified time had actually been given and received.

Id. at 19, 61 S.Ct. at 83.

This construction has been followed consistently by the federal courts. See, e.g., Consolidated Elec. Distrib., Inc. v. Altech, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fredette v. Secretary of State
1997 ME 105 (Supreme Judicial Court of Maine, 1997)
Thibeault v. Larson
666 A.2d 112 (Supreme Judicial Court of Maine, 1995)
State v. Watson
657 A.2d 776 (Supreme Judicial Court of Maine, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
651 A.2d 377, 1994 Me. LEXIS 313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vacuum-systems-inc-v-washburn-me-1994.