United States Ex Rel. Twin County Transit Mix, Inc. v. R. P. McTeague Construction Corp.

264 F. Supp. 619, 1967 U.S. Dist. LEXIS 9003
CourtDistrict Court, E.D. New York
DecidedFebruary 20, 1967
Docket64-C-1092
StatusPublished
Cited by5 cases

This text of 264 F. Supp. 619 (United States Ex Rel. Twin County Transit Mix, Inc. v. R. P. McTeague Construction Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Twin County Transit Mix, Inc. v. R. P. McTeague Construction Corp., 264 F. Supp. 619, 1967 U.S. Dist. LEXIS 9003 (E.D.N.Y. 1967).

Opinion

BARTELS, District Judge.

The United States has instituted this suit on behalf of Twin County Transit Mix, Inc. (referred to herein as the plaintiff) on a bond given by the defendant R. P. McTeague Construction Corp. (McTeague) under the Miller Act, 40 U.S.C.A. § 270a-d, for the purpose of securing payment for labor and material supplied under a contract entered into by McTeague with the Government.

McTeague was the general contractor for the construction of an automotive maintenance shop at the Suffolk County Air Base under a contract entered into with the Government, dated February 12, 1964. In connection with the execution of the contract McTeague delivered to the Government a bond executed by Fidelity and Deposit Company of Maryland as surety, in the sum of $205,747.50, conditioned upon the payment of claims of persons supplying labor and material for the construction of the above mentioned project.

About February 24, 1964 McTeague sublet to Jondray Construction Corp. the performance of certain concrete work required for the construction of the project by the plans and specifications referred to in the general contract. Between April 16,1964 and July 18,1964, pursuant to orders received from Jon-dray Construction Corp., the plaintiff delivered to the site of the project a total of 716 cubic yards of concrete which was used by Jondray in the prosecution of its work on the project. A dispute developed between McTeague and Jon- *620 dray and Jondray’s services at the job site were terminated during July 1964. The date of the last delivery by the plaintiff was July 18, 1964. The agreed price and reasonable value of the concrete delivered was $9,760.75, no part of which was paid. Plaintiff claims that it mailed to McTeague an unregistered letter dated September 4, 1964 demanding from it payment of the sums due from Jondray. McTeague denies receiving the letter and consequently a question of fact is presented.

I

One of the purposes of the registered mail requirement in the Miller Act is to require written notice to a general contractor by those supplying labor and material within ninety days after completion of the work, in order that the contractor may delay settlement with his sub-contractor and thus protect himself and his bond against unknown claimants with whom he has no direct contractual relationship. Coffee v. United States, 5 Cir. 1946, 157 F.2d 968. The leading case of Fleisher Engineering & Constr. Co. v. United States, 1940, 311 U.S. 15, 19, 61 S.Ct. 81, 83, 85 L.Ed. 12, states that the purpose of requiring service by registered mail is “ * * * to assure receipt of the notice, not to make the described method mandatory so as to deny right of suit when the required written notice within the specified time had actually been given and received. In the face .of such receipt, the reason for a particular mode of service fails. It is not reasonable to suppose that .Congress intended to insist upon an idle form.” (Emphasis supplied.) It is agreed by the authorities that the Miller Act must be liberally construed in order that the remedy afforded to laborers and materialmen on a payment bond may not be defeated. When the notice is not sent by registered mail, the claimant must sustain the burden of proving receipt and it has been uniformly held that this fact may be proved as any other fact. Thus, in Coffee v. United States, supra, the materialman was able to establish receipt by testimony that he had exhibited to the contractor a written notice of his claim showing the amount claimed and the identity of the subcontractor. In Houston Fire & Casualty Insurance Co. v. United States, 5 Cir. 1954, 217 F.2d 727, oral notice of the claim and a written acknowledgment of of the request by the contractor in recognition of the sub-contractor’s indebtedness to the materialman complied with the statutory requirement of the Act even though the writing relied upon was not signed, since requisite knowledge of the claim or debt was brought home to the contractor. In McWaters and Bartlett v. United States, 10 Cir. 1959, 272 F.2d 291, the materialman established receipt of sufficient notice by exhibiting to the contractor a written itemized statement of the sums due which the contractor read and examined while standing next to the claimant. 1 If in fact, the letter was received, the necessity for registered mail has been obviated.

The evidence in this case upon that question is conflicting. Joseph Muratore, the president of plaintiff testified, among other things, that in mid-June of 1964 he told McTeague, the president of defendant, at the job site that Jondray had not paid him; that in mid-July he again told McTeague at *621 the job site that he had not been paid; that in the latter part of July he received a telephone call from McTeague at which time he told McTeague again that he had not been paid, at which time McTeague assured him not to worry about payment; that on September 4, 1964 he dictated and signed a letter to McTeague (a copy of which was introduced in evidence as Exhibit 6) in which he demanded payment of the sums owed to plaintiff by Jondray and that prior to dictating the letter he had talked with his attorney Morris Gaines; that the usual practice in his office was to place the letter in an envelope and to send one of the girls to the Post-Office to mail the same and that the envelope used contained a notation upon the outside of plaintiff’s address; that a week after September 4, 1964 he received a telephone call from McTeague who stated that he received the letter and would like to discuss the matter with him at MeTeague’s office and that McTeague would have his attorney there, whereupon Muratore replied that he would have his attorney there also; that he later telephoned his attorney Morris Gaines and told him of this conversation. McTeague, on the other hand, denied any discussions with Muratore at the job site or over the telephone regarding any monies due Muratore from Jondray and denied making any appointment with Muratore for late September. In fact, he denied any notice or knowledge that sums were due Muratore from Jondray until shortly before he was served with a summons and complaint in this action.

Morris Gaines (Muratore’s attorney) testified that about a week after September 4, 1964 (on which date more than a month remained during which a registered letter could have been mailed), Muratore had telephoned him and stated that he, Muratore, received a telephone call from McTeague in response to the September 4th letter, that McTeague wanted to sit down and discuss the matter, and that an appointment had been made for a Friday in the middle of September at 2 P.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Adams Steel, LLC v. Elkins Contractors, Inc.
225 F. Supp. 3d 351 (D. South Carolina, 2016)
Vacuum Systems, Inc. v. Washburn
651 A.2d 377 (Supreme Judicial Court of Maine, 1994)
Pi-Con, Inc. v. a J Anderson Construction Co.
458 N.W.2d 639 (Michigan Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
264 F. Supp. 619, 1967 U.S. Dist. LEXIS 9003, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-twin-county-transit-mix-inc-v-r-p-mcteague-nyed-1967.