Greaig v. Park West Construction Co.

637 P.2d 1079, 130 Ariz. 576, 1981 Ariz. App. LEXIS 582
CourtCourt of Appeals of Arizona
DecidedOctober 6, 1981
Docket1 CA-CIV 4763
StatusPublished
Cited by3 cases

This text of 637 P.2d 1079 (Greaig v. Park West Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greaig v. Park West Construction Co., 637 P.2d 1079, 130 Ariz. 576, 1981 Ariz. App. LEXIS 582 (Ark. Ct. App. 1981).

Opinion

OPINION

JACOBSON, Judge.

This appeal requires the determination of whether employees of a subcontractor gave both timely and sufficient notice to the contractor so as to subject the contractor’s payment bond to liability for the alleged non-payment of their wages.

This action was instituted by appellants Ralph Greaig and Ernest Newman against Kenneth A. McIntyre and his wife, doing business as Sunshine Concrete, H. B. Associates, Arizona Millwork and appellees Park West Construction Company (Park West) and Aetna Casualty and Surety Company (Aetna) to recover overtime wages allegedly unpaid by their former employer, Sunshine Concrete.

On cross-motions for summary judgment, the trial court entered judgment in favor of Park West and Aetna against appellants. Appellants have appealed. Sunshine Concrete, H. B. Associates, and Arizona Mill-work are not parties to this appeal.

The facts as presented to the trial court are that Greaig and Newman were employed in 1977 by McIntyre, a licensed cement contractor doing business as Sunshine Concrete, to build forms in which to pour concrete.

On August 15, 1977, Sunshine Concrete was awarded a subcontract by Park West in connection with the construction of a large, commercial structure upon which Park West was the general contractor. Pursuant to A.R.S. § 33-1003, the owner required Park West to ]>ost a payment bond in order to avoid the mechanic’s lien provisions of A.R.S. § 33—981. Aetna appears as surety on that bond.

Apparently, in order for Sunshine Concrete to fulfill its subcontract, both Greaig and Newman were required to perform overtime work. Greaig and Newman alleged that an oral agreement was entered into between them and their employer, Sunshine Concrete, that they would defer the compensation for overtime until completion of the job. According to depositions, Greaig terminated his employment with Sunshine “early in December” of 1977 and Newman “left sometime earlier than that.” 1 Sunshine Concrete’s work under the sub-contract was completed in “the middle or end of January,” 1978. Greaig and Newman alleged they were never paid by Sunshine Concrete for the overtime work.

On January 23, 1978, Greaig signed a “Notice and Claim of Lien” naming Arizona Millwork Company or H. B. Associates as the owners of the property upon which the construction took place and purported to place a lien on that real property. Park West as general contractor was not named in this document. This Notice and Claim of Lien was duly recorded and a copy mailed to Arizona Millwork Company. Arizona Millwork in turn forwarded the copy to Park West, which in turn sent the copy to Sunshine Concrete. Sunshine Concrete apparently disputes that any money is owed to Greaig or Newman.

On February 14, 1978, Newman signed a Notice of Claim and Lien in the same form as Greaig. The record does not show that this claim of lien was ever recorded and there was no evidence that it ever came to the attention of Park West.

*578 On March 27, 1978, Greaig and Newman filed this action. There is no contention that Greaig or Newman had any direct contractual rights against Park West or Aetna and the liability of Park West and Aetna arise solely by reason of the payment bond posted by Park West pursuant to A.R.S. § 33-1003. Park West and Aetna’s motion for summary judgment was based upon the failure of Greaig and Newman to comply with the statutory conditions precedent for imposing liability under this bond.

Normally, every person who performs labor or furnishes material in the construction of any building, may impose a lien thereon for the labor performed or material furnished. A.R.S. § 33-981. However, this right to subject the property to a lien is limited by the provisions of A.R.S. § 33-1003.

A.R.S. § 33-1003 provides in part:
Every owner of land . . . who enters a contract requiring any person to perform labor, or to furnish materials ... in the construction ... of any building . . . may avoid the lien provisions of § 33-981 . .. by requiring the person with whom he contracts to furnish a payment bond prior to or at the time of execution of such contract.
* * * * * *
The bond shall be conditioned in accordance with the provisions of § 34-223, subsections A and B.

A.R.S. § 34-223 in pertinent part provides that:

[A]ny such claimant having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no contractual relationship express or implied with such contractor shall have a right of action upon such payment bond upon giving written notice to such contractor within ninety days from the date on which such claimant performed the last of the labor or furnished or supplied the last of the material for which such claim is made .... (Emphasis added).

It is basically the contention of Park West and Aetna that as to Greaig the “Notice and Claim of Lien” filed by him did not furnish the notice required by A.R.S. § 34-223 and that as to Newman, if notice can be supplied by filing suit, the notice was untimely.

Since there is no evidence that Park West had notice of the Newman claim until suit was filed, we will first deal with Greaig’s claim as to which arguably Park West received notice. As to Greaig’s claim we must initially determine whether a Notice and Claim of Lien which does not name the general contractor andl which only fortuitously comes to the attention of the general contractor is sufficient to comply with the notice requirements of A.R.S. § 34-223 that “written notice” be given to the “contractor within ninety days from the date on which such claimant performed the last of the labor... . ”

In arguing that the Notice and Claim of Lien filed by Greaig constituted sufficient compliance with the statute, Greaig relies primarily on the case of Western Asbestos Co. v. T. G. K. Construction Co., Inc., 121 Ariz. 388, 590 P.2d 927 (1979). In Western Asbestos, the Arizona Supreme Court was required to determine whether the notice requirements of A.R.S. § 34-223

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maricopa Turf, Inc. v. Sunmaster, Inc.
842 P.2d 1370 (Court of Appeals of Arizona, 1992)
Coast to Coast Manufacturing v. Carnes Construction, Inc.
700 P.2d 499 (Court of Appeals of Arizona, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
637 P.2d 1079, 130 Ariz. 576, 1981 Ariz. App. LEXIS 582, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greaig-v-park-west-construction-co-arizctapp-1981.