This text of 422 F.2d 597 (United States v. United States Fidelity & Guaranty Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. United States Fidelity & Guaranty Company, 422 F.2d 597, 1970 U.S. App. LEXIS 10481 (4th Cir. 1970).

Opinion

422 F.2d 597

UNITED STATES of America for the Use of DuKANE CORPORATION, Appellant,
v.
UNITED STATES FIDELITY & GUARANTY COMPANY, Electronic Sound, Incorporated, Great American Insurance Company, Algernon-Blair, Incorporated, Volta Electric Company, Incorporated, Sound and Music, Incorporated, Appellees.

No. 12726.

United States Court of Appeals, Fourth Circuit.

March 3, 1970.

Israel Steingold, Norfolk, Va. (Steingold, Steingold & Chovitz, Norfolk, Va., on the brief), for appellant.

Joseph A. Leafe and William E. Baggs, Norfolk, Va. (Rixey & Rixey, Edward L. Breeden, III, and Breeden, Howard & McMillan, Norfolk, Va., on the brief), for appellees.

Before BOREMAN, WINTER and BUTZNER, Circuit Judges.

BOREMAN, Circuit Judge:

This litigation commenced by an action brought under the Miller Act1 by the United States for the use of DuKane Corporation (hereafter DuKane) against Electronic Sound, Incorporated (hereafter Electronic), Algernon-Blair, Incorporated (hereafter Algernon-Blair) and its surety, United States Fidelity & Guaranty Company (hereafter USF&G), Volta Electric Company, Incorporated (hereafter Volta), and its surety, Great American Insurance Company, and Sound and Music, Incorporated, the last-named defendant not being a party to this appeal. Answers were filed by all defendants except Volta. Algernon-Blair filed cross-claims for indemnity against its subcontractor Volta and Volta's surety, Great American. Great American answered the cross-claim and filed a third-party complaint against two individuals, Garcia and DeAngelo, who had undertaken to indemnify Great American.

Certain material facts are preliminarily stated but others will be developed during the discussion of issues and contentions presented on appeal.

On April 27, 1964, Algernon-Blair was awarded a general contract by the United States for the construction of a Composite Medical Facility (hereafter "the project") at Langley Field, Virginia, in the amount of $2,788,225.00. Algernon-Blair then awarded a subcontract for electrical work in connection with the project to Volta in the amount of $317,650.00. Volta, in turn, entered into a sub-subcontract with Electronic covering a portion of its electrical subcontract in the amount of $26,123.00 which was later reduced by change orders to $22,680.00.

DuKane, the use plaintiff, provided materials to Electronic at the latter's invitation, for which DuKane was not paid, in the amount of $13,893.02. On November 20, 1964, Electronic assigned to DuKane the proceeds of its contract with Volta which assignment was accepted by Volta in writing. The last of the materials supplied by DuKane and for which no payment was made were delivered on December 29, 1965. However, on February 8, 1966, and March 4, 1966, DuKane supplied other materials to the project but each shipment was on a C.O.D. basis and payment therefor was made on delivery.

During the process of construction DuKane became concerned about payment as there appeared to be some question about the financial stability of Electronic and Volta. DuKane refused to ship additional materials which had been ordered by Electronic and notified the general contractor, Algernon-Blair, to that effect. On December 3, 1965, Algernon-Blair agreed, by letter, with DuKane that it would see that DuKane was paid for all materials shipped to the project subsequent to that date. Algernon-Blair's letter was as follows:

This will confirm our telephone conversation today in which we advised that in consideration for prompt release of the balance of the materials and equipment which Electronic Sound, Inc., has ordered from you for use on this project, we will see that you receive payment for same.

As a condition of this arrangement, you are to send us a copy of each invoice involved. (Emphasis added.)

The materials shipped subsequent to December 3, 1965, for which DuKane was not paid, amounted to $8,304.30.

The assignment to DuKane by Electronic of the latter's contract rights with Volta ($22,680.00) was given to insure payment not only for the materials to be furnished by DuKane to the project but also other materials which had been theretofore furnished to Electronic by DuKane on other projects. In violation of Volta's obligation to make payments to DuKane by virtue of the assignment, Volta paid to Electronic on December 3, 1965, the sum of $4,000.00, and on December 15, 1965, Volta endorsed over to Electronic a check from Algernon-Blair made payable to both Electronic and Volta in the amount of $5,000.00. Electronic used the proceeds of the $5,000.00 check.

The case was tried without a jury and the district court rendered its Memorandum Decision containing extensive findings of fact2 and stating its conclusions of law. A final order was entered in the district court awarding judgment to DuKane against Algernon-Blair and its surety, USF&G, in the amount of $8,304.30, that being the invoice price of the materials delivered after December 3, 1965, the responsibility for payment having been assumed by Algernon-Blair. DuKane was awarded judgment against Great American, surety for Volta, in the amount of $13,893.02, provided, however, that this amount would be reduced by $8,304.30, the amount of DuKane's judgment against Algernon-Blair, if paid by Algernon-Blair or USF&G. Judgment was rendered in favor of DuKane, as assignee of Electronic, against Volta in the amount of $22,893.02, and against Electronic in the amount of $22,680.00. The judgment order further provided that Algernon-Blair recover from Volta, or its surety, Great American, all payments which Algernon-Blair was required to make plus its costs and attorneys' fees, and that Great American recover from Volta and the individual indemnitor, Garcia, all sums which Great American was required to pay to Algernon-Blair, USF&G, or DuKane plus its own costs and attorneys' fees.

On this appeal DuKane attacks the holding of the district court with respect to the liability of Algernon-Blair and its surety, USF&G, to DuKane and the holding with respect to the liability of Great American, Volta's surety, by virtue of the assignment to DuKane from Electronic of the latter's claim against Volta. DuKane contends that Algernon-Blair and its Miller Act surety, USF&G, are liable to it under the Act for the full sum of $22,680.00 (Electronic's contract with Volta) plus $13,893.02, the value of materials actually furnished by DuKane to the project (not to exceed, however, $30,855.36, the total amount shown by the evidence as owed to DuKane by Electronic from this and all other projects), either by reason of the assignment from Electronic to DuKane or by reason of Algernon-Blair's letter of December 3, 1965, to DuKane.

Pertinent to the consideration and determination of claims of DuKane with respect to rights asserted under the Miller Act are the provisions of 40 U.S.C. § 270b(a) as shown below.3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
422 F.2d 597, 1970 U.S. App. LEXIS 10481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-united-states-fidelity-guaranty-company-ca4-1970.