S & S Paving & Construction, Inc. v. Berkley Regional Insurance

372 P.3d 1036, 239 Ariz. 512, 738 Ariz. Adv. Rep. 16, 2016 Ariz. App. LEXIS 81
CourtCourt of Appeals of Arizona
DecidedMay 12, 2016
DocketNo. 1 CA-CV 15-0239
StatusPublished
Cited by7 cases

This text of 372 P.3d 1036 (S & S Paving & Construction, Inc. v. Berkley Regional Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & S Paving & Construction, Inc. v. Berkley Regional Insurance, 372 P.3d 1036, 239 Ariz. 512, 738 Ariz. Adv. Rep. 16, 2016 Ariz. App. LEXIS 81 (Ark. Ct. App. 2016).

Opinion

OPINION

DOWNIE, Judge:

¶ 1 S & S Paving and Construction, Inc. (“S & S”) appeals the dismissal of its bad faith claim against Berkley Regional Insurance Company (“Berkley”). We hold that a surety on a payment bond issued under Arizona’s “Little Miller Act” may not be sued for bad faith and therefore affirm the judgment of the superior court.

FACTS AND PROCEDURAL HISTORY

¶ 2 The City of Prescott retained Spire Engineering, LLC (“Spire”) to act as general contractor for the Demerse Avenue Overlay Project (“the Project”). Berkley issued a payment bond for the Project. See Ariz. Rev. Stat. (“A.R.S.”) § 34-222(A)(2) (requiring payment bonds for public projects).

¶ 3 In October 2011, S & S’s attorney sent a demand letter to Berkley, stating that S & S had performed paving work for the Project pursuant to its subcontract with Spire and had not been paid $23,763. Berkley acknowledged the claim, requested additional information, and advised that its review of S & S’s demand “does not toll the running of any statute of limitations or other time period.”

¶ 4 S & S provided Berkley with the requested information, which included a proof of claim. Berkley acknowledged receipt of the documentation in December 2011 and stated that it needed to ascertain Spire’s position regarding S & S’s claim, after which it would communicate further. Berkley reiterated that its investigation of the claim “in no way waives or alters any rights, interests [514]*514or defenses that we may have under our bond or applicable law.” No further communication occurred between the parties until May 2013, when counsel for S & S sent another demand letter, and Berkley responded that S & S’s claim was untimely.

¶ 5 In November 2013, S & S sued Berkley for breach of contract and bad faith.1 Berkley moved for summary judgment on both claims. The superior court ruled that the breach of contract claim was barred by the statute of limitations. See A.R.S. § 34-223(B) (one-year statute of limitations for public work payment bonds). The court also dismissed S & S’s bad faith claim, concluding there was no “contractual relationship or special relationship for the claim to survive.” The court denied S & S’s motion for reconsideration and awarded Berkley attorneys’ fees.

¶ 6 S & S timely appealed. We have jurisdiction pursuant to A.R.S. §§ 12-120.21(A)(1) and -2101(A)(1).

DISCUSSION

¶ 7 We review a grant of summary judgment de novo. Chalpin v. Snyder, 220 Ariz. 413, 418, ¶ 17, 207 P.3d 666, 671 (App.2008). Summary judgment is appropriate if “there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law.” Ariz. R. Civ. P. 56(a). We will affirm the judgment if it is correct for any reason. Ariz. Bd. of Regents v. State ex rel. Ariz. Pub. Safety Ret. Fund Manager, 160 Ariz. 150, 154, 771 P.2d 880, 884 (App.1989).

¶ 8 In 1969, Arizona adopted the Little Miller Act, A.R.S. §§ 34-221, et seq. (“the Act”). See SCA Constr. Supply v. Aetna Cas. & Sur. Co., 157 Ariz. 64, 65-66, 754 P.2d 1339, 1340-41 (1988). Modeled after the federal Miller Act, 40 U.S.C. § 270a, et seq., the Act requires contractors on public works projects to furnish payment bonds “for the protection of claimants supplying labor or materials to the contractor or his subcontractors.” A.R.S. § 34-222(A)(2). A claimant who is not paid in full for labor or materials “shall have the right to sue on such payment bond.” A.R.S. § 34-223(A). “The purpose behind both of the Miller Acts is to provide security for those who supply materials or labor in the construction of public projects.” SCA Constr., 157 Ariz. at 66, 754 P.2d at 1341. Such statutory protection is necessary because no lien rights exist on public projects. See F.D. Rich Co. v. United States ex rel. Indus. Lumber Co., 417 U.S. 116, 122, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974) (liens “cannot attach to Government property,” so the Miller Act is intended “to provide an alternative remedy to protect” suppliers on public works projects).

¶ 9 S & S does not challenge the dismissal of its breach of contract claim on statute of limitations grounds. See AR.S. § 34-223(B) (No suit “shall be commenced after the expiration of one year from the date on which the last of the labor was performed or materials were supplied by the person bringing ... suit.”). It instead contends the superior court erred by dismissing its bad faith claim because sureties issuing payment bonds under the Act have a duty to “undertake an investigation adequate to determine whether a claimant’s claim is tenable or valid.” According to S & S, sureties owe the same duty of good faith to claimants under the Act as insurance companies owe to insureds.

¶ 10 S & S asks us to graft a common law remedy onto a statutory scheme that includes within its ambit both the availability of complete relief and specific conditions precedent to recovery. But “where a statute expressly provides a particular remedy or remedies, a court must be chary of reading others into it.” Transamerica Mortg. Advisors, Inc. v. Lewis, 444 U.S. 11, 19, 100 S.Ct. 242, 62 L.Ed.2d 146 (1988); see also State ex rel. Horne v. AutoZone, Inc., 229 Ariz. 358, 362-63, 275 P.3d 1278, 1282-83 (2012) (declining to read disgorgement remedy into statutory scheme “unless and until” the Arizona Legislature makes such a determination).

¶ 11 The Arizona Legislature has defined the breadth of liability under the Act. Section 34-222(F) dictates the terms that payment [515]*515bonds must include—one of which is the statement that “all liabilities on this bond shall be determined in accordance with the provisions, conditions and limitations of title 34, chapter 2, article 2, Arizona Revised Statutes, to the same extent as if they were copied at length in this agreement.” (Emphasis added.) “All liabilities” is a broad term. Recognizing a common law bad faith remedy would be inconsistent with the legislature’s defined liability for Act sureties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pillsbury v. Butler
Court of Appeals of Arizona, 2021
Everson v. Tucci
Court of Appeals of Arizona, 2020
Acedo v. Mannion
Court of Appeals of Arizona, 2020
Jackson v. Dequina
Court of Appeals of Arizona, 2018
Sundance v. Glawe
Court of Appeals of Arizona, 2018
Claborn v. Yuma County
Court of Appeals of Arizona, 2017
Wells Fargo v. Hoag
Court of Appeals of Arizona, 2016

Cite This Page — Counsel Stack

Bluebook (online)
372 P.3d 1036, 239 Ariz. 512, 738 Ariz. Adv. Rep. 16, 2016 Ariz. App. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-s-paving-construction-inc-v-berkley-regional-insurance-arizctapp-2016.