Trio Forest Products, Inc. v. FNF Construction, Inc.

893 P.2d 1, 182 Ariz. 1, 167 Ariz. Adv. Rep. 34, 1994 Ariz. App. LEXIS 125
CourtCourt of Appeals of Arizona
DecidedJune 16, 1994
Docket2 CA-CV 94-0071
StatusPublished
Cited by4 cases

This text of 893 P.2d 1 (Trio Forest Products, Inc. v. FNF Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trio Forest Products, Inc. v. FNF Construction, Inc., 893 P.2d 1, 182 Ariz. 1, 167 Ariz. Adv. Rep. 34, 1994 Ariz. App. LEXIS 125 (Ark. Ct. App. 1994).

Opinion

OPINION

HATHAWAY, Judge.

This is an appeal from a summary determination by the trial court holding that appellant Trio Forest Products, Inc. (Trio) had no claim against appellees FNF Construction, Inc. (FNF) and its surety, National Union Fire Insurance Company of Pittsburgh, PA., (National Union), under the Arizona Little MiUer Act, A.R.S. §§ 34-221 through 34-226. We reverse.

Arizona enacted the Little MiUer Act in 1969, modeling it after the Federal MUler Act, 40 U.S.C. §§ 270a through 270d (the Federal Act). Both acts require that a general contractor on a pubUc project post a bond to ensure that aU who supply labor or materials on the project are paid. The Little MUler Act provides, in part:

Every claimant who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which a payment bond is furnished under the provisions of § 34-222, and who has not been paid in full ... shall have the right to sue on such payment bond ..., provided however that any such claimant *2 having a direct contractual relationship with a subcontractor of the contractor furnishing such payment bond but no contractual relationship express or implied with such contractor shall have a right of action upon such payment bond upon giving the contractor only a written preliminary twenty day notice____

A.R.S. § 34-223(A). Since no lien rights are permitted on public projects, the Little Miller Act allows an unpaid party to recover under the bond. General Acrylics v. United States Fidelity and Guaranty Co., 128 Ariz. 50, 623 P.2d 839 (App.1980). The broad purpose behind both acts is to “provide protection comparable to that afforded by state mechanic’s hen laws on private contracts____” J.W. Bateson Co., Inc. v. U.S. ex rel. Board of Trustees, 434 U.S. 586, 602, 98 S.Ct. 873, 882, 55 L.Ed.2d 50, 62 (1978).

FACTS

FNF was the general contractor on a bridge project for the Arizona Department of Transportation. As required by Arizona’s Little Miller Act, FNF provided payment and performance bonds that were supplied by National Union as its surety. FNF subcontracted with S.Y. Construction, Inc. (S.Y.) to build the bridge, and S.Y. contracted with Southern American Insurance Company (Southern American) to provide payment and performance bonds. Appellant Trio was a material supplier to S.Y. Soon after the project began, S.Y. defaulted and Southern American, as its surety, assumed responsibility for completion of the project. In that capacity, Southern American completed the subcontract through its wholly-owned subsidiary, Seven Peaks Construction, Inc. (Seven Peaks).

At the inception of Southern American’s involvement, it told FNF that “Seven Peaks Construction is a wholly-owned subsidiary of Southern American Insurance created for the sole purpose of ease in completing defaulted construction projects.” Seven Peaks further stated that “you [FNF] should treat Seven Peaks for all purposes as the completing contractor on the project.” FNF did so and never objected to this arrangement. Throughout the completion of the project, FNF addressed letters to “S.Y./7 Peaks Construction” and obligated Southern American through Seven Peaks to perform according to the precise terms of the original subcontract with S.Y. FNF made all contract payments to Seven Peaks under the S.Y. contract name and number.

It is undisputed that Trio filed all preliminary notices required by the Little Miller Act to put FNF on notice that it was a material supplier. Before the project was completed, Southern American filed for bankruptcy. S.Y. paid Trio for materials, but Seven Peaks did not. This case is based upon a claim by Trio against FNF and National Union for the balance due for materials it supplied to Seven Peaks.

Both parties filed motions for summary judgment. The trial court ruled in favor of FNF that Trio had “no claim against FNF for lumber furnished to Seven Peaks Construction, Inc. because it was sub-subcontractor to FNF, thereby making Plaintiff too remote to recover on FNF’s payment bond.” We disagree and reverse.

ARIZONA’S LITTLE MILLER ACT PROVIDES PROTECTION FOR A SUB-SUBCONTRACTOR

FNF argues that because the Little Miller Act was modeled upon the Federal Act, Arizona courts must follow federal case law which holds that a sub-subcontractor may not recover under the Federal Act. J.W. Bateson Co., supra. We disagree. This court is under no obligation to follow federal decisions that interpret the Federal Act. Division One of the Arizona Court of Appeals has noted the “conspicuous lack of reported decisions dealing with Arizona’s version of this statute [Little Miller Act].” Honeywell, Inc. v. Arnold Const. Co., Inc., 134 Ariz. 153, 156, 654 P.2d 301, 304 (App. 1982) (Federal Act followed because its notice period was the same as in the Little Miller Act); See also, SCA Const. Supply v. Aetna Casualty & Surety Co., 157 Ariz. 64, 754 P.2d 1339 (1987) (Arizona Supreme Court declined to follow Federal Act where there was no federal counterpart to the Arizona rule in question, and federal case law was thus inapplicable).

*3 FNF argues that because it did not enter into a separate subcontract with Southern American, Trio, as Seven Peaks’ subcontractor was too remote to recover under FNF’s surety. To the contrary, the correct test to determine whether the parties are too remote to allow recovery is a functional relationship test which examines the nature of the dealings between the parties. Advance Leasing & Crane Co., Inc. v. Del E. Webb Corp., 117 Ariz. 451, 573 P.2d 525 (App.1977); cf. Ray Electric, Inc. v. Merchants Bonding Company (Mutual), 157 Ariz. 374, 758 P.2d 149 (App.1988) (court looks at elements such as who exercises control to determine contractual chain for Little Miller Act purposes). This court has previously held that a direct contract between a supplier and a general contractor is not required for the supplier to recover under the Little Miller Act. Arizona Laborers, Teamsters & Cement Masons Local 395 Health & Welfare Trust Fund v. New Pueblo Constructors, Inc., 131 Ariz. 278, 640 P.2d 209

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & S Paving & Construction, Inc. v. Berkley Regional Insurance
372 P.3d 1036 (Court of Appeals of Arizona, 2016)
S&S Paving v. Berkley
Court of Appeals of Arizona, 2016
R.E. Monks Construction Co. v. Aetna Casualty & Surety Co.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
RE MONKS CONST. v. Aetna Cas. & Sur.
944 P.2d 517 (Court of Appeals of Arizona, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
893 P.2d 1, 182 Ariz. 1, 167 Ariz. Adv. Rep. 34, 1994 Ariz. App. LEXIS 125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trio-forest-products-inc-v-fnf-construction-inc-arizctapp-1994.