Honeywell, Inc. v. Arnold Const. Co., Inc.

654 P.2d 301, 134 Ariz. 153, 1982 Ariz. App. LEXIS 559
CourtCourt of Appeals of Arizona
DecidedSeptember 23, 1982
Docket1 CA-CIV 5148
StatusPublished
Cited by18 cases

This text of 654 P.2d 301 (Honeywell, Inc. v. Arnold Const. Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Honeywell, Inc. v. Arnold Const. Co., Inc., 654 P.2d 301, 134 Ariz. 153, 1982 Ariz. App. LEXIS 559 (Ark. Ct. App. 1982).

Opinion

OPINION

GRANT, Judge.

This case was originally brought by Plaintiff-Appellee Honeywell, Inc., under Arizona’s public construction bonding statute, known as the “Little Miller Act,” A.R.S. §§ 34-221 to 224. 1 The facts material to a resolution of the issues presented are as follows. On July 22, 1975, Arnold Construction Company was awarded the general contract for construction of a business education addition to the Trevor G. *155 Browne High School in Phoenix, Arizona. On the same day Arnold executed a payment bond, required by A.R.S. § 34-222, naming Safeco Insurance Company of America as its surety. Shortly thereafter, Arnold subcontracted the ventilation work to Southwest Air Conditioning, Inc. Squthwest in turn hired Honeywell, Inc. to furnish and install a “comprehensive pneumatic system of automatic temperature control,” which would be connected to the high school’s fire alarm system.

Work progressed with no apparent difficulty. Arnold fully paid Southwest except for the contractual ten percent retention, which would only become payable ten days after Arnold received full payment for the entire project. The architects issued their certificate of substantial completion for the whole addition, effective June 1, 1976. On that same date, the project engineer issued a “punch list,” identifying various items still requiring completion, repair or replacement before the project would be finished. Honeywell continued to perform both the punch list and other work at the construction site, after the June 1st substantial completion date, until approximately October 21, 1976. Characterization of this work, more completely described below, is the central issue in this appeal.

Honeywell first notified Arnold by letter dated June 14, 1976, that Southwest had failed to pay them any amounts due on their $31,127.00 contract. Again, on July 21, 1976, Honeywell sent written notice to Arnold which said that they still had not been paid by Southwest. This letter further stated that if payment was not soon made, Honeywell would look to Arnold and Safeco for satisfaction of the debt. On September 16, 1976, Honeywell sent one last letter to Arnold indicating that suit would be brought against Arnold’s payment bond if the debt remained unsatisfied by the end of the month. Honeywell received no payment.

On June 21, 1977, Honeywell filed suit against Arnold, Safeco and Southwest for payment of the $31,127.00 contract price. 2 Arnold cross-claimed against Southwest for any amounts it would be found to owe Honeywell. Arnold also filed a third party complaint against John and Joan Owens, claiming they were alter egos of Southwest and therefore liable for its debts.

Honeywell moved for, and was granted, judgment on the pleadings against Southwest, who did not contest the motion. At the end of Arnold’s presentation of evidence, the Owenses moved for a directed verdict in their favor on Arnold’s third party complaint. The motion was granted, relieving the Owenses of any possible personal liability. Upon completion of the non-jury trial, the court granted judgment in favor of Honeywell against Arnold and Safeco. Additionally, Arnold was granted judgment against Southwest on its cross-claim. Arnold’s and Safeeo’s subsequent motion for new trial was denied. Filing a timely notice of appeal, Arnold and Safeco challenged the judgment in favor of Honeywell and the directed verdict granted in favor of the Owenses. They also appealed the denial of their motion for a new trial.

We first address the challenge by Arnold and Safeco to the judgment in favor of Honeywell. As noted above, Honeywell’s suit was brought under authority of Arizona’s A.R.S. §§ 34-221 to 224. This statute generally covers the award, execution and performance of public construction contracts. The general contractor on a public construction project is required to furnish, “[a] payment bond in an amount equal to the full contract amount solely for the protection of claimants supplying labor or materials to the contractor or his subcontractors in the prosecution of the work.... ” A.R.S. § 34-222(A)(2). A right of action against this payment bond is granted to subcontractors, and their labor or material-men, in the event they are not fully paid within ninety days from the date on which *156 they last performed labor or furnished materials. A.R.S. § 34-223. The right of action contains, however, two significant limitation periods. First, one not having a direct contractual relationship with the general contractor who furnished the bond, but who has such a relationship with one of his subcontractors, must give the general contractor written notice of the claim within ninety days from the date on which he last performed labor or supplied materials. A.R.S. § 34 — 223(A). Second, every suit brought under this statute must be commenced within “one year from the date on which the last of the labor was performed or materials were supplied.... ” A.R.S. § 34-223(C).

While they do not contest the timeliness or adequacy of compliance with the ninety day notice period, Arnold and Safeco argue that Honeywell has run afoul of the one year period of limitation for filing the action. Specifically, Arnold and Safeco contend that Honeywell performed no work of sufficient magnitude to constitute “labor .. . performed or materials .. . supplied” within one year prior to the filing of its complaint on June 21, 1977. They claim that any work done by Honeywell within the statutory period was only for minor repair or correction of defects. [Honeywell filed its complaint on June 21, 1977.] The focus of our inquiry is therefore whether any of the work performed by Honeywell between June 21, 1976, and October 21, 1976, the last date on which it claims to have performed anything under the contract, could be considered labor performed or materials supplied within the meaning of A.R.S. § 34-223(0).

We note the conspicuous lack of reported decisions dealing with Arizona’s version of this statute. Because our formulation so closely follows the federal legislation, however, federal cases interpreting the Miller Act are highly persuasive. Western Asbestos Co. v. TGK Construction Co., Inc., 121 Ariz. 388, 590 P.2d 927 (1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estrada v. Figari
Court of Appeals of Arizona, 2015
commerce/cra v. Zinke
Court of Appeals of Arizona, 2014
R.E. Monks Construction Co. v. Aetna Casualty & Surety Co.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
RE MONKS CONST. v. Aetna Cas. & Sur.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
Deutsche Credit Corp. v. Case Power & Equipment Co.
876 P.2d 1190 (Court of Appeals of Arizona, 1994)
Trio Forest Products, Inc. v. FNF Construction, Inc.
893 P.2d 1 (Court of Appeals of Arizona, 1994)
Herberman v. Bergstrom
816 P.2d 244 (Court of Appeals of Arizona, 1991)
Leo Eisenberg & Co., Inc. v. Payson
785 P.2d 49 (Arizona Supreme Court, 1989)
Camelback Del Este Home-Owners Ass'n v. Warner
749 P.2d 930 (Court of Appeals of Arizona, 1987)
SCA Construction Supply v. Aetna Casualty & Surety Co.
746 P.2d 22 (Court of Appeals of Arizona, 1987)
Standage v. Standage
711 P.2d 612 (Court of Appeals of Arizona, 1985)
Dahl v. Gardner
583 F. Supp. 1262 (D. Utah, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
654 P.2d 301, 134 Ariz. 153, 1982 Ariz. App. LEXIS 559, Counsel Stack Legal Research, https://law.counselstack.com/opinion/honeywell-inc-v-arnold-const-co-inc-arizctapp-1982.