United States ex rel. Erie City Iron Works v. Fullerton Construction Co.

298 F. Supp. 1157, 1969 U.S. Dist. LEXIS 10672
CourtDistrict Court, D. South Carolina
DecidedApril 30, 1969
DocketCiv. A. No. 68-323
StatusPublished
Cited by4 cases

This text of 298 F. Supp. 1157 (United States ex rel. Erie City Iron Works v. Fullerton Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Erie City Iron Works v. Fullerton Construction Co., 298 F. Supp. 1157, 1969 U.S. Dist. LEXIS 10672 (D.S.C. 1969).

Opinion

ORDER

SIMONS, District Judge.

This action was instituted pursuant to the Miller Act, 40 U.S.C.A. § 270a et seq.1 and is before this court on defendants’ motion for summary judgment.

The facts surrounding this controversy are essentially undisputed. On October 30, 1964, the defendant, Fullerton Construction Company, and its surety, Continental Casualty Company, entered into a contract with the United States of America for the construction of a central heating and refrigeration plant at Fort Jackson, South Carolina. This contract contained a one-year guaranty provision covering materials and workmanship which began running upon the date of beneficial or final acceptance by the government, whichever came earlier2 On January 22,1965 the defendant Fullerton entered into a subcontract with the plaintiff whereby the plaintiff agreed to furnish certain labor and material necessary for the installation of three boilers called for under the original contract between the United States of America and the defendants.

On May 23, 1966 all construction required by the government contract was substantially complete. On August 9, 1966, and September 22, 1966, the entire project, including the work performed by the plaintiff, was inspected and approved by the government. Approximately six and one-half months elapsed after the government had inspected the project. Then between April 6 and April [1159]*115915 of 1967 the plaintiff performed additional work and supplied additional materials for the purpose of correcting defects and/or making repairs to the work previously completed by the plaintiff pursuant to his subcontract with the defendant Fullerton. This was done at the request of the government pursuant to and in accordance with the one year guaranty contained in the prime contract. (Note 2, swpra). Within a year thereafter, on April 12, 1968, the plaintiff instituted the present action contending that the additional work done and materials provided under the guaranty constituted “labor performed or material supplied” in performance of the original contract, and that the suit was timely under Section 270b(b) of the Miller Act, (Note 1, supra). The defendants maintain that the action brought by the plaintiff is untimely, contending that the correction of defects and the making of repairs, regardless of the fact that the same were accomplished in accordance with the guaranty provision in the prime contract, do not extend the statutory time limit for instituting suit under the Miller Act, and do not constitute work performed or material supplied as a part of the original contract. Thus, the precise issue for determination is whether the making of repairs and/or the correcting of defects pursuant to a one-year guaranty provision contained in the original contract constitute labor performed or material supplied as a part of the original contract.

After a careful review of the authorities, the court has concluded that the issue must be resolved in the negative and, therefore, that the plaintiff’s action is untimely under Section 270b (b), (Note 1, supra). The applicable legal test of Section 270b(b), as recently stated by the Fourth Circuit in United States of America for Use of Noland Company v. Andrews and Parrish, et al., 406 F.2d 790 (decided Jan. 24, 1969), is “whether the work was performed and the material supplied as a ‘part of the original contract’ or for the ‘purpose of correcting defects, or making repairs following inspection of the project.’ ” Thus, under the decided cases of this jurisdiction, as well as other jurisdictions, the furnishing of labor and materials for the purpose of correcting defects or making repairs of the original undertaking is not labor performed or material supplied as a part of the original contract and will not extend the statutory time limitation. United States of America ex rel. for Use of Noland Company v. Andrews and Parrish, et al., supra; United States of America ex rel. Palmer Asphalt Co. v. Debardelaben, 278 F.Supp. 722 (D.C.S.C.1967), aff’d, 4 Cir., 388 F.2d 309 (4th Cir. 1967); United States of America ex rel. Austin v. Western Electric Co., 337 F.2d 568 (9th Cir. 1964); United States of America ex rel. Weithman v. Buckeye Union Cas. Company, 207 F.Supp. 552 (N.D.Ohio 1962); United States of America ex rel. John T. Evanick & Co. v. Merritt-Chapman & Scott Corp., 185 F.Supp. 587 (M.D.Pa.1960). See also United States ex rel. State Electric Supply Co. v. Hesselden Construction Co., 404 F.2d 774 (10th Cir. 1968).

Unquestionably, the labor and material furnished by the plaintiff in April of 1967 was for the sole purpose of correcting the previously supplied defective materials and/or making repairs to such previously supplied materials or parts. It cannot be said that the materials supplied in April of 1967 by the plaintiff were materials that were called for by the terms of the original contract and not supplied until April of 1967. The factual situation here does not present a case where there has been a failure in some manner to fully complete the original contract, such as where some parts or materials called for by the contract have never been supplied. It is undisputed that all work performed and materials supplied during April of 1967 were merely for the purpose of correcting defects, or making repairs, to materials or parts already furnished, following the inspection and acceptance of the project by the government, and the fact that the one-year guaranty existed as a part of [1160]*1160the original contract cannot change the status of the April work from that of curing defects or of making repairs to work done or materials furnished as a part of the original contract.3

Plaintiff cites the case of Trinity-Universal Insurance Company v. Girdner, 379 F.2d 317 (5th Cir. 1967), as authority for its position. In that case the court held that work performed to correct defects or make repairs in the work originally completed, upon demand of the government, was work performed within the language of the statute. However, in the Girdner case the only work done by the subcontractor within the year before the commencement of the suit was to replace some defective pipe installation which he had previously installed and to replace a seal in an air conditioning unit. The subcontractor performed these operations on the demand of the government inspector, who had refused to approve the original work. Thus, the Girdner case is readily distinguishable from the case at hand in that here the government approved the original work, and the replacement of the defective parts was not made until six and one-half months following the inspection.

The commencement of an action within the one year statutory time limitation is a condition precedent to the maintenance of an action under the Miller Act. The correction of the defects and the making of the repairs by the Use plaintiff in the month of April 1967, although performed pursuant to the one-year guaranty in the prime contract (Note 2, supra,), did not serve to toll the running of the one-year statutory limitation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Honeywell, Inc. v. Arnold Const. Co., Inc.
654 P.2d 301 (Court of Appeals of Arizona, 1982)
Lehigh Elec. Prod. v. Pa. Nat. Mut. Cas. Ins.
390 A.2d 781 (Superior Court of Pennsylvania, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
298 F. Supp. 1157, 1969 U.S. Dist. LEXIS 10672, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-erie-city-iron-works-v-fullerton-construction-co-scd-1969.