Eclipse Lumber Co. v. Bitler

241 N.W. 696, 213 Iowa 1313
CourtSupreme Court of Iowa
DecidedMarch 8, 1932
DocketNo. 41115.
StatusPublished
Cited by4 cases

This text of 241 N.W. 696 (Eclipse Lumber Co. v. Bitler) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eclipse Lumber Co. v. Bitler, 241 N.W. 696, 213 Iowa 1313 (iowa 1932).

Opinion

Kindig, J.

But one question arises on this appeal: namely, whether a mechanic’s lien held by the plaintiff-appellant, Eclipse Lumber Company, is .inferior to a mortgage owned by the defendant-appellee, Fred Andresen.

On or about October 12, 1927, the appellant Lumber Company entered into an oral contract with the defendant-appellee, A. S. Bitler, to furnish him building materials to construct a house on certain real estate owned by the latter in Clinton. These building materials were delivered by appellant to the appellee, Bitler, between October "12, 1927, and March 23, 1928. During the progress of the work, and on December 1, 1927, the appellee Bitler, in accordance with the contract between bim and the appellant, gave a mortgage on the premises to the defendant-appellee, Fred Andresen, for the purpose of securing a $4,000 loan. This $4000 was thus borrowed by Bitler from Andresen to pay, or partly pay, for constructing the house. The mortgage was recorded September 21, 1928. After the mortgage was given and the aforesaid materials for the house were being delivered, the appellee Bitler conveyed the- aforesaid premises by deed to the appellee, George W. Brown.

Although the last of the said materials were delivered on the premises March 23, 1928, yet the appellant did not file his *1315 statement for a mechanic’s lien until August 23, 1928, approximately two months later than the ninety days of grace during which, under the statute, the principal contractor could perfect the mechanic’s lien after the last labor or material was furnished. Appellant contends, however, that its mechanic’s lien is superior to the mortgage held by the appellee, Andresen, because the mortgage was given while the materials were being furnished, and prays for judgment accordingly. See Wood v. Ball, 194 Iowa 50.

As said in the preliminary statement, the district court found the mortgage to be a superior lien, but established the appellant’s mechanic’s lien as prior to the rights of the appellees, Bitler and Brown. No objection is made by the appellant to any portion of the judgment and decree, except the part thereof which, as before explained, declares the mortgage superior to the mechanic’s lien. Bitler and Brown do not appeal.

Andresen, the appellee, admits that the mechanic’s lien would be superior to his mortgage were it not for appellant’s waiver of such priority. In other words, it is contended by Andresen, the mortgagee, that the appellant waived the priority of its mechanic’s lien and consented that the mortgage should be first at the time the contract for the materials was made with the owner, Bitler. That contract between Bitler and appellant,as before stated, was made on or about October 12, 1927. Bitler could not finance the construction of the house on a cash basis. Therefore, he applied to appellant for more liberal terms under which the project might be completed. Following those negotiations, it was orally agreed between appellant and Bitler that the materials would be furnished under the following concessions : First, a mortgage could be placed on the premises by Bitler with which to procure the money to pay for the materials aforesaid; or, second, the real estate could be sold by Bitler and the money obtained in that way with which to pay the appellant; and/ or, third, if neither a mortgage nor a sale were possible, then the appellant agreed to take a mortgage on house and lot for the amount due it. Consequently it is asserted by the mortgagee that the appellant thereby consented that the mechanic’s lien should be inferior to the mortgage. To put the thought differently, it is claimed by the mortgagee that the appellant, through the aforesaid contract, waived the priority of its me *1316 chanic’s lien. Generally speaking, “a waiver is-the voluntary and intentional relinquishment of a known right, benefit, or advantage.” Chicago, Northwestern Railway Co. v. Sedgwick, 203 Iowa 726 (local citation, 729).

See, also, In re Estate of Sarvey, 206 Iowa 527 (local citation, 532).

Did appellant waive the priority of his mechanic’s lien so far as Andresen’s mortgage is concerned? This is the only question involved.

One entitled to a mechanic’s lien may waive his right thereto. By virtue of the statute, the taking of collateral security under certain conditions amounts, in effect, to a waiver of a mechanic’s lien. Section 10272, 1931 Code. In that section is this provision:

“No person shall be entitled to a mechanic’s lien who # * * during the progress of the work, shall take any collateral security on such contract (to furnish labor or material).”

Whether that statute applies to the facts in the case at bar, it is not necessary to decide. Regardless of the statute, however, the appellant may waive its mechanic’s lien so far as Andre-sen’s mortgage is concerned. Peatman v. Centerville Light, Heat & Power Co,, 105 Iowa, 1 (local citation, 8); Van Dyck Heating & Plumbing Co. v. Central Iowa B. Co., 200 Iowa, 1003 (local citation 1004). The following language may be found on page 1004 of the Van Dyck case:

“A mechanic’s lien is a right or privilege given to a contractor to protect himself against loss for material and labor furnished. It is wholly a creature of statute. We know of no reason, and none has been urged, which would prevent the contractor from waiving such a lien by contract, so as to be binding in a contest between the property owner and the original contractor. ’ ’

See also Ponder v. Safety Building & Loan Co., 59 S. W. 858 (Ky.).

Although there may be a waiver of a mechanic’s lien, yet the contract so stipulating must be clear, satisfactory, unambiguous, and free from doubt. All doubts must be resolved in favor of the lien. Van Dyck Heating & Plumbing Co. v. Central *1317 Iowa B. Co., (200 Iowa 1003), supra; Carson-Payson Co. v. Cleveland C. C. & St. L. Railway Co., 105 N. E. 503 (Ind.); Masson v. Indiana Lighting Fixture Co., 100 N. E. 875 (Ind.); Concord Apartment House Co. v. O’Brien, 81 N. E. 1076 (Ill.); Davis v. LaCrosse Hospital Association, 99 N. W. 351 (Wis.); Carl Miller Lumber Co. v. Meyer, 196 N. W. 840 (Wis.).

While in the Van Dyck Case (200 Iowa 1003), supra, it is stated that the contract for waiver must -be explicit, yet the word “explicit” was not there used as synonymous with “express.” This conclusion is apparent when considering the portion of the opinion in question with the remainder thereof, and reading the cases cited in support of the rule. Webster’s New International Dictionary indicates that explicit may mean: “Not obscure or ambiguous; * * * having no disguised meaning or reservation.” Such definition of explicit thus expressed in the dictionary is in éffect laid down- as the basis for a waiver of a mechanic’s lien in the cases cited in support of the Van Dyck case (200 Iowa 1003), supra. To illustrate, it is said in Davis v. LaCrosse Hospital Association (99 N. W. 351), supra; reading on page 352: -

“A builder may waive his right to the lien remedy given by statute, and does so by agreeing not to exercise such right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joyce Lumber Co. v. Marshalltown Construction League
283 N.W. 912 (Supreme Court of Iowa, 1939)
Bankers Trust Co. v. Economy Coal Co.
276 N.W. 16 (Supreme Court of Iowa, 1937)
Fullerton Lumber Co. v. Miller
252 N.W. 760 (Supreme Court of Iowa, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
241 N.W. 696, 213 Iowa 1313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eclipse-lumber-co-v-bitler-iowa-1932.