Opinion

Mr. Justice Carter

delivered the opinion of the court:

It is claimed by appellant that the contract was improperly admitted in evidence under the common counts. It is well established that where a contract has been performed and it only remains to pay the contract price for labor or property, the plaintiff may sue and recover under the common counts, and that the agreement may be read in evidence for the purpose of showing its terms and to recover damages. (Adlard v. Muldoon, 45 Ill. 193; 1 Chitty’s Pl.— 14th Am. ed.—340.) Counsel for appellant admits this proposition without question, but strongly insists that it does not apply here because in this case the contract was not fully performed. With this contention we do not agree. The proof shows that the final certificate was issued by. the appellant’s superintendent after conference between himself, appellee and Rolfe, the secretary of the company; that appellee returned the certificate to Rolfe, and that is the last he knew of it. He did not remember whether Rolfe returned it or not. Appellee testified that he made a search among his papers and cound not find it. Rolfe stated in his testimony that such a certificate was issued, and agreed with the testimony of the appellee as to the amount it showed as due. In 1898 attorney W. W. Augur, representing some of the creditors of O’Brien, called on Rolfe, at that time manager and secretary of appellant company, to ascertain the exact amount due O’Brien. Rolfe gave to Augur the following certificate:

“This is to certify that a final certificate for $4568 was issued by the Concord Apartment House Company in favor of W. D. O’Brien, August 10th, A. D. 1896.
A. A. Rolfe, Secy."

If it was error to admit this as a part of appellee’s testimony given in chief it did not in any way harm appellant, because Rolfe afterward took the stand and admitted the truth of this written statement. The certificate having been lost it was proper to prove its contents. The fact that it was lost did not change the rights or relations of the parties nor in any way affect the validity of the certificate. (Arnold v. Bournique, 144 Ill. 132.) There was proof tending to show not only the form but the substance of this lost certificate, and it seems to have been in substantial compliance with the law and the contract.

It is urged that appellee failed to complete his contract as to the automatic regulator, fusible plugs and coil of galvanized iron pipe, and that the brickwork about the boilers was not in accordance with the specifications and contract. On all of these questions there was a conflict of evidence, hence, as this court has repeatedly held, the finding of the lower court and the judgment of the Appellate Court on such questions are conclusive.

Appellee admitted that he had made slight changes from the specifications in carrying out the contract but claimed that these changes were authorized and directed by the superintendent, and that although no written order was given, under the first article of the contract the superintendent acted as agent of said owner and hence had authority to permit these alterations. After the amount due has been fixed by agreement of the parties and set out in the final certificate it would be manifest injustice to hold that the contractor could not recover because he had no written order from the superintendent for the modifications. The contract in this respect was as binding upon the superintendent, and through him upon the owner, as it was upon the contractor. Either party could waive the requirements as to written notice. On this record the appellant clearly waived any right to insist on this point.

Appellant contends that even on this state of the record, under the decision of the court in Hart v. Carsley Manf. Co. 221 Ill. 444, the contract was improperly admitted in evidence, and no recovery could be had on the common counts because all of the conditions precedent were not complied with. In this last case the final certificate was not issued as required by the contract, and this was held to be a condition precedent. Under the reasoning in that case, had the final certificate been issued a recovery could have been had under the common counts. This court held in Catholic Bishop of Chicago v. Bauer, 62 Ill. 188, that “when there has been full performance [of the contract] and nothing remains to be done but the payment of the money, or where there has been only part performance and the remainder has been waived or prevented and the work performed has been accepted, then, in either case, recovery may be had for the contract price of the service performed, under an indebitatus assumpsit.” This decision on this point has been quoted with approval by this court in Mount Hope Cemetery Ass. v. Weidenmann, 139 Ill. 67, O’Brien v. Sexton, 140 id. 517, Foster v. McKeown, 192 id. 339, and Rubens v. Hill, 213 id. 523. In Fowler v. Deakman, 84 Ill. 130, this court held that although there was a special count which did not in some respects conform to the proof, the introduction of a written statement of the architect showing why he had not given a final certificate was a sufficient excuse for not procuring the certificate, and that this statement was admissible under the common counts. In harmony on this point with the decisions just quoted are Shepard v. Mills, 173 Ill. 223, and Evans v. Howell, 211 id. 85. We do not think the decisions of Hart v. Carsley Manf. Co. supra, City of Peoria v. Construction Co. 169 Ill. 36, and Parmly v. Farrar, 169 id. 606, cited by appellant, in any way conflict with this conclusion. It was not error to admit the contract or to permit judgment to be entered under the common counts.

Free access — add to your briefcase to read the full text and ask questions with AI

Concord Apartment House Co. v. O'Brien, 81 N.E. 1038, 228 Ill. 360, 1907 Ill. LEXIS 3213 (Ill. 1907).

81 N.E. 1038 (Concord Apartment House Co. v. O'Brien) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Morton Buildings, Inc. v. Witvoet
413 N.E.2d 202 (Appellate Court of Illinois, 1980)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
Strom v. Lipschultz
282 N.E.2d 257 (Appellate Court of Illinois, 1972)
Halvorson v. Blue Mountain Prune Growers Cooperative
217 P.2d 254 (Oregon Supreme Court, 1950)
Halvorson v. Blue Mt. Prune Growers Co-Op.
217 P.2d 254 (Oregon Supreme Court, 1949)
Toledo, P. & W. R. R. v. Peoria & P. Union Ry. Co.
72 F.2d 745 (Seventh Circuit, 1934)
Foley & Co. v. Excelsior Stove & Manufacturing Co.
265 Ill. App. 78 (Appellate Court of Illinois, 1932)
Hardy v. Dobler
248 Ill. App. 361 (Appellate Court of Illinois, 1928)
White v. City of Ottawa
230 Ill. App. 493 (Appellate Court of Illinois, 1923)
Sanford Coal Co. v. Wisconsin Bridge & Iron Co.
293 F. 735 (Seventh Circuit, 1923)
McWilliams v. Eldred Drainage & Levee District
229 Ill. App. 91 (Appellate Court of Illinois, 1923)
American Spirits Manufacturing Co. v. Western Manufacturing & Oil Co.
210 Ill. App. 454 (Appellate Court of Illinois, 1918)
Northwestern Marble & Tile Co. v. Swenson
166 N.W. 406 (Supreme Court of Minnesota, 1918)
Ferguson v. Christensen
59 Colo. 42 (Supreme Court of Colorado, 1915)
Wheeler, Osgood Co. v. Fidelity & Deposit Co.
139 P. 53 (Washington Supreme Court, 1914)
Peterson v. Pusey
86 N.E. 692 (Illinois Supreme Court, 1908)
Expanded Metal Fireproofing Co. v. Boyce
84 N.E. 275 (Illinois Supreme Court, 1908)