Northwestern Marble & Tile Co. v. Swenson

166 N.W. 406, 139 Minn. 365, 1918 Minn. LEXIS 489
CourtSupreme Court of Minnesota
DecidedFebruary 15, 1918
DocketNo. 20,739
StatusPublished
Cited by11 cases

This text of 166 N.W. 406 (Northwestern Marble & Tile Co. v. Swenson) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern Marble & Tile Co. v. Swenson, 166 N.W. 406, 139 Minn. 365, 1918 Minn. LEXIS 489 (Mich. 1918).

Opinion

Hallam, J.

Plaintiff, in its complaint, alleged a cause of action to recover the reasonable value of labor and material furnished to defendant, at his instance and request. Defendant, in his answer, admitted that plaintiff furnished certain labor and material to defendant, but alleged that the same were furnished under a written contract which the plaintiff failed to fully perform. Plaintiff replied, admitting that the labor and material were furnished under a written contract and alleged the contract was fully performed.

When the case came on for trial plaintiff ignored the admitted contract and offered proof of furnishing the work and material and of the reasonable value thereof. The trial court repeatedly admonished plaintiff’s counsel that, since the work was done under an ■ agreed contract, it could recover only on proof of its performance, but counsel declined to offer the contract in evidence or to prove that it had been performed. At the conclusion of plaintiff’s testimony the court dismissed the case, but later granted a new trial. Defendant appeals from this order.

1. There was no difficulty with the pleadings. Under the allegations of quantum meruit in the complaint, plaintiff (1) might prove work and material furnished at the instance of defendant without express contract, and recover the reasonable value, or (2) it might prove that there was an express contract and that it had fully performed on its part, and recover the amount due. Larson v. Schmaus, 31 Minn. 410, 18 N. W. 273. While there is some confusion in the-early cases in this state as to the second proposition, any doubt that ever existed is well cleared up in Meyer v. Saterbak, 128 Minn. 304, 150 N. W. 901. This is the prevailing rule. 40 Cyc. 2835. Scott v. Congdon, 106 Ind. 268, 6 N. E. 625; Atkins v. County of Barnstable, 97 Mass. 428; Concord Apartment House Co. v. O’Brien, 228 Ill. 360, 367, 81 N. E. 1038. Even the common law system of procedure indulged this liberality. 1 Chitty, Pl. (16th Am. ed.) *357-359; Gordon v. Martin, Fitzg. 302; Alcorn v. Westbrook, Wilson, 115; Felton v. Dickinson, 10 Mass. 287; Frazer v. Gregg, 20 Ill. 300. Over 100 years ago, Justice Story recognized this doctrine as “incontrovertibly settled.” Bank of Columbia v. Patterson, 7 Cranch, 299, 3 L. ed. 351. The amount of recovery in such eases is the contract price. Kruta v. Lough, 131 Minn. 13, 154 N. W. [367]*367514; Theodore Wetmore & Co. v. Thurman, 121 Minn. 352, 356, 141 N. W. 481; Dermott v. Jones, 2 Wall. 1, 17 L. ed. 762; Hubbard v. Investment Co. 119 U. S. 696, 701, 7 Sup. Ct. 353, 30 L. ed. 548; Williams v. Sherman, 7 Wend. 109; Fuchs v. Standard Thermometer Co. 178 Mich. 37, 144 N. W. 484. It follows that there was no departure in the reply, for the reply was simply a particular allegatioh or admission of certain 'facts which plaintiff could have proven under the general allegation of the complaint.

2. But these rules, calculated to simplify pleading and eliminate technicality in procedures, were never intended to abrogate contract obligations. It is now, as always, the law that’ where partie's enter into an express contract they are bound by its terms. Neither party can, as plaintiff claims, “lay it aside” and proceed as though no contract had ever been made. The contract determines the rights of the- parties, and if the plaintiff either alleges or admits the existence of an express contract it must show a right of recovery consistent with its terms. This is part of its cause of action. This is true whether it.relies on full performance by itself or on a breach of the other party, or on any other condition that may give it a right of recovery. Hammond v. Dunbar, 41 Mass. 172, 180. Had it not appeared in this case that there was an express contract, plaintiff’s proof that it furnished work and material of a given value to defendant at his instance and request, would have made out a prima facie case, but since -the existence of an express contract did appear by the allegation of the defendant and the admission of plaintiff, and since, in its pleadings, plaintiff relied on full performance, it could only recover upon showing that the contract was fully performed. Plaintiff did not offier to do so. The action was properly dismissed- and it was error to grant a new trial.

Order reversed.

Holt, J., took no part.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Langford Tool & Drill Co. v. The 401 Group, LLC
Court of Appeals of Minnesota, 2015
Sallblad v. Burman
29 N.W.2d 673 (Supreme Court of Minnesota, 1947)
Schimmelpfennig v. Gaedke
27 N.W.2d 416 (Supreme Court of Minnesota, 1947)
Benedict v. Pfunder
237 N.W. 2 (Supreme Court of Minnesota, 1931)
Hawley v. Town of Stuntz
227 N.W. 358 (Supreme Court of Minnesota, 1929)
Marshall v. Anderson
207 N.W. 193 (Supreme Court of Minnesota, 1926)
Ritchell v. Remington
198 N.W. 813 (Supreme Court of Minnesota, 1924)
Wallace Plumbing Co. v. Dillon
205 P. 950 (Supreme Court of Colorado, 1922)
James E. Carlson, Inc. v. Babler
174 N.W. 824 (Supreme Court of Minnesota, 1919)
State v. Gilbert
169 N.W. 790 (Supreme Court of Minnesota, 1918)
State v. Freerks
168 N.W. 23 (Supreme Court of Minnesota, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
166 N.W. 406, 139 Minn. 365, 1918 Minn. LEXIS 489, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-marble-tile-co-v-swenson-minn-1918.