Palmer v. Meriden Britannia Co.

59 N.E. 247, 188 Ill. 508
CourtIllinois Supreme Court
DecidedDecember 20, 1900
StatusPublished
Cited by35 cases

This text of 59 N.E. 247 (Palmer v. Meriden Britannia Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer v. Meriden Britannia Co., 59 N.E. 247, 188 Ill. 508 (Ill. 1900).

Opinion

Mr. Justice Magruder

delivered the opinion of the court:

This action is brought to recover the sum of $5000.00, which, by the terms of the lease, the lessors were to pay to the lessee at the end of the term for the building erected upon the premises, with its fixtures and appurtenances, “on being put in possession thereof.” Hotchkin and Palmer were'to pay said sum of $5000.00 “at the end of the said term, if the said lessee shall have duly fulfilled all its covenants and agreements herein contained, and if the said building, to be erected as aforesaid and maintained or renewed as aforesaid, shall remain on such ground in the condition above stipulated for.” It is not denied by the appellant, that the appellee paid all the rent during the term called for by the terms of the lease; nor is it denied by the appellant that, at the end of the term, the appellant was put in possession of the building, costing over $30,000.00, which appellee erected upon the premises during the term. The defense, set up by the appellant, is that the building", erected upon the premises by the appellee, was not, in certain particulars, such a building as the terms of the lease called for, and that, therefore, the appellee did not fulfill all its covenants and agreements, and that the building did not remain upon the ground at the end of the term in the condition stipulated for. The contention of the appellant is, that the agreement of the appellee to construct a building, which should be internally finished in a particular way, was a condition precedent to the right of appellee to recover the sum of $5000.00, and that, appellee, not having performed the condition precedent named in the covenant, is not- entitled to be paid the sum named for the building erected by it.

The respects, in which the building is said to have fallen short of the requirements mentioned in the lease, are that, internally, the building was constructed with center columns, as supports for the ceilings, when the same could'have been constructed without such columns at an extra cost not exceeding $1500.00; that the whole of the basement of the building was not cemented on the bottom with Portland cement; and that the walls of the basement and of the fourth, fifth and sixth floors were not lathed and plastered.

First — It is true, that the building was constructed with center columns, and the question, whether it could have been constructed without center columns at a cost not exceeding $1500.00, is a question of fact. The case was tried below before the court without a jury, and the testimony upon this question of fact is conflicting. The testimony, introduced by the appellee, tends to show that the building could not have been constructed without center columns for less than an extra cost of between $3000.00 and $4000.00, while the testimony, ■ introduced by the appellant, tends to show .that it could have been constructed without such columns at a cost of less than $1500.00. The very language of the lease itself upon this subject implies, that the cost of construction without columns would be greater than the cost of such construction with columns. Inasmuch as there was evidence, tending to sustain the contention of the appellee upon this subject, and inasmuch as all the evidence introduced on both sides was conflicting, the finding of the court below on this question of fact will not be disturbed.

The trial court held as law in the decision of the case the following propositions, submitted to it by the appellant: “The construction of the building with center columns was not a substantial performance of the contract to construct a building without center columns, unless the construction of the building without center columns would have cost more than $1500.00 additional;” “The burden of proof is on the plaintiff to show that the construction of the building without center columns would have cost more than $1500.00, in addition to the cost of the building actually erected.” The court below, after holding these propositions to be law in the decision of the case, could not have found the issues for the appellee without at the same time finding from the evidence, that the construction of the building without center columns would have cost more than the $1500.00 named in the lease. In other words, the trial court found that the omission of center supporting columns would have entailed an extra cost, exceeding $1500.00. The Appellate Court has affirmed the judgment of the trial court, and this judgment of affirmance has settled all the disputed questions of fact in the case. (Wrought Iron Bridge Co. v. Comrs. of Highways, 101 Ill. 518).

Upon the question, whether the third and fourth stories of the building were lathed and plastered or not, there is also a conflict of testimony. The evidence, introduced by the appellee, tends to show that the third and fourth stories were lathed and plastered before the expiration of the term of the lease on April 30,1895. The findings of the lower court are conclusive-upon this question of fact. As to the lathing and plastering of the sixth floor, which was a loft used for storage, it may be observed that the lease did not require the erection of a building six stories high, but only of a building five stories high. As a matter of fact, appellee constructed a building one story higher than the lease required it to do. The agreement in the lease, that “all walls and ceilings will be properly lathed and plastered,” refers to all walls and ceilings of a building five stories in height. Hence, there really was no agreement on the part of appellee to lath and plaster the sixth story of any building. As we read the evidence, however, there is testimony tending to show that the sixth floor was lathed and plastered, and, upon the question of fact whether it was so lathed and plastered or not, the judgments of the lower courts are conclusive;

It is claimed, however, by the appellant, that the court below improperly permitted the appellee to introduce hearsay evidence upon the question, whether the omission of the center supporting columns entailed an extra cost of over $1500.00. The architect, who constructed the building for appellee, was dead at the time of the trial of the present case. The agent of the appellee testified, that such deceased architect made an estimate of the cost of construction without columns, and that his estimate made the extra cost about $4000.00. The hearsay testimony complained of is the statement of appellee’s agent as to the estimate made by the deceased architect. It may be admitted, that this testimony was incompetent as being hearsay evidence, but there was other evidence,besides the objectionable testimony, to the effect that the extra cost would have exceeded $1500.00. As the trial was before the court without a jury, the fact, that some incompetent testimony was admitted, is no ground of reversal, when the record shows that there was competent testimony sustaining the finding of the •court. “Where a cause is tried by the court without a jury, and there is enough of unobjectionable testimony to sustain the finding of the court, it will not be disturbed notwithstanding the reception of the incompetent evidence, as the same harmful effect does not follow in such a case, as when before a jury.” (Schroeder v. Harvey, 75 Ill. 638; Partridge v. Ryan, 134 id. 247).

Second — What has already been said disposes of the complaints made against the construction of the building, except the provisions relating to the basement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greggs USA, Inc. v. 400 East Professional Associates, LP
2021 IL App (1st) 200959 (Appellate Court of Illinois, 2021)
Sahadi v. Continental Illinois National Bank
706 F.2d 193 (Seventh Circuit, 1983)
Watson Lumber Co. v. Mouser
333 N.E.2d 19 (Appellate Court of Illinois, 1975)
Perry v. Waddelow
145 F. Supp. 349 (E.D. Illinois, 1956)
Zeta Building Corp. v. Garst
97 N.E.2d 331 (Illinois Supreme Court, 1951)
Arrow Petroleum Co. v. Johnston
162 F.2d 269 (Seventh Circuit, 1947)
Shapleigh Hardware Co. v. Enterprise Foundry Co.
305 Ill. App. 180 (Appellate Court of Illinois, 1940)
Fargo Glass & Paint Co. v. Smith
266 N.W. 100 (North Dakota Supreme Court, 1936)
Foreman State Trust & Savings Bank v. Tauber
180 N.E. 827 (Illinois Supreme Court, 1932)
Moss v. Best Knitting Mills
130 S.E. 635 (Supreme Court of North Carolina, 1925)
Clark v. Clark
204 N.W. 936 (Supreme Court of Minnesota, 1925)
Alderson v. Republican-Courier Co.
221 P. 544 (Montana Supreme Court, 1923)
Rosengren v. Manufacturers National Bank
220 Ill. App. 608 (Appellate Court of Illinois, 1921)
Henry v. Excelsior Springs Mineral Water & Bottling Co.
211 S.W. 9 (Supreme Court of Missouri, 1919)
Connelly v. Wallin
181 Ill. App. 212 (Appellate Court of Illinois, 1913)
Susswein v. Pennsylvania Steel Co.
184 F. 102 (U.S. Circuit Court for the District of Southern New York, 1910)
Worthing v. Hall
153 Ill. App. 587 (Appellate Court of Illinois, 1910)
Harrison v. Thackaberry
154 Ill. App. 246 (Appellate Court of Illinois, 1910)
Freet v. American Electrical Supply Co.
152 Ill. App. 205 (Appellate Court of Illinois, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
59 N.E. 247, 188 Ill. 508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-v-meriden-britannia-co-ill-1900.